Appellant / Complainant
Archana Tyagi
Respondent
Greater Noida Industrial Development Authority
₹27,99,317
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126002542019 by Archana Tyagi against Greater Noida Industrial Development Authority before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal set aside the Regulatory Authority's order directing possession and instead ordered the respondent to refund the appellant's entire deposited amount with interest at the rate of MCLR+1% due to project delays.
Hearing
The Tribunal issued notice on the application for condonation of delay and directed the parties to exchange objections and replies regarding the delay before the next hearing scheduled for 24.03.2021.
For Order
The Tribunal adjourned the appeal to a later date after the respondent's counsel requested to file an additional reply and was unprepared to argue the matter on merits.
Further Order
The Tribunal granted a request from the counsels of both parties to adjourn the appeal and rescheduled the matter for hearing on 17.02.2021.
Tribunal Order #0901126002542019-23-09-2021
The Appellate Tribunal set aside the Regulatory Authority's order directing possession and instead ordered the respondent to refund the appellant's entire deposited amount with interest at the rate of MCLR+1% due to project delays.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal set aside the Regulatory Authority's order directing possession and instead ordered the respondent to refund the appellant's entire deposited amount with interest at the rate of MCLR+1% due to project delays. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal set aside the Regulatory Authority's order directing possession and instead ordered the respondent to refund the appellant's entire deposited amount with interest at the rate of MCLR+1% due to project delays.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1%
Interest Period
from the date of deposit till the actual date of payment
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Sharad Tyagi
Respondent Advocate(s)
- Rajesh Chadha
Official RERA Tribunal Orders (1)
The Appellate Tribunal set aside the Regulatory Authority's order directing possession and instead ordered the respondent to refund the appellant's entire deposited amount with interest at the rate of MCLR+1% due to project delays.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.