up_reraStatus: Completed
CASE ID: 0901126001492019

Appellant / Complainant

Colourful Estates Pvt. Ltd.

VS

Respondent

Ramnik Jain

Developer Firm

colourful estates pvt. ltd.

Disputed Amount

37,45,825

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

13 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126001492019 by Colourful Estates Pvt. Ltd. against Ramnik Jain before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferJurisdiction & Maintainability
2
Stage 115/03/2022

for delivery of Judgment/Order

The Appellate Tribunal dismissed the promoter's appeal and upheld the RERA order directing the payment of interest for delayed possession, while further directing that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.

3
Stage 227/09/2021

Hearing

The appellant challenges a RERA order regarding interest for delayed possession, arguing that the completion certificate should be considered valid under the deeming provisions of the U.P. Apartment Act, 2016; judgment has been reserved.

4
Stage 313/04/2021

Hearing

No text available.

5
Stage 426/03/2021

Hearing

No text available.

6
Stage 505/03/2021

Compliance of section 43(5)

The court adjourned the hearing of Appeal-339/2019 to 26.03.2021 because lawyers were abstaining from judicial work in support of a call by the Oudh Bar Association.

7
Stage 618/02/2021

For Order

The Tribunal granted a request for adjournment from the appellant's counsel due to being out of station and rescheduled the defective appeal for hearing on 05.03.2021.

8
Stage 727/01/2021

For Order

The Tribunal adjourned the appeal for two weeks to allow the appellant to negotiate with the respondent regarding the issue of interest for delay.

9
Stage 813/01/2021

Further Order

No text available.

10
Stage 908/12/2020

Further Order

No text available.

11
Stage 10Interim Order

Tribunal Order #0901126001492019-27-09-2021

The appellant challenges a RERA order regarding interest for delayed possession, arguing that the completion certificate should be considered valid under the deeming provisions of the U.P. Apartment Act, 2016; judgment has been reserved.

12
Stage 11Final Ruling Order

Tribunal Order #0901126001492019-15-03-2022

The Appellate Tribunal dismissed the promoter's appeal and upheld the RERA order directing the payment of interest for delayed possession, while further directing that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the promoter's appeal and upheld the RERA order directing the payment of interest for delayed possession, while further directing that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.

Disposal Winner: RespondentInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the promoter's appeal and upheld the RERA order directing the payment of interest for delayed possession, while further directing that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1%

Interest Period

as per penalty mentioned in the Builder Buyer Agreement, till 30.04.2016 and at the rate of MCLR+1% from 01.05.2016

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • In Person
  • Anurag Singh

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126001492019-27-09-2021

The appellant challenges a RERA order regarding interest for delayed possession, arguing that the completion certificate should be considered valid under the deeming provisions of the U.P. Apartment Act, 2016; judgment has been reserved.

FINAL_ORDEROrder ID: 0901126001492019-15-03-2022

The Appellate Tribunal dismissed the promoter's appeal and upheld the RERA order directing the payment of interest for delayed possession, while further directing that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee.

TathyaGrid RERA Intelligence AI

Need to research all rulings for colourful estates pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →