Appellant / Complainant
Pawan Kumar
Respondent
Yamuna Expressway Industrial Development Authority
₹21,72,587
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126001742019 by Pawan Kumar against Yamuna Expressway Industrial Development Authority before up_rera.
Re-Hearing
The Tribunal partially allowed the appeal, modifying the previous order to direct the respondent to pay delay interest at the rate of MCLR+1% per annum from the date of delay (22.11.2013) until the offer of possession or obtaining OC/CC, whichever is later.
Hearing
The Tribunal heard arguments regarding the calculation of delay interest and subsequently reserved its judgment for a later date.
Hearing
The Tribunal has adjourned the appeal to 25.09.2024 following a joint request from both parties.
Hearing
The Tribunal adjourned the proceedings of Appeal-408/2022 and scheduled the matter for orders or hearing on 23.08.2024.
Hearing
The Tribunal adjourned the appeal to 22.07.2024 because the appellant's counsel was occupied with another online hearing.
Hearing
The Tribunal noted the absence of the respondent's counsel and rescheduled the defective appeal for orders/hearing on 22.05.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to him being out of station and rescheduled the hearing for 22.04.2024.
Hearing
The proceedings were adjourned at the request of the appellant's counsel and the matter is scheduled for hearing on 15.03.2024.
Hearing
The Tribunal refers the parties to a previous order passed in Appeal No. 407/2022 for further directions.
Hearing
The Tribunal adjourned the proceedings to 01.11.2023 because the counsel for the respondent was reported to be ill.
Hearing
The Tribunal granted the appellant a one-week extension to comply with a previous order dated 14.07.2023 and to file a reply to the respondent's objections, scheduling the next hearing for 20.09.2023.
Final Hearing
The Tribunal directed the appellant's counsel to place the online complaint filed before the Regulatory Authority on record within one week and scheduled the matter for hearing on 03.08.2023.
Final Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal for a hearing on 14.07.2023.
Final Hearing
The Tribunal has rescheduled the hearing for Appeal-408/2022 to July 5, 2023, due to lack of time in the current session.
Final Hearing
Upon a joint request from the counsels for both parties, the Tribunal adjourned the hearing of Appeal-408/2022 to 05.12.2022.
Further Order
The Tribunal allowed an adjournment application filed by the respondent's counsel and rescheduled the appeal for a final hearing on 05.12.2022.
Further Order
The parties have reached a preliminary agreement regarding interest rates for delayed possession, with the appellant offering MCLR+1% and the respondent offering 6% interest, and the matter is listed for further hearing on 10.11.2022.
Further Order
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the hearing for October 11, 2022.
Further Order
The Tribunal noted the exchange of pleadings and directed both parties to file lists of dates and events, along with cited cases, at least 10 days before the next hearing on 08.09.2022.
for delivery of Judgment/Order
The U.P. Real Estate Appellate Tribunal condoned a 94-day delay in filing four consolidated appeals (Misc. Cases No. 606/2019 to 609/2019) upon payment of costs of Rs. 3,000 per case, and ordered them to be registered as regular appeals.
Hearing
The Tribunal heard arguments regarding a limitation application and granted the applicant 10 days to file supporting case laws before reserving judgment.
Hearing
The Tribunal noted the absence of both parties during the hearing and ordered that notices be issued to the parties and their counsels via email, scheduling the next hearing for 28.10.2021.
Tribunal Order #0901126001742019-11-10-2022
The parties have reached a preliminary agreement regarding interest rates for delayed possession, with the appellant offering MCLR+1% and the respondent offering 6% interest, and the matter is listed for further hearing on 10.11.2022.
Tribunal Order #0901126001742019-11-07-2025
The Tribunal partially allowed the appeal, modifying the previous order to direct the respondent to pay delay interest at the rate of MCLR+1% per annum from the date of delay (22.11.2013) until the offer of possession or obtaining OC/CC, whichever is later.
Tribunal Order #0901126001742019-13-06-2022
The U.P. Real Estate Appellate Tribunal condoned a 94-day delay in filing four consolidated appeals (Misc. Cases No. 606/2019 to 609/2019) upon payment of costs of Rs. 3,000 per case, and ordered them to be registered as regular appeals.
Tribunal Disposal & Final Award Ruling
The Tribunal partially allowed the appeal, modifying the previous order to direct the respondent to pay delay interest at the rate of MCLR+1% per annum from the date of delay (22.11.2013) until the offer of possession or obtaining OC/CC, whichever is later. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% p.a..
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal partially allowed the appeal, modifying the previous order to direct the respondent to pay delay interest at the rate of MCLR+1% per annum from the date of delay (22.11.2013) until the offer of possession or obtaining OC/CC, whichever is later.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR + 1% p.a.
Interest Period
from the date of delay, i.e., 22.11.2013 till offer of possession/obtaining of OC/CC whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Amit Yadav
Respondent Advocate(s)
- Ankit Raj Chaudhary
Official RERA Tribunal Orders (3)
The parties have reached a preliminary agreement regarding interest rates for delayed possession, with the appellant offering MCLR+1% and the respondent offering 6% interest, and the matter is listed for further hearing on 10.11.2022.
The Tribunal partially allowed the appeal, modifying the previous order to direct the respondent to pay delay interest at the rate of MCLR+1% per annum from the date of delay (22.11.2013) until the offer of possession or obtaining OC/CC, whichever is later.
The U.P. Real Estate Appellate Tribunal condoned a 94-day delay in filing four consolidated appeals (Misc. Cases No. 606/2019 to 609/2019) upon payment of costs of Rs. 3,000 per case, and ordered them to be registered as regular appeals.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.