up_reraStatus: Completed
CASE ID: 0901126002672023

Appellant / Complainant

U.P. State Industrial Development Corporation Limited

VS

Respondent

Manoj Awasthi

Developer Firm

u.p. state industrial development corporation limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002672023 by U.P. State Industrial Development Corporation Limited against Manoj Awasthi before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 107/05/2024

for delivery of Judgment/Order

The Tribunal dismissed 29 appeals filed by UPSIDA against RERA orders, upholding the requirement to pay delay interest at MCLR+1% and directing the transfer of pre-deposited funds to U.P. RERA for distribution to allottees.

3
Stage 225/01/2024

For Order

The court has reserved the judgment for this appeal following a previous order passed in related Appeal No. D132/2023.

4
Stage 308/01/2024

For Order

The Tribunal issued notice to the respondent to file objections within 10 days and scheduled the appeal for hearing on January 25, 2024, following a High Court remand.

5
Stage 419/07/2023

Delay condonation

The Tribunal rejected the delay condonation application and dismissed the defective appeal (Appeal No. 140/2023) via an order dated 19.07.2023.

6
Stage 505/05/2023

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for July 19, 2023.

7
Stage 620/04/2023

Delay condonation

The Tribunal granted the appellant's counsel one week to file an affidavit of service and scheduled the defective appeal for further orders on May 5, 2023.

8
Stage 713/03/2023

Delay condonation

The Tribunal acknowledges the appellant's deposit of Rs. 22,68,060/- in compliance with Section 43(5) and issues notice to the respondent regarding the application for condonation of delay, scheduling the matter for hearing on 20.04.2023.

9
Stage 8Final Ruling Order

Tribunal Order #0901126002672023-19-07-2023

The Tribunal rejected the delay condonation application and dismissed the defective appeal (Appeal No. 140/2023) via an order dated 19.07.2023.

10
Stage 9Interim Order

Tribunal Order #0901126002672023-13-03-2023

The Tribunal acknowledges the appellant's deposit of Rs. 22,68,060/- in compliance with Section 43(5) and issues notice to the respondent regarding the application for condonation of delay, scheduling the matter for hearing on 20.04.2023.

11
Stage 10Final Ruling Order

Tribunal Order #0901126002672023-07-05-2024

The Tribunal dismissed 29 appeals filed by UPSIDA against RERA orders, upholding the requirement to pay delay interest at MCLR+1% and directing the transfer of pre-deposited funds to U.P. RERA for distribution to allottees.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the delay condonation application and dismissed the defective appeal (Appeal No. 140/2023) via an order dated 19.07.2023. The Tribunal dismissed 29 appeals filed by UPSIDA against RERA orders, upholding the requirement to pay delay interest at MCLR+1% and directing the transfer of pre-deposited funds to U.P. RERA for distribution to allottees. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.

Disposal Winner: RespondentInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the delay condonation application and dismissed the defective appeal (Appeal No. 140/2023) via an order dated 19.07.2023. The Tribunal dismissed 29 appeals filed by UPSIDA against RERA orders, upholding the requirement to pay delay interest at MCLR+1% and directing the transfer of pre-deposited funds to U.P. RERA for distribution to allottees.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1%

Interest Period

from December 2016 till receipt of OC/CC or the date of offer of possession, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kartikey Dubey
  • Ramesh Chandra Mishra

Respondent Advocate(s)

  • Deepak Dwivedi

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126002672023-19-07-2023

The Tribunal rejected the delay condonation application and dismissed the defective appeal (Appeal No. 140/2023) via an order dated 19.07.2023.

INTERIM_ORDEROrder ID: 0901126002672023-13-03-2023

The Tribunal acknowledges the appellant's deposit of Rs. 22,68,060/- in compliance with Section 43(5) and issues notice to the respondent regarding the application for condonation of delay, scheduling the matter for hearing on 20.04.2023.

FINAL_ORDEROrder ID: 0901126002672023-07-05-2024

The Tribunal dismissed 29 appeals filed by UPSIDA against RERA orders, upholding the requirement to pay delay interest at MCLR+1% and directing the transfer of pre-deposited funds to U.P. RERA for distribution to allottees.

TathyaGrid RERA Intelligence AI

Need to research all rulings for u.p. state industrial development corporation limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →