up_reraStatus: Completed
CASE ID: 0901126002762019

Appellant / Complainant

Shaileshwar Nath Singh

VS

Respondent

Lucknow Development Authority

Disputed Amount

49,50,000

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

37 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002762019 by Shaileshwar Nath Singh against Lucknow Development Authority before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferMaintenance & Utility Disputes
2
Stage 117/07/2023

for delivery of Judgment/Order

The Tribunal modified the Regulatory Authority's order to grant the appellant interest at MCLR+1% for the entire delay period from 14.09.2014 until the issuance of the Completion Certificate on 17.02.2020, rejecting the developer's claim that shifting high-tension wires constituted a force majeure event.

3
Stage 206/07/2023

Hearing

The appellant challenges the Regulatory Authority's decision to grant a two-year extension for possession due to high-tension wire shifting, seeking interest for the delay period from 14.09.2014 until the receipt of the completion certificate on 17.02.2020.

4
Stage 329/05/2023

Hearing

The Tribunal has adjourned the matter to 06.07.2023 for orders/hearing based on a joint request from both the appellant and the respondent's counsel.

5
Stage 421/04/2023

Hearing

The Tribunal adjourned the matter due to the absence of respondent counsel and issued a warning that if no one appears on the next date, the case will proceed ex-parte against the Lucknow Development Authority.

6
Stage 517/03/2023

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to his absence from the station and rescheduled the hearing for 21.04.2023.

7
Stage 608/02/2023

Hearing

No text available.

8
Stage 722/12/2022

Hearing

This text represents the header/caption of an appellate order from the U.P. Real Estate Appellate Tribunal regarding Appeal-268/2019 between Shaileshwar Nath Singh and Lucknow Development Authority; however, no substantive ruling or directive is contained in this specific excerpt.

9
Stage 812/10/2022

Part Heard

The appellant challenges a Regulatory Authority order regarding the exclusion of a two-year period for interest calculations on delayed possession; the Tribunal has heard arguments from both parties and reserved its judgment.

10
Stage 906/09/2022

Hearing

The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the hearing for 12.10.2022.

11
Stage 1008/08/2022

Final Hearing

The Tribunal heard arguments regarding interest on a delay period but adjourned the matter to 06.09.2022 for further hearing as the respondent's counsel was unable to argue due to the absence of the case file.

12
Stage 1112/07/2022

Final Hearing

The Tribunal directed that the appeal be listed before Bench No. 2 on 08.08.2022 to determine if the matter is part-heard and to proceed accordingly.

13
Stage 1220/05/2022

Final Hearing

The Tribunal directed both parties to file and exchange concise written arguments with supporting judgments and scheduled the next hearing for 12.07.2022 regarding the appellant's claims for interest on delayed possession and benefits from increased flat density.

14
Stage 1319/04/2022

Final Hearing

The Tribunal granted an application for adjournment and rescheduled the hearing of Appeal-268/2019 to 20.05.2022.

15
Stage 1402/03/2022

Final Hearing

The Tribunal directed the parties to file a list of dates and events along with cited case laws and scheduled the matter for final arguments on 19.04.2022.

16
Stage 1519/01/2022

Final Hearing

No text available.

17
Stage 1607/01/2022

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the hearing for 19.01.2022.

18
Stage 1714/12/2021

Final Hearing

The Tribunal granted the appellant one week to review documents filed by the respondent and directed that a response be filed via the e-portal before the next hearing on 07.01.2022.

19
Stage 1825/11/2021

Final Hearing

The Tribunal granted the respondent one week to comply with a previous order dated 16.10.2020 and scheduled the appeal for hearing on 14.12.2021.

20
Stage 1928/10/2021

Hearing

The Tribunal adjourned the appeal to 25.11.2021 and directed the respondent to ensure compliance with the previous order dated 16.10.2020 in the interim.

21
Stage 2001/10/2021

Hearing

The Tribunal granted the respondent's counsel one week to comply with the previous order dated 16.10.2020 and scheduled the next hearing for 28.10.2021.

22
Stage 2115/09/2021

Hearing

The Tribunal granted the respondent one week's time to ensure compliance with a previous order dated 16.10.2020 and scheduled the next hearing for 01.10.2021.

23
Stage 2230/04/2021

Hearing

No text available.

24
Stage 2307/04/2021

Hearing

No text available.

25
Stage 2417/03/2021

Hearing

The Tribunal granted the respondent a one-week extension to respond to a previous query and scheduled the next hearing for April 7, 2021.

26
Stage 2523/02/2021

Hearing

The Tribunal directed the Lucknow Development Authority to provide information regarding possession and conveyance deed formalities to the appellant and granted a final one-week deadline for the respondent to respond to previous queries regarding flat enhancement and common area cost calculations.

27
Stage 2608/02/2021

For Order

The appeal was adjourned to 23.02.2021 following a request for adjournment by the respondent's counsel due to illness.

28
Stage 2719/01/2021

Hearing

The Tribunal issued a notice to the respondent for 08.02.2021 and directed the appellant to serve the order via email, noting that the matter may proceed ex-parte if no one appears on the next date.

29
Stage 2814/12/2020

Hearing

No text available.

30
Stage 29Final Ruling Order

Tribunal Order #0901126002762019-17-07-2023

The Tribunal modified the Regulatory Authority's order to grant the appellant interest at MCLR+1% for the entire delay period from 14.09.2014 until the issuance of the Completion Certificate on 17.02.2020, rejecting the developer's claim that shifting high-tension wires constituted a force majeure event.

31
Stage 30Interim Order

Tribunal Order #0901126002762019-06-07-2023

The appellant challenges the Regulatory Authority's decision to grant a two-year extension for possession due to high-tension wire shifting, seeking interest for the delay period from 14.09.2014 until the receipt of the completion certificate on 17.02.2020.

32
Stage 31Interim Order

Tribunal Order #0901126002762019-12-10-2022

The appellant challenges a Regulatory Authority order regarding the exclusion of a two-year period for interest calculations on delayed possession; the Tribunal has heard arguments from both parties and reserved its judgment.

33
Stage 32Interim Order

Tribunal Order #0901126002762019-28-10-2021

The Tribunal adjourned the appeal to 25.11.2021 and directed the respondent to ensure compliance with the previous order dated 16.10.2020 in the interim.

34
Stage 33Interim Order

Tribunal Order #0901126002762019-23-02-2021

The Tribunal directed the Lucknow Development Authority to provide information regarding possession and conveyance deed formalities to the appellant and granted a final one-week deadline for the respondent to respond to previous queries regarding flat enhancement and common area cost calculations.

35
Stage 34Interim Order

Tribunal Order #0901126002762019-21-04-2023

The Tribunal adjourned the matter due to the absence of respondent counsel and issued a warning that if no one appears on the next date, the case will proceed ex-parte against the Lucknow Development Authority.

36
Stage 35Interim Order

Tribunal Order #0901126002762019-20-05-2022

The Tribunal directed both parties to file and exchange concise written arguments with supporting judgments and scheduled the next hearing for 12.07.2022 regarding the appellant's claims for interest on delayed possession and benefits from increased flat density.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal modified the Regulatory Authority's order to grant the appellant interest at MCLR+1% for the entire delay period from 14.09.2014 until the issuance of the Completion Certificate on 17.02.2020, rejecting the developer's claim that shifting high-tension wires constituted a force majeure event. Awarded in favor of Partial. Awarded interest rate: MCLR + 1%.

Disposal Winner: PartialInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal modified the Regulatory Authority's order to grant the appellant interest at MCLR+1% for the entire delay period from 14.09.2014 until the issuance of the Completion Certificate on 17.02.2020, rejecting the developer's claim that shifting high-tension wires constituted a force majeure event.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR + 1%

Interest Period

from 14.09.2014 till 17.02.2020

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 11(4)(d)Section 19(6)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • In Person

Respondent Advocate(s)

  • Abhishek Khare

Official RERA Tribunal Orders (7)

FINAL_ORDEROrder ID: 0901126002762019-17-07-2023

The Tribunal modified the Regulatory Authority's order to grant the appellant interest at MCLR+1% for the entire delay period from 14.09.2014 until the issuance of the Completion Certificate on 17.02.2020, rejecting the developer's claim that shifting high-tension wires constituted a force majeure event.

INTERIM_ORDEROrder ID: 0901126002762019-06-07-2023

The appellant challenges the Regulatory Authority's decision to grant a two-year extension for possession due to high-tension wire shifting, seeking interest for the delay period from 14.09.2014 until the receipt of the completion certificate on 17.02.2020.

INTERIM_ORDEROrder ID: 0901126002762019-12-10-2022

The appellant challenges a Regulatory Authority order regarding the exclusion of a two-year period for interest calculations on delayed possession; the Tribunal has heard arguments from both parties and reserved its judgment.

INTERIM_ORDEROrder ID: 0901126002762019-28-10-2021

The Tribunal adjourned the appeal to 25.11.2021 and directed the respondent to ensure compliance with the previous order dated 16.10.2020 in the interim.

INTERIM_ORDEROrder ID: 0901126002762019-23-02-2021

The Tribunal directed the Lucknow Development Authority to provide information regarding possession and conveyance deed formalities to the appellant and granted a final one-week deadline for the respondent to respond to previous queries regarding flat enhancement and common area cost calculations.

INTERIM_ORDEROrder ID: 0901126002762019-21-04-2023

The Tribunal adjourned the matter due to the absence of respondent counsel and issued a warning that if no one appears on the next date, the case will proceed ex-parte against the Lucknow Development Authority.

INTERIM_ORDEROrder ID: 0901126002762019-20-05-2022

The Tribunal directed both parties to file and exchange concise written arguments with supporting judgments and scheduled the next hearing for 12.07.2022 regarding the appellant's claims for interest on delayed possession and benefits from increased flat density.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →