up_reraStatus: Completed
CASE ID: 0901126001352019

Appellant / Complainant

Bishnu Kumar Agrawal

VS

Respondent

Himalaya Realstate Pvt. Ltd.

Developer Firm

himalaya realstate pvt. ltd.

Disputed Amount

28,21,220

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Refund of InvestmentDelay Compensation / InterestUnfair Cancellation & Forfeiture

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126001352019 by Bishnu Kumar Agrawal against Himalaya Realstate Pvt. Ltd. before up_rera.

Refund of InvestmentDelay Compensation / InterestUnfair Cancellation & Forfeiture
2
Stage 131/05/2023

for delivery of Judgment/Order

The Appellate Tribunal set aside the Regulatory Authority's order and the developer's cancellation of allotment, directing the respondent to refund the entire amount paid by the appellant with interest at MCLR + 1% p.a. from the date of each deposit.

3
Stage 204/04/2023

Hearing

The Tribunal recorded that arguments from both the appellant and respondent were heard and formally reserved the judgment for a later date.

4
Stage 313/03/2023

Hearing

The Tribunal has scheduled the case for hearing or orders on 04.04.2023 and directed reference to a previous order passed in Appeal No. 370/2019.

5
Stage 412/11/2021

Further Order

The Tribunal heard arguments from both parties and reserved the judgment for further consideration.

6
Stage 505/10/2021

Hearing

The Tribunal addressed a dispute regarding the calculation of interest for a refund, suggesting that the parties settle by calculating the remaining balance due to the appellant after deducting previous payments and considering installments or unit allotment.

7
Stage 610/09/2021

Hearing

The Tribunal adjourned the matter to 05.10.2021 because neither party appeared despite the case being called several times.

8
Stage 706/05/2021

Arguments

No text available.

9
Stage 809/04/2021

Arguments

No text available.

10
Stage 916/03/2021

Further Order

The order records the appearance of the respondent's representative while noting the absence of the appellant during the court call on 16.03.2021.

11
Stage 1018/02/2021

Final Hearing

No text available.

12
Stage 1113/01/2021

Further Order

No text available.

13
Stage 1224/11/2020

Further Order

No text available.

14
Stage 13Final Ruling Order

Tribunal Order #0901126001352019-31-05-2023

The Appellate Tribunal set aside the Regulatory Authority's order and the developer's cancellation of allotment, directing the respondent to refund the entire amount paid by the appellant with interest at MCLR + 1% p.a. from the date of each deposit.

15
Stage 14Interim Order

Tribunal Order #0901126001352019-05-10-2021

The Tribunal addressed a dispute regarding the calculation of interest for a refund, suggesting that the parties settle by calculating the remaining balance due to the appellant after deducting previous payments and considering installments or unit allotment.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal set aside the Regulatory Authority's order and the developer's cancellation of allotment, directing the respondent to refund the entire amount paid by the appellant with interest at MCLR + 1% p.a. from the date of each deposit. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% p.a..

Disposal Winner: AppellantInterest Rate: MCLR + 1% p.a.Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal set aside the Regulatory Authority's order and the developer's cancellation of allotment, directing the respondent to refund the entire amount paid by the appellant with interest at MCLR + 1% p.a. from the date of each deposit.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1% p.a.

Interest Period

from the date of deposit till the date of actual refund

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Bishnu Kr. Agarwal(huf)

Respondent Advocate(s)

  • Chander Shekhar Azad

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126001352019-31-05-2023

The Appellate Tribunal set aside the Regulatory Authority's order and the developer's cancellation of allotment, directing the respondent to refund the entire amount paid by the appellant with interest at MCLR + 1% p.a. from the date of each deposit.

INTERIM_ORDEROrder ID: 0901126001352019-05-10-2021

The Tribunal addressed a dispute regarding the calculation of interest for a refund, suggesting that the parties settle by calculating the remaining balance due to the appellant after deducting previous payments and considering installments or unit allotment.

TathyaGrid RERA Intelligence AI

Need to research all rulings for himalaya realstate pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →