Appellant / Complainant
Nishi Kant Rai
Respondent
Paramount Probuild Pvt. Ltd.
paramount probuild pvt. ltd.
₹4,51,956
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126002252019 by Nishi Kant Rai against Paramount Probuild Pvt. Ltd. before up_rera.
Part Heard
The Tribunal allowed the appeals, directing the respondent promoter to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal additional charges and enhanced super area payments with interest, and commence maintenance charges only from the date of physical possession.
Hearing
The Tribunal has granted a request to list the appeal as a part-heard matter on 02.12.2025.
Further Hearing
The Tribunal granted a mutual request for adjournment from both parties and rescheduled the case for orders on 27.11.2025, noting that no further adjournments will be permitted.
Further Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the appeal for hearing on 13.11.2025, noting that no further adjournments will be permitted.
Further Hearing
The Tribunal heard arguments from both parties but found them inconclusive and adjourned the appeal for further hearing on 03.11.2025.
Further Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 09.10.2025.
Further Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the case for orders on 09.09.2025, noting that no further adjournments will be permitted.
Further Hearing
The Tribunal granted the respondent time to upload documents regarding disputed charges and adjourned the matter to 27.08.2025 for orders or further hearing.
Further Hearing
The Tribunal directed the respondent/promoter to ensure the appellant or their tenant has unhindered ingress and egress to the unit, including the right to move goods and furniture in or out.
Further Hearing
The Tribunal granted the respondent a one-week extension to comply with a previous order and directed the respondent promoter to provide all admissible maintenance services to the appellant, who is currently paying maintenance charges from the date of possession.
Further Hearing
The respondent's counsel requested and was granted additional time to comply with the previous order dated 07.03.2025, with the case scheduled for orders on 14.07.2025.
Further Hearing
The Tribunal granted a request from the respondent's counsel to adjourn the matter and scheduled the next hearing for 21.05.2025, allowing parties to exchange pleadings in the interim.
Further Hearing
The Tribunal granted the appellant's counsel additional time to comply with a previous order and rescheduled the case for hearing on 30.04.2025.
Further Hearing
The Tribunal directed the respondent to file an affidavit explaining the execution of additional FAR and ordered the appellant to deposit maintenance fees from the date of possession, pending the appeal outcome.
Hearing
At the request of the respondent's counsel, the tribunal has adjourned the appeal and scheduled it for a hearing on March 7, 2025.
Hearing
The Tribunal has scheduled the case for orders on February 12, 2025, noting the absence of the respondent's counsel.
Hearing
The Tribunal directed the respondent/promoter to submit the super area computation and provide a categorical statement regarding compliance with building bye-laws, while scheduling the next hearing for January 24, 2025.
Hearing
The court adjourned the proceedings at the request of the respondent's counsel and rescheduled the hearing for December 20, 2024, noting that no further adjournments will be granted.
Hearing
The parties expressed an intent to settle the matter out of court, and the tribunal adjourned the appeal to 20.11.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the case for orders on 15.10.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for a final hearing on 11.09.2024.
Hearing
The Tribunal granted a request from the respondent's counsel to reschedule the appeal for orders/hearing to 08.08.2024.
Hearing
The Tribunal noted that the appeal is ready for hearing and scheduled the matter for a hearing on 10.07.2024.
Hearing
The Tribunal granted an adjournment request from the respondent's counsel and scheduled the next hearing for 10.04.2024, noting that no further adjournments will be permitted.
Hearing
The Tribunal has ordered the appeal to be listed for a hearing on 22.03.2024.
Hearing
The Tribunal noted the absence of the respondent's counsel and scheduled the appeal for a hearing on 28.02.2024.
Hearing
The Tribunal fixed the next hearing date for Appeal-101/2019 to 31.01.2024 and directed that no further adjournments will be granted, noting that the matter will proceed based on available records if parties fail to appear.
Hearing
The Tribunal adjourned the proceedings and rescheduled the hearing for 17.10.2023 due to a strike called by the Bar Council of Uttar Pradesh.
Hearing
The Tribunal adjourned the appeal to 11.09.2023 due to the counsel for the appellant being on sanctioned leave, with a strict directive that no further adjournments will be granted on the next date.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to personal reasons, but warned that no further adjournments will be permitted and the case will proceed based on available records if counsel fails to appear on the next date.
Hearing
The Tribunal granted a request from the appellant's counsel to adjourn the matter and rescheduled the hearing for 18.08.2023.
Hearing
The Tribunal granted the respondent counsel time to prepare his brief and scheduled the appeal for a hearing on 24.05.2023.
Hearing
The U.P. Real Estate Appellate Tribunal adjourned the proceedings due to the absence of the respondent's counsel and scheduled the appeal for a hearing on 21.04.2023.
Hearing
The Tribunal heard arguments regarding claims for delay penalties, super area discrepancies, and structural defects, subsequently directing both parties to exchange and file any additional material facts within 15 days and reserving the judgment.
Hearing
The Tribunal directed the parties to be prepared for the final hearing of the appeal scheduled for 20.11.2021, noting that no further adjournments will be granted on that date.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the final hearing for 15.11.2021.
Hearing
The Tribunal granted an adjournment requested by the respondent and rescheduled the appeal for hearing on 21.10.2021.
Hearing
The Tribunal directed the Registry to record documents uploaded by the appellant and adjourned the matter to 26.03.2021 due to the absence of the respondent.
Tribunal Order #0901126002252019-30-07-2025
The Tribunal directed the respondent/promoter to ensure the appellant or their tenant has unhindered ingress and egress to the unit, including the right to move goods and furniture in or out.
Tribunal Order #0901126002252019-20-11-2021
The Tribunal heard arguments regarding claims for delay penalties, super area discrepancies, and structural defects, subsequently directing both parties to exchange and file any additional material facts within 15 days and reserving the judgment.
Tribunal Order #0901126002252019-02-12-2025
The Tribunal allowed the appeals, directing the respondent promoter to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal additional charges and enhanced super area payments with interest, and commence maintenance charges only from the date of physical possession.
Tribunal Order #0901126002252019-14-07-2025
The Tribunal granted the respondent a one-week extension to comply with a previous order and directed the respondent promoter to provide all admissible maintenance services to the appellant, who is currently paying maintenance charges from the date of possession.
Tribunal Order #0901126002252019-07-03-2025
The Tribunal directed the respondent to file an affidavit explaining the execution of additional FAR and ordered the appellant to deposit maintenance fees from the date of possession, pending the appeal outcome.
Tribunal Order #0901126002252019-20-12-2024
The Tribunal directed the respondent/promoter to submit the super area computation and provide a categorical statement regarding compliance with building bye-laws, while scheduling the next hearing for January 24, 2025.
Tribunal Disposal & Final Award Ruling
The Tribunal allowed the appeals, directing the respondent promoter to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal additional charges and enhanced super area payments with interest, and commence maintenance charges only from the date of physical possession. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal allowed the appeals, directing the respondent promoter to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal additional charges and enhanced super area payments with interest, and commence maintenance charges only from the date of physical possession.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR + 1%
Interest Period
w.e.f. 01.07.2016 to 08.12.2022
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Suchita Singh
Respondent Advocate(s)
- Saurabh Misra
- Shashank Kumar
- Krishna Kumar Singh
Official RERA Tribunal Orders (6)
The Tribunal directed the respondent/promoter to ensure the appellant or their tenant has unhindered ingress and egress to the unit, including the right to move goods and furniture in or out.
The Tribunal heard arguments regarding claims for delay penalties, super area discrepancies, and structural defects, subsequently directing both parties to exchange and file any additional material facts within 15 days and reserving the judgment.
The Tribunal allowed the appeals, directing the respondent promoter to pay delay interest from 01.07.2016 to 08.12.2022, refund illegal additional charges and enhanced super area payments with interest, and commence maintenance charges only from the date of physical possession.
The Tribunal granted the respondent a one-week extension to comply with a previous order and directed the respondent promoter to provide all admissible maintenance services to the appellant, who is currently paying maintenance charges from the date of possession.
The Tribunal directed the respondent to file an affidavit explaining the execution of additional FAR and ordered the appellant to deposit maintenance fees from the date of possession, pending the appeal outcome.
The Tribunal directed the respondent/promoter to submit the super area computation and provide a categorical statement regarding compliance with building bye-laws, while scheduling the next hearing for January 24, 2025.
Need to research all rulings for paramount probuild pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.