up_reraStatus: Completed
CASE ID: 0901126002112019

Appellant / Complainant

Rajendra Kumar

VS

Respondent

Jai Prakash Associates Ltd., Progressive Welfare Society

Developer Firm

jai prakash associates ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002112019 by Rajendra Kumar against Jai Prakash Associates Ltd., Progressive Welfare Society before up_rera.

2
Stage 102/03/2023

Hearing

The Tribunal allowed the appellant's application to withdraw the appeal but rejected the request for liberty to re-approach the Tribunal on the same cause of action, resulting in the appeal being dismissed as withdrawn.

3
Stage 223/11/2022

Final Hearing

The Tribunal directed the appellant to implead the Progressive Welfare Society as a necessary party to the proceedings within 10 days, failing which the appeal will be dismissed for want of proper respondents.

4
Stage 319/11/2022

Final Hearing

The Tribunal adjourned the proceedings at the request of the appellant's counsel to allow time to decide whether to proceed with a rectification application regarding the impleadment of a project management body.

5
Stage 431/10/2022

Final Hearing

The court has granted an adjournment of today's proceedings following a request from the counsel for the appellant.

6
Stage 526/09/2022

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to a scheduling conflict and rescheduled the hearing for 31.10.2022.

7
Stage 630/08/2022

Final Hearing

The Tribunal granted the applicant one week to take necessary steps to implead the authorized body currently managing the project following its de-registration by RERA.

8
Stage 703/08/2022

Further Hearing

The Tribunal directed the parties to ensure compliance with a previous order dated 10.05.2022 and scheduled the appeal for a hearing on 30.08.2022.

9
Stage 820/07/2022

Further Hearing

The Tribunal granted the appellant an extension of one week to comply with a previous order regarding the project's status and has rescheduled the hearing for August 3, 2022.

10
Stage 910/05/2022

Further Order

The Tribunal directed both the appellant and respondent to file the current status of the project and the specific unit in question before the next hearing date of July 20, 2022.

11
Stage 1005/04/2022

for delivery of Judgment/Order

The Tribunal condoned the delay (if any) and ruled that the limitation period begins from the date of the Review Petition order (30.10.2019), subsequently directing the defective appeal to be registered as a Regular Appeal.

12
Stage 1121/09/2021

Hearing

The Tribunal held a hearing for Appeal-366/2019 and reserved its orders regarding the limitation point.

13
Stage 1222/04/2021

For Order

No text available.

14
Stage 1325/03/2021

Delay condonation

The Tribunal heard arguments regarding the application for condonation of delay and its objection, subsequently scheduling the matter for April 22, 2021, to pass an order on the limitation application.

15
Stage 1415/03/2021

Delay condonation

The Tribunal adjourned the matter to 25.03.2021 for a hearing on the limitation application and its objection, following submissions from both counsels regarding supporting legal precedents.

16
Stage 1509/02/2021

Delay condonation

The Tribunal directed the Registry to locate a missing affidavit regarding a condonation of delay application and instructed parties to file relevant case law on limitation before the next hearing on 15.03.2021.

17
Stage 1612/01/2021

Hearing

No text available.

18
Stage 1704/12/2020

Hearing

No text available.

19
Stage 18Interim Order

Tribunal Order #0901126002112019-23-11-2022

The Tribunal directed the appellant to implead the Progressive Welfare Society as a necessary party to the proceedings within 10 days, failing which the appeal will be dismissed for want of proper respondents.

20
Stage 19Interim Order

Tribunal Order #0901126002112019-05-04-2022

The Tribunal condoned the delay (if any) and ruled that the limitation period begins from the date of the Review Petition order (30.10.2019), subsequently directing the defective appeal to be registered as a Regular Appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Ashish Chaturvedi
  • Shraddha Agarwal

Respondent Advocate(s)

  • Altaf Mansoor
  • Nitin Kapoor

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126002112019-23-11-2022

The Tribunal directed the appellant to implead the Progressive Welfare Society as a necessary party to the proceedings within 10 days, failing which the appeal will be dismissed for want of proper respondents.

INTERIM_ORDEROrder ID: 0901126002112019-05-04-2022

The Tribunal condoned the delay (if any) and ruled that the limitation period begins from the date of the Review Petition order (30.10.2019), subsequently directing the defective appeal to be registered as a Regular Appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for jai prakash associates ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →