up_reraStatus: Completed
CASE ID: 0901126002132019

Appellant / Complainant

U.P. Avas Evam Vikas Parishad

VS

Respondent

Priyanka Yadav

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002132019 by U.P. Avas Evam Vikas Parishad against Priyanka Yadav before up_rera.

2
Stage 110/02/2022

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal rejected the applicant's application for condonation of delay and consequently dismissed Misc. Case-438/2019, finding the explanation for the 353-day delay to be fictitious and concocted.

3
Stage 229/11/2021

Further Order

The Tribunal heard arguments on the limitation application and reserved judgment on the point of limitation.

4
Stage 310/11/2021

Hearing

No text available.

5
Stage 421/09/2021

Hearing

The Tribunal adjourned the matter to 10.11.2021 to align with the disposal schedule of similar cases, following arguments regarding parking allotment and interest grievances.

6
Stage 522/04/2021

Hearing

No text available.

7
Stage 623/03/2021

For Order

The applicant (developer) assured the Tribunal that all construction defects will be rectified and a parking space will be allotted to the respondent within 15 days.

8
Stage 727/01/2021

For Order

The Tribunal directed the respondent to file supporting documents via the Registry and email, while allowing the appellant the opportunity to file a rebuttal before the next hearing on 23.03.2021.

9
Stage 806/11/2020

For Order

No text available.

10
Stage 9Final Ruling Order

Tribunal Order #0901126002132019-10-02-2022

The U.P. Real Estate Appellate Tribunal rejected the applicant's application for condonation of delay and consequently dismissed Misc. Case-438/2019, finding the explanation for the 353-day delay to be fictitious and concocted.

11
Stage 10Interim Order

Tribunal Order #0901126002132019-23-03-2021

The applicant (developer) assured the Tribunal that all construction defects will be rectified and a parking space will be allotted to the respondent within 15 days.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the applicant's application for condonation of delay and consequently dismissed Misc. Case-438/2019, finding the explanation for the 353-day delay to be fictitious and concocted. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the applicant's application for condonation of delay and consequently dismissed Misc. Case-438/2019, finding the explanation for the 353-day delay to be fictitious and concocted.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Akhand Pratap Singh
  • Vijay Pratap Singh Chauhan

Respondent Advocate(s)

  • Dilip Singh

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126002132019-10-02-2022

The U.P. Real Estate Appellate Tribunal rejected the applicant's application for condonation of delay and consequently dismissed Misc. Case-438/2019, finding the explanation for the 353-day delay to be fictitious and concocted.

INTERIM_ORDEROrder ID: 0901126002132019-23-03-2021

The applicant (developer) assured the Tribunal that all construction defects will be rectified and a parking space will be allotted to the respondent within 15 days.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →