up_reraStatus: Completed
CASE ID: 0901126001632019

Appellant / Complainant

Rajednder Singh Manav

VS

Respondent

Yamuna Expressway Industrial Development Authority

Disputed Amount

39,01,835

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

43 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126001632019 by Rajednder Singh Manav against Yamuna Expressway Industrial Development Authority before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 108/07/2025

Hearing

The U.P. Real Estate Appellate Tribunal modified the previous order to mandate that the respondent pay delay interest at a uniform rate of MCLR+1% per annum from the date of delay (21.11.2013) until the offer of possession or obtaining OC/CC, overriding the lower 6% rate previously granted.

3
Stage 202/07/2025

Hearing

The Tribunal has scheduled the appeal for final arguments on July 8, 2025.

4
Stage 302/05/2025

For Order

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the case for orders on July 2, 2025, noting that no further adjournments will be permitted for the appellant.

5
Stage 408/04/2025

For Order

The Tribunal denied a request for further adjournment by the respondent's counsel due to illness and scheduled the appeal for hearing on 02.05.2025.

6
Stage 512/03/2025

For Order

The Tribunal noted the absence of the respondent's counsel and adjourned the matter to 08.04.2025 for orders.

7
Stage 606/02/2025

For Order

The Tribunal granted an adjournment requested by the appellant's counsel due to him being out of station and rescheduled the case for orders on 12.03.2025.

8
Stage 723/01/2025

For Order

The Tribunal granted a request to adjourn the matter due to the absence of the respondent's counsel and scheduled the appeal for orders on 06.02.2025.

9
Stage 807/01/2025

For Order

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the matter for orders on 23.01.2025.

10
Stage 925/09/2024

Hearing

The Tribunal heard arguments regarding the calculation of delay interest and subsequently reserved its judgment for future pronouncement.

11
Stage 1023/08/2024

Hearing

The Tribunal has rescheduled the hearing of Appeal-410/2022 to 25.09.2024 following a joint request from both parties.

12
Stage 1122/07/2024

Hearing

The Tribunal adjourned the proceedings in the interest of justice and scheduled the appeal for orders/hearing on 23.08.2024.

13
Stage 1222/05/2024

Hearing

The appeal has been adjourned to 22.07.2024 because the counsel for the appellant was unavailable due to a conflicting online hearing.

14
Stage 1322/04/2024

Hearing

The Tribunal noted the absence of the respondent's counsel and rescheduled the hearing for the defective appeal to 22.05.2024.

15
Stage 1415/03/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to him being out of station and rescheduled the hearing for 22.04.2024.

16
Stage 1526/02/2024

Hearing

The U.P. Real Estate Appellate Tribunal has adjourned the proceedings at the request of the appellant's counsel and rescheduled the hearing for March 15, 2024.

17
Stage 1631/01/2024

Hearing

The Tribunal refers the parties to a previous order passed in appeal No. 407/2022 for further directions.

18
Stage 1701/11/2023

Hearing

No text available.

19
Stage 1820/09/2023

Hearing

The Tribunal adjourned the proceedings to 01.11.2023 because counsel for the respondent was reported to be ill.

20
Stage 1903/08/2023

Hearing

The Tribunal granted the appellant a one-week extension to comply with a previous order dated 14.07.2023 and to file a reply to the respondent's objections, scheduling the next hearing for 20.09.2023.

21
Stage 2014/07/2023

Final Hearing

The Tribunal directed the appellant's counsel to file the online complaint previously submitted to the Regulatory Authority within one week and scheduled the matter for hearing on 03.08.2023.

22
Stage 2105/07/2023

Final Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal for a hearing on 14.07.2023.

23
Stage 2227/04/2023

Final Hearing

The Tribunal has rescheduled the hearing for Appeal-410/2022 to 05.07.2023 due to insufficient time remaining on the current list.

24
Stage 2320/03/2023

Final Hearing

No text available.

25
Stage 2409/02/2023

Final Hearing

No text available.

26
Stage 2505/01/2023

Final Hearing

No text available.

27
Stage 2605/12/2022

Final Hearing

No text available.

28
Stage 2719/11/2022

Final Hearing

The Tribunal granted a joint request from the counsels of both parties to adjourn the hearing and rescheduled the appeal for 05.12.2022.

29
Stage 2810/11/2022

Final Hearing

The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the appeal for final hearing on 05.12.2022.

30
Stage 2911/10/2022

Final Hearing

The Tribunal recorded the respective submissions of both parties regarding interest rates for delayed possession and listed the appeal for a hearing on 10.11.2022.

31
Stage 3008/09/2022

Final Hearing

The Tribunal allowed an adjournment application filed by the respondent's counsel and rescheduled the hearing for October 11, 2022.

32
Stage 3108/08/2022

Notice

The Tribunal noted that pleadings have been exchanged and directed the parties to file a list of dates, events, and relied-upon cases at least 10 days before the next hearing scheduled for September 8, 2022.

33
Stage 3213/06/2022

for delivery of Judgment/Order

The Tribunal condoned the 94-day delay in filing the appeals for Misc. Cases No. 606/2019 through 609/2019, subject to a cost of Rs. 3,000 per case to be deposited in the Tribunal's fund, and ordered them to be registered as regular appeals.

34
Stage 3328/10/2021

Hearing

The Tribunal heard arguments regarding a limitation application, noted that the respondent filed no objection, and reserved judgment while allowing the applicant ten days to submit supporting case law.

35
Stage 3415/09/2021

Hearing

The Tribunal noted the absence of both parties during the hearing and ordered that notices be issued to the parties and their counsels via email, with the case scheduled for further orders on 28.10.2021.

36
Stage 3515/04/2021

For Order

No text available.

37
Stage 3619/03/2021

Delay condonation

No text available.

38
Stage 3722/02/2021

Hearing

No text available.

39
Stage 3819/01/2021

Delay condonation

No text available.

40
Stage 3902/12/2020

Delay condonation

No text available.

41
Stage 40Final Ruling Order

Tribunal Order #0901126001632019-08-07-2025

The U.P. Real Estate Appellate Tribunal modified the previous order to mandate that the respondent pay delay interest at a uniform rate of MCLR+1% per annum from the date of delay (21.11.2013) until the offer of possession or obtaining OC/CC, overriding the lower 6% rate previously granted.

42
Stage 41Interim Order

Tribunal Order #0901126001632019-13-06-2022

The Tribunal condoned the 94-day delay in filing the appeals for Misc. Cases No. 606/2019 through 609/2019, subject to a cost of Rs. 3,000 per case to be deposited in the Tribunal's fund, and ordered them to be registered as regular appeals.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal modified the previous order to mandate that the respondent pay delay interest at a uniform rate of MCLR+1% per annum from the date of delay (21.11.2013) until the offer of possession or obtaining OC/CC, overriding the lower 6% rate previously granted. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% p.a..

Disposal Winner: AppellantInterest Rate: MCLR + 1% p.a.Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal modified the previous order to mandate that the respondent pay delay interest at a uniform rate of MCLR+1% per annum from the date of delay (21.11.2013) until the offer of possession or obtaining OC/CC, overriding the lower 6% rate previously granted.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1% p.a.

Interest Period

from the date of delay i.e., 21.11.2013 till offer of possession/obtaining of OC/CC whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav

Respondent Advocate(s)

  • Ankit Raj Chaudhary

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126001632019-08-07-2025

The U.P. Real Estate Appellate Tribunal modified the previous order to mandate that the respondent pay delay interest at a uniform rate of MCLR+1% per annum from the date of delay (21.11.2013) until the offer of possession or obtaining OC/CC, overriding the lower 6% rate previously granted.

INTERIM_ORDEROrder ID: 0901126001632019-13-06-2022

The Tribunal condoned the 94-day delay in filing the appeals for Misc. Cases No. 606/2019 through 609/2019, subject to a cost of Rs. 3,000 per case to be deposited in the Tribunal's fund, and ordered them to be registered as regular appeals.