up_reraStatus: Completed
CASE ID: 0901126002702019

Appellant / Complainant

Shruti Mittal, Amit Mittal

VS

Respondent

Upptal Chadha Hi-Tech Developers Pvt. Ltd.

Developer Firm

upptal chadha hi-tech developers pvt. ltd.

Disputed Amount

5,79,570

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional MisrepresentationMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

17 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002702019 by Shruti Mittal, Amit Mittal against Upptal Chadha Hi-Tech Developers Pvt. Ltd. before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestPromotional MisrepresentationMaintenance & Utility Disputes
2
Stage 115/03/2022

for delivery of Judgment/Order

The Tribunal set aside the Regulatory Authority's non-speaking order and remanded the matter back to RERA for a fresh decision, ruling that the developer failed to provide promised amenities despite collecting various charges.

3
Stage 221/10/2021

Hearing

The Tribunal heard arguments from both parties regarding an appeal against a RERA order, specifically questioning the respondent about project amenities such as roads and drainage, before reserving judgment.

4
Stage 317/09/2021

Hearing

The Tribunal adjourned the matter to 21.10.2021 due to the respondent's repeated non-appearance and issued a warning that the case may be heard ex-parte on the next date.

5
Stage 423/04/2021

Final Hearing

No text available.

6
Stage 508/04/2021

Final Hearing

No text available.

7
Stage 618/03/2021

Hearing

The Tribunal issued a show cause notice to the respondent's counsel for repeated non-appearance, warning that failure to explain may result in a referral to the U.P. Bar Council for professional misconduct.

8
Stage 708/03/2021

Hearing

The Tribunal adjourned the matter to 18.03.2021 for final hearing due to the absence of the respondent's counsel.

9
Stage 824/02/2021

For Order

The appeal is adjourned due to a call for lawyers to abstain from work by the Oudh Bar Association, with the matter rescheduled for 08.03.2021.

10
Stage 911/02/2021

For Order

The Tribunal granted an adjournment requested by the respondent's counsel due to injury and rescheduled the hearing for 24.02.2021.

11
Stage 1028/01/2021

For Order

The Tribunal granted the appellant's counsel three days to file a reply to the respondent's objections and scheduled the next hearing for 11.02.2021.

12
Stage 1112/01/2021

Hearing

No text available.

13
Stage 1208/12/2020

Hearing

No text available.

14
Stage 13Final Ruling Order

Tribunal Order #0901126002702019-15-03-2022

The Tribunal set aside the Regulatory Authority's non-speaking order and remanded the matter back to RERA for a fresh decision, ruling that the developer failed to provide promised amenities despite collecting various charges.

15
Stage 14Interim Order

Tribunal Order #0901126002702019-21-10-2021

The Tribunal heard arguments from both parties regarding an appeal against a RERA order, specifically questioning the respondent about project amenities such as roads and drainage, before reserving judgment.

16
Stage 15Interim Order

Tribunal Order #0901126002702019-18-03-2021

The Tribunal issued a show cause notice to the respondent's counsel for repeated non-appearance, warning that failure to explain may result in a referral to the U.P. Bar Council for professional misconduct.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's non-speaking order and remanded the matter back to RERA for a fresh decision, ruling that the developer failed to provide promised amenities despite collecting various charges. Awarded in favor of Appellant. Awarded interest rate: 18%.

Disposal Winner: AppellantInterest Rate: 18%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's non-speaking order and remanded the matter back to RERA for a fresh decision, ruling that the developer failed to provide promised amenities despite collecting various charges.

Ruling Awarded To

Appellant

Awarded Interest Rate

18%

Interest Period

from the date of payment till entire facilities described above is provided

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 12Section 11(4)(d)Section 19(6)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saghar Mehdi

Respondent Advocate(s)

  • Bal Kishor Verma

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126002702019-15-03-2022

The Tribunal set aside the Regulatory Authority's non-speaking order and remanded the matter back to RERA for a fresh decision, ruling that the developer failed to provide promised amenities despite collecting various charges.

INTERIM_ORDEROrder ID: 0901126002702019-21-10-2021

The Tribunal heard arguments from both parties regarding an appeal against a RERA order, specifically questioning the respondent about project amenities such as roads and drainage, before reserving judgment.

INTERIM_ORDEROrder ID: 0901126002702019-18-03-2021

The Tribunal issued a show cause notice to the respondent's counsel for repeated non-appearance, warning that failure to explain may result in a referral to the U.P. Bar Council for professional misconduct.

TathyaGrid RERA Intelligence AI