Appellant / Complainant
Greater Noida Industrial Development Authority
Respondent
Bhagwat Swaroop Sharma
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126002552020 by Greater Noida Industrial Development Authority against Bhagwat Swaroop Sharma before up_rera.
Delay condonation
The Tribunal permitted the applicant to withdraw the defective appeal following an amicable settlement and directed the release of the amount deposited under Section 43(5) via RTGS after the applicant submits necessary bank details.
Delay condonation
The Tribunal adjourned the proceedings to 04.07.2023 to allow for a potential amicable settlement between the parties.
Delay condonation
The Tribunal directed the respondent to upload their objections to the digital folder and resend them to the applicant within three days due to a blank file, with the case scheduled for orders on 21.04.2023.
Delay condonation
The Tribunal granted an adjournment due to the illness of the appellant's counsel and directed the respondent to file objections within 10 days, with the case listed for orders on 15.03.2023.
Delay condonation
The Tribunal granted an adjournment request made by the appellant's counsel due to illness and rescheduled the hearing for consideration of the condonation of delay application to 07.02.2023.
Delay condonation
Upon a joint request from the counsels for both parties, the Tribunal adjourned the matter and scheduled it for further orders on 09.01.2023.
Delay condonation
The Tribunal granted an extension of time to the respondent's counsel to file a vakalatnama and objections to the delay condonation application, with a warning that failure to do so will result in the disposal of the delay application.
Delay condonation
The Tribunal directed the respondent to file their Vakalatnama, objection to the delay condonation application, and a reply to the grounds of appeal before the next hearing. The case is scheduled for 02.11.2022 for the disposal of the delay condonation application.
Delay condonation
The Tribunal scheduled the case for 23.09.2022 to consider the disposal of a delay condonation application and any related objections.
Hearing
The Tribunal directed the applicant to rectify filing errors regarding misplaced documents and ordered the issuance of notice to the respondent for a hearing on the delay condonation application scheduled for 25.08.2022.
Hearing
The Tribunal issued a fresh notice to the respondent and directed the appellant to serve the memo of appeal via speed post and email, including provisions for Dasti service.
Hearing
The Tribunal issued a notice to the respondent and directed the appellant to serve the memo of appeal via speed post, scheduling the next hearing for April 29, 2022, to address the limitation application.
Delay condonation
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections regarding the application for condonation of delay and rescheduled the hearing to 23.03.2022.
Delay condonation
The Tribunal granted an adjournment requested by the applicant and rescheduled the case to 12.01.2022 for consideration of the application for condonation of delay and its objections.
Delay condonation
The Tribunal adjourned the matter to 21.12.2021 for the disposal of a limitation application and its corresponding objection.
Delay condonation
The Tribunal granted an application for adjournment and rescheduled the case to 24.11.2021 for the disposal of a limitation application, warning that the application may be decided in the absence of counsel.
Delay condonation
The Tribunal adjourned the case to 26.10.2021 and directed both parties to exchange pleadings and file originals with the Registry at least one week before the next hearing.
Hearing
The Tribunal adjourned the defective appeal to 16.03.2021 due to an advocate strike and directed the applicant's counsel to file a reply to the respondent's objections.
Delay condonation
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and directed both parties to upload their filings to the e-portal before the next hearing on 26.02.2021.
Tribunal Order #0901126002552020-04-07-2023
The Tribunal permitted the applicant to withdraw the defective appeal following an amicable settlement and directed the release of the amount deposited under Section 43(5) via RTGS after the applicant submits necessary bank details.
Tribunal Order #0901126002552020-11-07-2022
The Tribunal directed the applicant to rectify filing errors regarding misplaced documents and ordered the issuance of notice to the respondent for a hearing on the delay condonation application scheduled for 25.08.2022.
Tribunal Disposal & Final Award Ruling
The Tribunal permitted the applicant to withdraw the defective appeal following an amicable settlement and directed the release of the amount deposited under Section 43(5) via RTGS after the applicant submits necessary bank details. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal permitted the applicant to withdraw the defective appeal following an amicable settlement and directed the release of the amount deposited under Section 43(5) via RTGS after the applicant submits necessary bank details.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Ajai Kumar Gupta
- Rishindra Vikram Singh
Respondent Advocate(s)
- Pradeep Kumar
Official RERA Tribunal Orders (2)
The Tribunal permitted the applicant to withdraw the defective appeal following an amicable settlement and directed the release of the amount deposited under Section 43(5) via RTGS after the applicant submits necessary bank details.
The Tribunal directed the applicant to rectify filing errors regarding misplaced documents and ordered the issuance of notice to the respondent for a hearing on the delay condonation application scheduled for 25.08.2022.