Appellant / Complainant
Rajendra Kumar
Respondent
Jai Prakash Associates Ltd., Progressive Welfare Society
jai prakash associates ltd.
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126002112019 by Rajendra Kumar against Jai Prakash Associates Ltd., Progressive Welfare Society before up_rera.
Hearing
The Tribunal allowed the appellant's application to withdraw the appeal but rejected the request for liberty to re-approach the Tribunal on the same cause of action, resulting in the appeal being dismissed as withdrawn.
Final Hearing
The Tribunal directed the appellant to implead the Progressive Welfare Society as a necessary party to the proceedings within 10 days, failing which the appeal will be dismissed for want of proper respondents.
Final Hearing
The Tribunal adjourned the proceedings at the request of the appellant's counsel to allow time to decide whether to proceed with a rectification application regarding the impleadment of a project management body.
Final Hearing
The court has granted an adjournment of today's proceedings following a request from the counsel for the appellant.
Final Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to a scheduling conflict and rescheduled the hearing for 31.10.2022.
Final Hearing
The Tribunal granted the applicant one week to take necessary steps to implead the authorized body currently managing the project following its de-registration by RERA.
Further Hearing
The Tribunal directed the parties to ensure compliance with a previous order dated 10.05.2022 and scheduled the appeal for a hearing on 30.08.2022.
Further Hearing
The Tribunal granted the appellant an extension of one week to comply with a previous order regarding the project's status and has rescheduled the hearing for August 3, 2022.
Further Order
The Tribunal directed both the appellant and respondent to file the current status of the project and the specific unit in question before the next hearing date of July 20, 2022.
for delivery of Judgment/Order
The Tribunal condoned the delay (if any) and ruled that the limitation period begins from the date of the Review Petition order (30.10.2019), subsequently directing the defective appeal to be registered as a Regular Appeal.
Hearing
The Tribunal held a hearing for Appeal-366/2019 and reserved its orders regarding the limitation point.
Delay condonation
The Tribunal heard arguments regarding the application for condonation of delay and its objection, subsequently scheduling the matter for April 22, 2021, to pass an order on the limitation application.
Delay condonation
The Tribunal adjourned the matter to 25.03.2021 for a hearing on the limitation application and its objection, following submissions from both counsels regarding supporting legal precedents.
Delay condonation
The Tribunal directed the Registry to locate a missing affidavit regarding a condonation of delay application and instructed parties to file relevant case law on limitation before the next hearing on 15.03.2021.
Tribunal Order #0901126002112019-23-11-2022
The Tribunal directed the appellant to implead the Progressive Welfare Society as a necessary party to the proceedings within 10 days, failing which the appeal will be dismissed for want of proper respondents.
Tribunal Order #0901126002112019-05-04-2022
The Tribunal condoned the delay (if any) and ruled that the limitation period begins from the date of the Review Petition order (30.10.2019), subsequently directing the defective appeal to be registered as a Regular Appeal.
Tribunal Disposal & Final Award Ruling
Dismissed as withdrawn Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed as withdrawn
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Ashish Chaturvedi
- Shraddha Agarwal
Respondent Advocate(s)
- Altaf Mansoor
- Nitin Kapoor
Official RERA Tribunal Orders (2)
The Tribunal directed the appellant to implead the Progressive Welfare Society as a necessary party to the proceedings within 10 days, failing which the appeal will be dismissed for want of proper respondents.
The Tribunal condoned the delay (if any) and ruled that the limitation period begins from the date of the Review Petition order (30.10.2019), subsequently directing the defective appeal to be registered as a Regular Appeal.