up_reraStatus: Completed
CASE ID: 0901126001932019

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Puran Singh

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126001932019 by Lucknow Development Authority against Puran Singh before up_rera.

2
Stage 116/03/2023

Hearing

The appeal filed by the Lucknow Development Authority was dismissed for want of prosecution due to the absence of counsel and failure to assign a new representative following the resignation of the previous panel lawyer.

3
Stage 228/02/2023

Hearing

The Tribunal adjourned the proceedings following a request from the appellant's counsel and scheduled the appeal for final hearing on 16.03.2023, noting that no further adjournments will be granted.

4
Stage 327/01/2023

Hearing

No text available.

5
Stage 421/12/2022

Hearing

The Tribunal adjourned the appeal to 27.01.2023 for hearing due to the absence of the respondent.

6
Stage 524/12/2021

Compliance of section 43(5)

The Tribunal heard arguments from both parties following the exchange of pleadings and subsequently reserved the judgment for further consideration.

7
Stage 626/11/2021

Further Order

The Tribunal adjourned the appeal to 24.12.2021 following an adjournment application filed by the respondent's counsel.

8
Stage 702/11/2021

Further Order

The Tribunal adjourned the appeal to 26.11.2021 and directed the parties to exchange pleadings and file originals with the Registry at least one week before the next hearing.

9
Stage 806/10/2021

Hearing

The Tribunal adjourned the appeal due to the appellant's counsel being on leave and directed the parties to exchange pleadings and upload them to the e-portal before the next hearing on 02.11.2021.

10
Stage 920/04/2021

Hearing

No text available.

11
Stage 1026/03/2021

Hearing

No text available.

12
Stage 1105/03/2021

For Order

The court noted that lawyers were abstaining from judicial work due to a call by the Oudh Bar Association and subsequently rescheduled the appeal for hearing on 26.03.2021.

13
Stage 1224/02/2021

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for 24.02.2021.

14
Stage 1311/02/2021

For Order

The appeal was adjourned due to a request for adjournment by the appellant's counsel on the grounds of illness, with the matter rescheduled for 24.02.2021.

15
Stage 1422/01/2021

Compliance of section 43(5)

The Tribunal allowed the application for condonation of delay and recalled the order dated 07.07.2020, thereby restoring the appeal to its original number.

16
Stage 1505/01/2021

Hearing

No text available.

17
Stage 1617/12/2020

Hearing

No text available.

18
Stage 1710/12/2020

Hearing

No text available.

19
Stage 18Final Ruling Order

Tribunal Order #0901126001932019-16-03-2023

The appeal filed by the Lucknow Development Authority was dismissed for want of prosecution due to the absence of counsel and failure to assign a new representative following the resignation of the previous panel lawyer.

20
Stage 19Interim Order

Tribunal Order #0901126001932019-22-01-2021

The Tribunal allowed the application for condonation of delay and recalled the order dated 07.07.2020, thereby restoring the appeal to its original number.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The appeal filed by the Lucknow Development Authority was dismissed for want of prosecution due to the absence of counsel and failure to assign a new representative following the resignation of the previous panel lawyer. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The appeal filed by the Lucknow Development Authority was dismissed for want of prosecution due to the absence of counsel and failure to assign a new representative following the resignation of the previous panel lawyer.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • Anoop Kumar
  • Sandeep Srivastava

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126001932019-16-03-2023

The appeal filed by the Lucknow Development Authority was dismissed for want of prosecution due to the absence of counsel and failure to assign a new representative following the resignation of the previous panel lawyer.

INTERIM_ORDEROrder ID: 0901126001932019-22-01-2021

The Tribunal allowed the application for condonation of delay and recalled the order dated 07.07.2020, thereby restoring the appeal to its original number.