up_reraStatus: Completed
CASE ID: 0901126001712020

Appellant / Complainant

Ansal Properties & Infrastructure Pvt. Ltd.

VS

Respondent

U.P. Real Estate Regulatory Authority, Anr

Developer Firm

ansal properties & infrastructure pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Refund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

20 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126001712020 by Ansal Properties & Infrastructure Pvt. Ltd. against U.P. Real Estate Regulatory Authority, Anr before up_rera.

Refund of InvestmentDelay Compensation / Interest
2
Stage 106/04/2022

Delay condonation

The Tribunal rejected the applicant's application for condonation of delay, dismissed the appeal, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.

3
Stage 215/03/2022

Delay condonation

The Tribunal granted the applicant one week to file a better affidavit regarding the application for condonation of delay and scheduled the matter for hearing on 06.04.2022.

4
Stage 307/01/2022

Delay condonation

The Tribunal adjourned the matter to 02.02.2022 for the disposal of a limitation application and any related objections.

5
Stage 406/12/2021

Delay condonation

The Tribunal granted a short adjournment at the request of the applicant's counsel and scheduled the matter for further orders on 07.01.2022.

6
Stage 516/11/2021

Hearing

The Tribunal granted a request to list the case for hearing on 06.12.2021 to consider an application for condonation of delay.

7
Stage 608/10/2021

Delay condonation

The Tribunal granted a one-week extension to the applicant to file a vakalatnama and rescheduled the defective appeal for hearing on 16.11.2021.

8
Stage 722/09/2021

Delay condonation

The Tribunal granted the counsel for the appellant one week to file an application seeking permission to withdraw his vakalatnama due to personal difficulties and rescheduled the matter to 08.10.2021.

9
Stage 803/05/2021

Delay condonation

No text available.

10
Stage 909/04/2021

Delay condonation

No text available.

11
Stage 1025/03/2021

For Order

No text available.

12
Stage 1103/03/2021

Hearing

The appeal is adjourned due to a lawyer strike, with the matter rescheduled for 25.03.2021 to hear an application for condonation of delay and a direction for parties to exchange pleadings.

13
Stage 1210/02/2021

For Order

The Tribunal reprimanded the applicant's counsel for failing to serve replies to objections in a timely manner and directed that the appeal be listed on 03.03.2021 for consideration of the condonation of delay application.

14
Stage 1327/01/2021

Further Consideration

The Tribunal granted a request by the appellant's counsel to adjourn the matter and rescheduled the case for hearing on 10.02.2021.

15
Stage 1407/01/2021

Defect Removal

No text available.

16
Stage 1504/11/2020

Defect Removal

No text available.

17
Stage 1609/10/2020

Defect Removal

No text available.

18
Stage 17Final Ruling Order

Tribunal Order #0901126001712020-06-04-2022

The Tribunal rejected the applicant's application for condonation of delay, dismissed the appeal, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.

19
Stage 18Interim Order

Tribunal Order #0901126001712020-10-02-2021

The Tribunal reprimanded the applicant's counsel for failing to serve replies to objections in a timely manner and directed that the appeal be listed on 03.03.2021 for consideration of the condonation of delay application.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the applicant's application for condonation of delay, dismissed the appeal, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the applicant's application for condonation of delay, dismissed the appeal, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saurabh Misra
  • Krishna Kumar Singh
  • Gautam Johri

Respondent Advocate(s)

  • Tarun Prakash Srivastava

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126001712020-06-04-2022

The Tribunal rejected the applicant's application for condonation of delay, dismissed the appeal, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.

INTERIM_ORDEROrder ID: 0901126001712020-10-02-2021

The Tribunal reprimanded the applicant's counsel for failing to serve replies to objections in a timely manner and directed that the appeal be listed on 03.03.2021 for consideration of the condonation of delay application.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ansal properties & infrastructure pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →