up_reraStatus: Completed
CASE ID: 0901126001752019

Appellant / Complainant

Manish Kumar

VS

Respondent

Mahagun India Pvt. Ltd.

Developer Firm

mahagun india pvt. ltd.

Disposal Award

Both (Amicably Settled)

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

32 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126001752019 by Manish Kumar against Mahagun India Pvt. Ltd. before up_rera.

2
Stage 117/07/2023

Final Hearing

The Tribunal noted that the appellant's counsel lacked instructions to proceed, but the respondent informed the court that the dispute between the parties has been amicably settled.

3
Stage 205/07/2023

Final Hearing

The Tribunal adjourned the appeal to 17-07-2023 for consideration of a delay condonation application after the appellant's counsel reported that the dispute between the parties has been resolved.

4
Stage 327/04/2023

Final Hearing

The Tribunal adjourned the matter due to lack of time and rescheduled the hearing for July 5, 2023.

5
Stage 420/03/2023

Final Hearing

No text available.

6
Stage 509/02/2023

Final Hearing

No text available.

7
Stage 605/01/2023

Final Hearing

No text available.

8
Stage 701/12/2022

Final Hearing

The Tribunal noted the respondent's failure to provide annexures to the appellant and warned that inferences would be drawn against the respondent during the hearing if these documents are not furnished.

9
Stage 819/11/2022

Final Hearing

The Tribunal examined whether the Regulatory Authority's order was within the scope of the original pleadings and directed the respondent to file a Vakalatnama and reply to the grounds of appeal before the next hearing on 01.12.2022.

10
Stage 909/11/2022

Hearing

The Tribunal noted the appellant's objection regarding incomplete annexures from the respondent and adjourned the matter to 01.12.2022 for hearing.

11
Stage 1010/10/2022

Hearing

The Tribunal adjourned the appeal in the interest of justice and scheduled the matter for a hearing on 09.11.2022.

12
Stage 1121/09/2022

Hearing

The Tribunal directed the respondent to provide all annexures to their reply and scheduled the appeal for hearing on 10.10.2022.

13
Stage 1223/08/2022

Exchange of pleadings

The Tribunal granted an adjournment requested by the respondent and scheduled the next hearing for 21.09.2022, directing counsel for both parties to appear without fail.

14
Stage 1319/07/2022

Hearing

The Tribunal directed the respondent to provide a complete copy of their reply to the appellant and ordered the appellant to file a replication/rejoinder upon receipt before the next hearing on 23.08.2022.

15
Stage 1409/05/2022

Hearing

The Tribunal directed the respondent to provide a complete copy of their reply to the appellant and ordered the appellant to file a replication before the next hearing on 19.07.2022.

16
Stage 1504/04/2022

Hearing

The Tribunal directed the appellant's counsel to file a replication/rejoinder by the next hearing date and provided a new listing date of 09.05.2022 for final hearing.

17
Stage 1624/12/2021

for delivery of Judgment/Order

The Tribunal allowed the appellant's application for condonation of delay, permitting the appeal to be registered as a Regular Appeal subject to a cost of Rs. 4,000/-.

18
Stage 1708/12/2021

Hearing

The Tribunal heard arguments regarding the point of limitation and subsequently reserved orders on that specific issue.

19
Stage 1826/11/2021

Hearing

The Tribunal adjourned the matter to 08.12.2021 for the disposal of a limitation application and any related objections.

20
Stage 1922/11/2021

Hearing

The Tribunal directed that the matter be listed before Bench No. 2 on 26.11.2021 for the delivery of a reserved order regarding an application for condonation of delay.

21
Stage 2001/11/2021

Hearing

The Tribunal adjourned the pronouncement of the order on the application for condonation of delay to 22.11.2021 due to the unavailability of the concerned Bench.

22
Stage 2117/09/2021

Hearing

The Tribunal granted the appellant's counsel permission to file additional submissions regarding the point of limitation within 15 days and rescheduled the case for an order on 01.11.2021.

23
Stage 2219/04/2021

Hearing

No text available.

24
Stage 2318/03/2021

Hearing

No text available.

25
Stage 2419/02/2021

For Order

The matter is noted as part-heard from Bench No. 2 and is scheduled to be listed before the concerned Bench on March 18, 2021.

26
Stage 2512/01/2021

Delay condonation

No text available.

27
Stage 2605/11/2020

Delay condonation

No text available.

28
Stage 27Final Ruling Order

Tribunal Order #0901126001752019-17-07-2023

The Tribunal noted that the appellant's counsel lacked instructions to proceed, but the respondent informed the court that the dispute between the parties has been amicably settled.

29
Stage 28Interim Order

Tribunal Order #0901126001752019-19-11-2022

The Tribunal examined whether the Regulatory Authority's order was within the scope of the original pleadings and directed the respondent to file a Vakalatnama and reply to the grounds of appeal before the next hearing on 01.12.2022.

30
Stage 29Final Ruling Order

Tribunal Order #0901126001752019-24-12-2021

The Tribunal allowed the appellant's application for condonation of delay, permitting the appeal to be registered as a Regular Appeal subject to a cost of Rs. 4,000/-.

31
Stage 30Interim Order

Tribunal Order #0901126001752019-01-12-2022

The Tribunal noted the respondent's failure to provide annexures to the appellant and warned that inferences would be drawn against the respondent during the hearing if these documents are not furnished.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal noted that the appellant's counsel lacked instructions to proceed, but the respondent informed the court that the dispute between the parties has been amicably settled. The Tribunal allowed the appellant's application for condonation of delay, permitting the appeal to be registered as a Regular Appeal subject to a cost of Rs. 4,000/-. Awarded in favor of Both (Amicably Settled).

Disposal Winner: Both (Amicably Settled)Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal noted that the appellant's counsel lacked instructions to proceed, but the respondent informed the court that the dispute between the parties has been amicably settled. The Tribunal allowed the appellant's application for condonation of delay, permitting the appeal to be registered as a Regular Appeal subject to a cost of Rs. 4,000/-.

Ruling Awarded To

Both (Amicably Settled)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Fuhar Gupta

Respondent Advocate(s)

  • Anurag Srivastava

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126001752019-17-07-2023

The Tribunal noted that the appellant's counsel lacked instructions to proceed, but the respondent informed the court that the dispute between the parties has been amicably settled.

INTERIM_ORDEROrder ID: 0901126001752019-19-11-2022

The Tribunal examined whether the Regulatory Authority's order was within the scope of the original pleadings and directed the respondent to file a Vakalatnama and reply to the grounds of appeal before the next hearing on 01.12.2022.

FINAL_ORDEROrder ID: 0901126001752019-24-12-2021

The Tribunal allowed the appellant's application for condonation of delay, permitting the appeal to be registered as a Regular Appeal subject to a cost of Rs. 4,000/-.

INTERIM_ORDEROrder ID: 0901126001752019-01-12-2022

The Tribunal noted the respondent's failure to provide annexures to the appellant and warned that inferences would be drawn against the respondent during the hearing if these documents are not furnished.