up_reraStatus: Completed
CASE ID: 0901126002122020

Appellant / Complainant

Gaursons Realtech Pvt Ltd

VS

Respondent

Lokendra Singh

Developer Firm

gaursons realtech pvt ltd

Disputed Amount

30,34,646

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002122020 by Gaursons Realtech Pvt Ltd against Lokendra Singh before up_rera.

Delay in PossessionDelay Compensation / InterestMaintenance & Utility Disputes
2
Stage 122/03/2022

for delivery of Judgment/Order

The Appellate Tribunal dismissed the appeal filed by M/S Gaursons Realtech Pvt. Ltd., upholding the Adjudicating Officer's order for compensation due to delayed possession and directing the transfer of the promoter's pre-deposit to U.P. RERA for disbursement to the respondent.

3
Stage 207/12/2021

Final Hearing

The court heard arguments from both parties and reserved the judgment for a later date.

4
Stage 323/11/2021

Final Hearing

The Tribunal adjourned the appeal to 07.12.2021 to allow counsel for both parties to submit arguments regarding whether construction delays caused by NGT bans and COVID-19 should affect promised delivery dates.

5
Stage 422/11/2021

Hearing

The court granted an adjournment to the appellant's counsel due to unpreparedness and rescheduled the matter for hearing on 23.11.2021.

6
Stage 528/09/2021

Hearing

The Tribunal noted the possibility of a settlement between the parties and directed the respondent to appear in person at the next hearing on 22.11.2021.

7
Stage 629/04/2021

Hearing

No text available.

8
Stage 702/04/2021

For Order

The Tribunal directed the applicant to file a replication/rejoinder if desired and ordered both parties to upload their documents on the e-portal before the next hearing scheduled for 29.04.2021.

9
Stage 810/03/2021

Further Order

The Tribunal directed the Registry to verify a deposit of Rs. 72,566/- made via demand draft and submit a report within one week, while scheduling the defective appeal for hearing on 02.04.2021.

10
Stage 910/02/2021

Hearing

The Tribunal directed the appellant to file an amendment application to modify the relief sought and ordered them to submit proof of deposit regarding Section 43(5) within three days.

11
Stage 1020/11/2020

Admission

No text available.

12
Stage 11Interim Order

Tribunal Order #0901126002122020-10-02-2021

The Tribunal directed the appellant to file an amendment application to modify the relief sought and ordered them to submit proof of deposit regarding Section 43(5) within three days.

13
Stage 12Final Ruling Order

Tribunal Order #0901126002122020-22-03-2022

The Appellate Tribunal dismissed the appeal filed by M/S Gaursons Realtech Pvt. Ltd., upholding the Adjudicating Officer's order for compensation due to delayed possession and directing the transfer of the promoter's pre-deposit to U.P. RERA for disbursement to the respondent.

14
Stage 13Interim Order

Tribunal Order #0901126002122020-10-03-2021

The Tribunal directed the Registry to verify a deposit of Rs. 72,566/- made via demand draft and submit a report within one week, while scheduling the defective appeal for hearing on 02.04.2021.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeal filed by M/S Gaursons Realtech Pvt. Ltd., upholding the Adjudicating Officer's order for compensation due to delayed possession and directing the transfer of the promoter's pre-deposit to U.P. RERA for disbursement to the respondent. Awarded in favor of Respondent. Awarded interest rate: MCLR+1% per annum.

Disposal Winner: RespondentInterest Rate: MCLR+1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeal filed by M/S Gaursons Realtech Pvt. Ltd., upholding the Adjudicating Officer's order for compensation due to delayed possession and directing the transfer of the promoter's pre-deposit to U.P. RERA for disbursement to the respondent.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1% per annum

Interest Period

from 30.03.2018 till delivery of actual possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(d)Section 19(6)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • D N Verma
  • Samrat Vaish

Respondent Advocate(s)

  • Arvind Tilhari

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126002122020-10-02-2021

The Tribunal directed the appellant to file an amendment application to modify the relief sought and ordered them to submit proof of deposit regarding Section 43(5) within three days.

FINAL_ORDEROrder ID: 0901126002122020-22-03-2022

The Appellate Tribunal dismissed the appeal filed by M/S Gaursons Realtech Pvt. Ltd., upholding the Adjudicating Officer's order for compensation due to delayed possession and directing the transfer of the promoter's pre-deposit to U.P. RERA for disbursement to the respondent.

INTERIM_ORDEROrder ID: 0901126002122020-10-03-2021

The Tribunal directed the Registry to verify a deposit of Rs. 72,566/- made via demand draft and submit a report within one week, while scheduling the defective appeal for hearing on 02.04.2021.