up_reraStatus: Completed
CASE ID: 0901126001432022

Appellant / Complainant

Saurabh Dixit, Neelam Dixit

VS

Respondent

Lucknow Development Authority

Disputed Amount

23,63,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional MisrepresentationJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

24 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126001432022 by Saurabh Dixit, Neelam Dixit against Lucknow Development Authority before up_rera.

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional MisrepresentationJurisdiction & Maintainability
2
Stage 104/09/2024

for delivery of Judgment/Order

The Tribunal set aside the Adjudicating Officer's orders because it ruled that the officer exceeded jurisdiction by granting 'compensation' for delay to allottees who chose to stay in the project, rather than just 'interest' as prescribed by the Regulatory Authority; additionally, it rejected the developer's claim of force majeure regarding farmer agitations.

3
Stage 204/07/2024

Hearing

The Tribunal heard arguments from both parties regarding the appeal and subsequently reserved the judgment for a later date.

4
Stage 306/05/2024

Hearing

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on July 4, 2024.

5
Stage 403/04/2024

Hearing

The Tribunal has adjourned the matter and scheduled the appeal for a hearing on May 6, 2024.

6
Stage 529/02/2024

Hearing

The Tribunal has ordered the appeal to be listed for a hearing on 03.04.2024 due to lack of time.

7
Stage 619/01/2024

Hearing

The Tribunal granted a request for adjournment from both parties and rescheduled the hearing of the appeal to 29.02.2024.

8
Stage 717/10/2023

Hearing

No text available.

9
Stage 811/09/2023

Hearing

The Tribunal adjourned the proceedings due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh and rescheduled the hearing for 17.10.2023.

10
Stage 909/08/2023

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel on personal grounds and scheduled the appeal for hearing on 11.09.2023.

11
Stage 1029/05/2023

Hearing

The Tribunal adjourned the appeal to 09.08.2023 and directed the parties to exchange pleadings in the interim.

12
Stage 1118/04/2023

Hearing

The Tribunal adjourned the proceedings to allow the respondent's counsel time to examine a late-received reply to objections and scheduled the case for hearing on 29.05.2023.

13
Stage 1203/03/2023

Hearing

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the appeal for hearing on 18.04.2023.

14
Stage 1331/01/2023

For Order

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on March 3, 2023.

15
Stage 1421/12/2022

For Order

The Tribunal granted an adjournment requested by the respondent's counsel due to his engagement at the High Court and scheduled the appeal for hearing on 31.01.2023.

16
Stage 1525/11/2022

For Order

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the appeal for a hearing on 21.12.2022 since pleadings have been exchanged.

17
Stage 1620/10/2022

For Order

The Tribunal adjourned the proceedings due to requests for adjournment from the respondent's counsel and directed the parties to exchange pleadings in the interim.

18
Stage 1719/09/2022

Exchange of pleadings

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on 20.10.2022.

19
Stage 1822/08/2022

Defect Removal

The Tribunal allowed the application for condonation of delay, excusing a 175-day delay in filing the appeal due to the COVID-19 pandemic period recognized by the Supreme Court, and ordered the defective appeal to be registered as a Regular Appeal.

20
Stage 1921/07/2022

Defect Removal

The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objections and scheduled the matter for August 16, 2022, to consider the application for condonation of delay.

21
Stage 2027/05/2022

Defect Removal

The Tribunal directed the respondent to file their Vakalatnama, objections to the condonation of delay application, and grounds of appeal before the next hearing date.

22
Stage 21Final Ruling Order

Tribunal Order #0901126001432022-04-09-2024

The Tribunal set aside the Adjudicating Officer's orders because it ruled that the officer exceeded jurisdiction by granting 'compensation' for delay to allottees who chose to stay in the project, rather than just 'interest' as prescribed by the Regulatory Authority; additionally, it rejected the developer's claim of force majeure regarding farmer agitations.

23
Stage 22Interim Order

Tribunal Order #0901126001432022-22-08-2022

The Tribunal allowed the application for condonation of delay, excusing a 175-day delay in filing the appeal due to the COVID-19 pandemic period recognized by the Supreme Court, and ordered the defective appeal to be registered as a Regular Appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Adjudicating Officer's orders because it ruled that the officer exceeded jurisdiction by granting 'compensation' for delay to allottees who chose to stay in the project, rather than just 'interest' as prescribed by the Regulatory Authority; additionally, it rejected the developer's claim of force majeure regarding farmer agitations. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Adjudicating Officer's orders because it ruled that the officer exceeded jurisdiction by granting 'compensation' for delay to allottees who chose to stay in the project, rather than just 'interest' as prescribed by the Regulatory Authority; additionally, it rejected the developer's claim of force majeure regarding farmer agitations.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 31.05.2012 till 12.02.2019 (except from 27.04.2013 to 26.10.2016)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 14(3)Section 12Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Atul Tripathi

Respondent Advocate(s)

  • Abhishek Khare

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126001432022-04-09-2024

The Tribunal set aside the Adjudicating Officer's orders because it ruled that the officer exceeded jurisdiction by granting 'compensation' for delay to allottees who chose to stay in the project, rather than just 'interest' as prescribed by the Regulatory Authority; additionally, it rejected the developer's claim of force majeure regarding farmer agitations.

INTERIM_ORDEROrder ID: 0901126001432022-22-08-2022

The Tribunal allowed the application for condonation of delay, excusing a 175-day delay in filing the appeal due to the COVID-19 pandemic period recognized by the Supreme Court, and ordered the defective appeal to be registered as a Regular Appeal.