up_reraStatus: Completed
CASE ID: 0901126002162019

Appellant / Complainant

Ranjit Singh Kalra

VS

Respondent

Shalimar Lake City Pvt. Ltd.

Developer Firm

shalimar lake city pvt. ltd.

Disputed Amount

1,55,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

36 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002162019 by Ranjit Singh Kalra against Shalimar Lake City Pvt. Ltd. before up_rera.

Delay in PossessionJurisdiction & Maintainability
2
Stage 112/12/2024

Hearing

The Tribunal dismissed the appeal, ruling that the appellant was neither an 'allottee' nor an 'aggrieved person' under the RERA Act 2016 regarding the specific project in question, as his original booking was with a different entity for a separate, defunct township.

3
Stage 218/11/2024

Hearing

The Tribunal granted a request by the appellant's counsel to list the appeal for final hearing on 12.12.2024, noting that no further adjournments will be permitted.

4
Stage 303/10/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the matter for orders on 18.11.2024.

5
Stage 409/09/2024

Hearing

The Tribunal granted the respondent 7 days to supply a copy of their objection and directed both parties to upload all pleadings and documents to the portal within 7 days. The case is scheduled for hearing on 03.10.2024.

6
Stage 512/08/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the matter for hearing on 09.09.2024, providing a final opportunity to the respondent to argue.

7
Stage 612/07/2024

Hearing

No text available.

8
Stage 721/05/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and rescheduled the hearing for 12.07.2024.

9
Stage 824/04/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to his unavailability and scheduled the hearing for May 21, 2024.

10
Stage 921/03/2024

Hearing

The Tribunal adjourned the matter to 24.04.2024 following a request for adjournment from the respondent's counsel on health grounds and the absence of the appellant.

11
Stage 1027/02/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel on health grounds and rescheduled the hearing for 24.03.2024.

12
Stage 1131/01/2024

Hearing

The Tribunal granted a request for adjournment from the appellant's counsel and rescheduled the hearing of the appeal to 27.02.2024.

13
Stage 1201/11/2023

Hearing

No text available.

14
Stage 1320/09/2023

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to personal difficulties and rescheduled the hearing for November 1, 2023.

15
Stage 1425/08/2023

Hearing

The Tribunal granted the appellant's counsel additional time to prepare the case file and rescheduled the hearing for 20.09.2023.

16
Stage 1507/07/2023

Hearing

The tribunal adjourned the proceedings due to a request from the appellant on health grounds and rescheduled the matter for orders/hearing on 25.08.2023.

17
Stage 1627/04/2023

Hearing

Due to the previous Presiding Member demitting office before delivering a reserved judgment, the Tribunal has ordered a fresh hearing of the appeal on 07.07.2023.

18
Stage 1720/03/2023

Hearing

No text available.

19
Stage 1809/02/2023

Hearing

No text available.

20
Stage 1922/12/2022

Hearing

The Tribunal adjourned the matter due to lack of time and rescheduled the appeal for hearing on February 9, 2023.

21
Stage 2019/04/2022

Arguments

The Tribunal heard arguments from both parties and directed them to exchange lists of dates, events, and relied cases, allowing 20 days for filing additional documents before reserving the judgment.

22
Stage 2102/03/2022

Final Hearing

The Tribunal adjourned the case to 19.04.2022 for arguments and directed both parties to file relevant rulings on the points in question before the next hearing.

23
Stage 2219/01/2022

Final Hearing

No text available.

24
Stage 2307/01/2022

Final Hearing

The Tribunal granted the respondent's counsel additional time to prepare his brief and rescheduled the appeal hearing for 19.01.2022, noting that no further adjournments will be permitted on that date.

25
Stage 2403/12/2021

Hearing

The Tribunal noted that pleadings have been exchanged and adjourned the matter to 07.01.2022 for a final hearing before Bench No. 1.

26
Stage 2517/11/2021

Hearing

The Tribunal granted an adjournment requested by the appellant due to illness and rescheduled the hearing for December 3, 2021.

27
Stage 2624/09/2021

Hearing

The Tribunal directed the Respondent's Managing Director or an authorized person to appear in person on the next hearing date, warning that failure to do so will result in adverse inference due to the Respondent's lack of progress toward settlement.

28
Stage 2727/04/2021

Hearing

No text available.

29
Stage 2825/03/2021

Further Order

No text available.

30
Stage 2905/02/2021

Further Order

The Tribunal ruled that the moratorium declared against M/S M-Tech Developers Pvt. Ltd. does not affect the present case against respondent M/S Shalimar Lake City Pvt. Ltd., and directed the respondent to file a reply to the appeal.

31
Stage 3005/01/2021

Hearing

No text available.

32
Stage 3126/11/2020

Hearing

No text available.

33
Stage 32Final Ruling Order

Tribunal Order #0901126002162019-12-12-2024

The Tribunal dismissed the appeal, ruling that the appellant was neither an 'allottee' nor an 'aggrieved person' under the RERA Act 2016 regarding the specific project in question, as his original booking was with a different entity for a separate, defunct township.

34
Stage 33Interim Order

Tribunal Order #0901126002162019-05-02-2021

The Tribunal ruled that the moratorium declared against M/S M-Tech Developers Pvt. Ltd. does not affect the present case against respondent M/S Shalimar Lake City Pvt. Ltd., and directed the respondent to file a reply to the appeal.

35
Stage 34Interim Order

Tribunal Order #0901126002162019-24-09-2021

The Tribunal directed the Respondent's Managing Director or an authorized person to appear in person on the next hearing date, warning that failure to do so will result in adverse inference due to the Respondent's lack of progress toward settlement.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal, ruling that the appellant was neither an 'allottee' nor an 'aggrieved person' under the RERA Act 2016 regarding the specific project in question, as his original booking was with a different entity for a separate, defunct township. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal, ruling that the appellant was neither an 'allottee' nor an 'aggrieved person' under the RERA Act 2016 regarding the specific project in question, as his original booking was with a different entity for a separate, defunct township.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Vaibhav Krishna

Respondent Advocate(s)

  • Anurag Singh
  • Shreya Mehrotra
  • Praniti Agarwal
  • Unnati Vijay

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126002162019-12-12-2024

The Tribunal dismissed the appeal, ruling that the appellant was neither an 'allottee' nor an 'aggrieved person' under the RERA Act 2016 regarding the specific project in question, as his original booking was with a different entity for a separate, defunct township.

INTERIM_ORDEROrder ID: 0901126002162019-05-02-2021

The Tribunal ruled that the moratorium declared against M/S M-Tech Developers Pvt. Ltd. does not affect the present case against respondent M/S Shalimar Lake City Pvt. Ltd., and directed the respondent to file a reply to the appeal.

INTERIM_ORDEROrder ID: 0901126002162019-24-09-2021

The Tribunal directed the Respondent's Managing Director or an authorized person to appear in person on the next hearing date, warning that failure to do so will result in adverse inference due to the Respondent's lack of progress toward settlement.

TathyaGrid RERA Intelligence AI

Need to research all rulings for shalimar lake city pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →