up_reraStatus: Completed
CASE ID: 0901126001362019

Appellant / Complainant

Nimi Homes Pvt. Ltd.

VS

Respondent

Ankit Jain

Developer Firm

nimi homes pvt. ltd.

Disputed Amount

2,50,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126001362019 by Nimi Homes Pvt. Ltd. against Ankit Jain before up_rera.

2
Stage 111/04/2023

Hearing

The Tribunal allowed the appellant's application to withdraw the appeal following an amicable settlement and directed the release of Rs. 2,50,000/- deposited by the appellant in compliance with Section 43(5) of the Act.

3
Stage 227/02/2023

Hearing

The Tribunal has ordered the appeal to be listed for a fresh hearing on 11.04.2023 because the previous judgment could not be delivered following the departure of the Presiding Member of Bench No. 2.

4
Stage 319/04/2022

Hearing

The Tribunal directed the counsels for both parties to file relevant papers within one month and reserved the judgment for further consideration.

5
Stage 425/02/2022

Hearing

The Tribunal directed the appellant to provide a statement of payments made and ordered both parties to exchange lists of dates, events, and relied-upon case law before the next hearing on 19.04.2022.

6
Stage 517/01/2022

Hearing

No text available.

7
Stage 622/12/2021

Hearing

The Tribunal noted the absence of the respondent and directed them to comply with a previous order dated 26.11.2021, while listing the appeal for hearing on 17.01.2022.

8
Stage 726/11/2021

Hearing

No text available.

9
Stage 807/10/2021

Hearing

The Tribunal directed the parties to exchange lists of dates, events, and relied-upon cases and ordered the case to be registered as a Regular Appeal, scheduling the next hearing for 26.11.2021.

10
Stage 910/09/2021

Hearing

The Tribunal granted an adjournment application moved by the counsel for the applicant and rescheduled the case hearing to 07.10.2021.

11
Stage 1006/05/2021

Arguments

No text available.

12
Stage 1109/04/2021

Arguments

No text available.

13
Stage 1216/03/2021

Hearing

No text available.

14
Stage 1309/02/2021

Hearing

The Tribunal granted an adjournment application filed by the Appellant's counsel and rescheduled the hearing for 16.03.2021.

15
Stage 1417/12/2020

Hearing

No text available.

16
Stage 1509/10/2020

Hearing

No text available.

17
Stage 16Final Ruling Order

Tribunal Order #0901126001362019-11-04-2023

The Tribunal allowed the appellant's application to withdraw the appeal following an amicable settlement and directed the release of Rs. 2,50,000/- deposited by the appellant in compliance with Section 43(5) of the Act.

18
Stage 17Interim Order

Tribunal Order #0901126001362019-25-02-2022

The Tribunal directed the appellant to provide a statement of payments made and ordered both parties to exchange lists of dates, events, and relied-upon case law before the next hearing on 19.04.2022.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appellant's application to withdraw the appeal following an amicable settlement and directed the release of Rs. 2,50,000/- deposited by the appellant in compliance with Section 43(5) of the Act. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appellant's application to withdraw the appeal following an amicable settlement and directed the release of Rs. 2,50,000/- deposited by the appellant in compliance with Section 43(5) of the Act.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shashi Kant Verma

Respondent Advocate(s)

  • Dhananjay Srivastava

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126001362019-11-04-2023

The Tribunal allowed the appellant's application to withdraw the appeal following an amicable settlement and directed the release of Rs. 2,50,000/- deposited by the appellant in compliance with Section 43(5) of the Act.

INTERIM_ORDEROrder ID: 0901126001362019-25-02-2022

The Tribunal directed the appellant to provide a statement of payments made and ordered both parties to exchange lists of dates, events, and relied-upon case law before the next hearing on 19.04.2022.