up_reraStatus: Completed
CASE ID: 0901126001922023

Appellant / Complainant

S.P.Sai.It.Pvt. Ltd

VS

Respondent

Pravat Kumar Roy

Developer Firm

s.p.sai.it.pvt. ltd

Disputed Amount

2,00,000

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional MisrepresentationMaintenance & Utility DisputesJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

25 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126001922023 by S.P.Sai.It.Pvt. Ltd against Pravat Kumar Roy before up_rera.

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional MisrepresentationMaintenance & Utility DisputesJurisdiction & Maintainability
2
Stage 126/09/2025

for delivery of Judgment/Order

The Appellate Tribunal partially allowed the appeal, quashing the Adjudicating Officer's order regarding delay interest due to lack of jurisdiction but directing the payment of delay interest from 01.09.2018 to 22.07.2021 (excluding COVID-19 force majeure periods) and upholding the Rs. 75,000 compensation for structural defects.

3
Stage 208/05/2025

Hearing

The Tribunal heard arguments from both counsels regarding the appeal and its objections, subsequently reserving the judgment for future pronouncement.

4
Stage 311/04/2025

Hearing

The Tribunal has scheduled the case for orders on May 8, 2025, noting the presence of the respondent's counsel and the absence of the appellant's counsel.

5
Stage 416/12/2024

Hearing

The appeal filed by S.P. Sai IT Pvt. Ltd. was dismissed for want of prosecution due to the non-appearance of the appellant's counsel.

6
Stage 528/11/2024

Hearing

No text available.

7
Stage 622/10/2024

Hearing

The Tribunal granted a request from the appellant's counsel to reschedule the hearing, listing the appeal for 28-11-2024.

8
Stage 712/09/2024

Hearing

The Tribunal directed both parties to upload documents concerning compensation granted for structural defects within seven days and scheduled the matter for orders on 22.10.2024.

9
Stage 808/08/2024

For Order

The Tribunal granted a final opportunity to the appellant to argue the matter and rescheduled the hearing for 12.09.2024 due to their absence.

10
Stage 909/07/2024

For Order

The Tribunal noted the absence of both parties and rescheduled the appeal for orders/hearing on 08.08.2024.

11
Stage 1010/05/2024

For Order

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the appeal for hearing on 09.07.2024.

12
Stage 1109/04/2024

For Order

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for orders/hearing on 10.05.2024.

13
Stage 1205/03/2024

For Order

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the appeal for hearing on 09.04.2024.

14
Stage 1325/01/2024

For Order

The Tribunal granted a request for adjournment from the appellant and rescheduled the appeal for orders to 05.03.2024.

15
Stage 1427/10/2023

For Order

No text available.

16
Stage 1515/09/2023

For Order

The Tribunal directed the respondent's counsel to upload their objections to the respondent's folder and provide a soft copy to the appellant within three days, with the next hearing scheduled for 27.10.2023.

17
Stage 1627/07/2023

For Order

No text available.

18
Stage 1715/05/2023

For Order

The Tribunal granted the respondent 10 days to file objections against the appeal and allowed the appellant one week thereafter to file a reply, scheduling the next hearing for 27.07.2023.

19
Stage 1803/04/2023

For Order

The Tribunal converted the defective appeal into a regular appeal following the appellant's compliance with Section 43(5) via deposit of Rs. 3,75,000 and directed the issuance of notice to the respondent.

20
Stage 1924/03/2023

Defect Removal

The Tribunal noted procedural defects regarding the multiple uploading of annexures on the portal and directed the appellant's counsel to rectify these issues with the Registry before the next hearing on 27.03.2023.

21
Stage 20Final Ruling Order

Tribunal Order #0901126001922023-26-09-2025

The Appellate Tribunal partially allowed the appeal, quashing the Adjudicating Officer's order regarding delay interest due to lack of jurisdiction but directing the payment of delay interest from 01.09.2018 to 22.07.2021 (excluding COVID-19 force majeure periods) and upholding the Rs. 75,000 compensation for structural defects.

22
Stage 21Final Ruling Order

Tribunal Order #0901126001922023-16-12-2024

The appeal filed by S.P. Sai IT Pvt. Ltd. was dismissed for want of prosecution due to the non-appearance of the appellant's counsel.

23
Stage 22Interim Order

Tribunal Order #0901126001922023-03-04-2023

The Tribunal converted the defective appeal into a regular appeal following the appellant's compliance with Section 43(5) via deposit of Rs. 3,75,000 and directed the issuance of notice to the respondent.

24
Stage 23Interim Order

Tribunal Order #0901126001922023-12-09-2024

The Tribunal directed both parties to upload documents concerning compensation granted for structural defects within seven days and scheduled the matter for orders on 22.10.2024.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal partially allowed the appeal, quashing the Adjudicating Officer's order regarding delay interest due to lack of jurisdiction but directing the payment of delay interest from 01.09.2018 to 22.07.2021 (excluding COVID-19 force majeure periods) and upholding the Rs. 75,000 compensation for structural defects. The appeal filed by S.P. Sai IT Pvt. Ltd. was dismissed for want of prosecution due to the non-appearance of the appellant's counsel. Awarded in favor of Partial. Awarded interest rate: MCLR + 1% per annum.

Disposal Winner: PartialInterest Rate: MCLR + 1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal partially allowed the appeal, quashing the Adjudicating Officer's order regarding delay interest due to lack of jurisdiction but directing the payment of delay interest from 01.09.2018 to 22.07.2021 (excluding COVID-19 force majeure periods) and upholding the Rs. 75,000 compensation for structural defects. The appeal filed by S.P. Sai IT Pvt. Ltd. was dismissed for want of prosecution due to the non-appearance of the appellant's counsel.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR + 1% per annum

Interest Period

w.e.f. 01.09.2018 to 22.07.2021 (excluding the period from 25.03.2020 to 25.09.2020)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 14(3)Section 12Section 11(4)(d)Section 19(6)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Vaibhav Krishna
  • Anurag Vikram Singh

Respondent Advocate(s)

  • Vijay Kant Srivastava

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126001922023-26-09-2025

The Appellate Tribunal partially allowed the appeal, quashing the Adjudicating Officer's order regarding delay interest due to lack of jurisdiction but directing the payment of delay interest from 01.09.2018 to 22.07.2021 (excluding COVID-19 force majeure periods) and upholding the Rs. 75,000 compensation for structural defects.

FINAL_ORDEROrder ID: 0901126001922023-16-12-2024

The appeal filed by S.P. Sai IT Pvt. Ltd. was dismissed for want of prosecution due to the non-appearance of the appellant's counsel.

INTERIM_ORDEROrder ID: 0901126001922023-03-04-2023

The Tribunal converted the defective appeal into a regular appeal following the appellant's compliance with Section 43(5) via deposit of Rs. 3,75,000 and directed the issuance of notice to the respondent.

INTERIM_ORDEROrder ID: 0901126001922023-12-09-2024

The Tribunal directed both parties to upload documents concerning compensation granted for structural defects within seven days and scheduled the matter for orders on 22.10.2024.