up_reraStatus: Completed
CASE ID: 0901126002302019

Appellant / Complainant

Bishnu Kumar Agarwal HUF

VS

Respondent

Himalaya Realestate Pvt. Ltd.

Developer Firm

himalaya realestate pvt. ltd.

Disputed Amount

28,21,220

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Refund of InvestmentDelay Compensation / InterestUnfair Cancellation & Forfeiture

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002302019 by Bishnu Kumar Agarwal HUF against Himalaya Realestate Pvt. Ltd. before up_rera.

Refund of InvestmentDelay Compensation / InterestUnfair Cancellation & Forfeiture
2
Stage 131/05/2023

for delivery of Judgment/Order

The Appellate Tribunal set aside the Regulatory Authority's order and the developer's cancellation of allotment, directing the respondent to refund the entire amount paid by the appellant with interest at MCLR + 1% per annum.

3
Stage 204/04/2023

Hearing

The Tribunal heard arguments from both the appellant and respondent, but the judgment has been reserved for a later date.

4
Stage 313/03/2023

Hearing

The Tribunal has scheduled the case for hearing/orders on 04.04.2023 and directed reference to a previous order passed in Appeal No. 370/2019.

5
Stage 412/11/2021

Further Order

The Tribunal heard arguments from both parties regarding Appeal-340/2019 and reserved the judgment for a later date.

6
Stage 505/10/2021

Hearing

The Tribunal addressed a dispute regarding the calculation of interest for a refund, suggesting that the parties settle by calculating the remaining balance due to the appellant after deducting previously paid amounts and proposing payment via installments or unit allotment.

7
Stage 610/09/2021

Hearing

The Tribunal adjourned the case due to the absence of both parties and rescheduled the hearing for October 5, 2021.

8
Stage 706/05/2021

Arguments

No text available.

9
Stage 809/04/2021

Arguments

No text available.

10
Stage 916/03/2021

Hearing

The Tribunal granted an adjournment requested by the appellant and rescheduled the hearing for April 9, 2021.

11
Stage 1018/02/2021

Final Hearing

No text available.

12
Stage 1113/01/2021

For Order

No text available.

13
Stage 1220/10/2020

For Order

No text available.

14
Stage 13Final Ruling Order

Tribunal Order #0901126002302019-31-05-2023

The Appellate Tribunal set aside the Regulatory Authority's order and the developer's cancellation of allotment, directing the respondent to refund the entire amount paid by the appellant with interest at MCLR + 1% per annum.

15
Stage 14Interim Order

Tribunal Order #0901126002302019-05-10-2021

The Tribunal addressed a dispute regarding the calculation of interest for a refund, suggesting that the parties settle by calculating the remaining balance due to the appellant after deducting previously paid amounts and proposing payment via installments or unit allotment.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal set aside the Regulatory Authority's order and the developer's cancellation of allotment, directing the respondent to refund the entire amount paid by the appellant with interest at MCLR + 1% per annum. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% p.a..

Disposal Winner: AppellantInterest Rate: MCLR + 1% p.a.Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal set aside the Regulatory Authority's order and the developer's cancellation of allotment, directing the respondent to refund the entire amount paid by the appellant with interest at MCLR + 1% per annum.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1% p.a.

Interest Period

from the date of deposit till the date of actual refund

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Bishnu Kr. Agarwal

Respondent Advocate(s)

  • Chandrashekhar Azad

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126002302019-31-05-2023

The Appellate Tribunal set aside the Regulatory Authority's order and the developer's cancellation of allotment, directing the respondent to refund the entire amount paid by the appellant with interest at MCLR + 1% per annum.

INTERIM_ORDEROrder ID: 0901126002302019-05-10-2021

The Tribunal addressed a dispute regarding the calculation of interest for a refund, suggesting that the parties settle by calculating the remaining balance due to the appellant after deducting previously paid amounts and proposing payment via installments or unit allotment.

TathyaGrid RERA Intelligence AI

Need to research all rulings for himalaya realestate pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →