up_reraStatus: Active
CASE ID: 0901126002692023

Appellant / Complainant

U.P. State Industrial Development Corporation Limited

VS

Respondent

Sunil Srivastava

Developer Firm

u.p. state industrial development corporation limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

8 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002692023 by U.P. State Industrial Development Corporation Limited against Sunil Srivastava before up_rera.

2
Stage 116/10/2024

For Order

The Tribunal has ordered that this appeal be listed only after the decision is rendered in RERA Appeal No. 37 of 2022 (U.P. State Industrial Development Authority Vs. Ankur Gupta), which has stayed the effect of related orders.

3
Stage 221/08/2023

Delay condonation

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal; it further directed that the pre-deposited amount under Section 43(5) be transferred to the U.P. RERA for disbursement to the allottee during execution proceedings.

4
Stage 303/07/2023

Delay condonation

The Tribunal granted an adjournment to the respondent on health grounds and directed them to file objections to the application for condonation of delay and the grounds of appeal within 10 days.

5
Stage 420/04/2023

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and grounds of appeal, scheduling the matter for hearing on July 3, 2023.

6
Stage 513/03/2023

Delay condonation

The Tribunal issued notice to the respondent regarding an application for condonation of delay and directed the applicant to serve the notice and appeal documents via speed-post and email.

7
Stage 6Final Ruling Order

Tribunal Order #0901126002692023-21-08-2023

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal; it further directed that the pre-deposited amount under Section 43(5) be transferred to the U.P. RERA for disbursement to the allottee during execution proceedings.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal; it further directed that the pre-deposited amount under Section 43(5) be transferred to the U.P. RERA for disbursement to the allottee during execution proceedings. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal; it further directed that the pre-deposited amount under Section 43(5) be transferred to the U.P. RERA for disbursement to the allottee during execution proceedings.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kartikey Dubey
  • Ramesh Chandra Mishra

Respondent Advocate(s)

  • Deepak Dwivedi

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126002692023-21-08-2023

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal; it further directed that the pre-deposited amount under Section 43(5) be transferred to the U.P. RERA for disbursement to the allottee during execution proceedings.

TathyaGrid RERA Intelligence AI

Need to research all rulings for u.p. state industrial development corporation limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →