up_reraStatus: Completed
CASE ID: 0901126001122019

Appellant / Complainant

Sushma Shukla

VS

Respondent

Lucknow Development Authority

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

42 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126001122019 by Sushma Shukla against Lucknow Development Authority before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 101/04/2025

Hearing

The Tribunal set aside the Regulatory Authority's order and ruled that a one-sided settlement cannot waive a promoter's statutory obligation to pay delay interest under Section 18(1) of the Act; consequently, the appellant is awarded interest at MCLR +1% from the promised completion date until physical possession.

3
Stage 210/03/2025

Hearing

The matter is a part-heard appeal scheduled to be listed before Bench No. 2 on April 1, 2025.

4
Stage 304/03/2025

Hearing

The Tribunal has adjourned the matter to 10.03.2025 to allow the appellant's counsel time to respond to arguments regarding a settlement and the waiver of delay interest.

5
Stage 403/03/2025

Hearing

The Tribunal granted the respondent a final 24-hour extension to file a reply/case law and scheduled the appeal for a final hearing on March 4, 2025, noting that no further adjournments will be permitted.

6
Stage 527/02/2025

Hearing

The Tribunal granted the respondent time to reply to a cited judgment and scheduled the appeal for final hearing on March 3, 2025, with a strict warning against further adjournments.

7
Stage 607/02/2025

For Order

Upon the request of the appellant's counsel, the tribunal has adjourned the appeal to be listed for hearing on 27.02.2025.

8
Stage 705/02/2025

For Order

The Tribunal heard arguments from counsel for both parties and adjourned the matter for further hearing on 07.02.2025.

9
Stage 817/01/2025

For Order

The Tribunal has scheduled the case for orders or hearing on February 5, 2025.

10
Stage 930/08/2024

Hearing

The Tribunal heard arguments from both parties regarding the appeal and has reserved its judgment.

11
Stage 1012/08/2024

Hearing

The Tribunal granted a final opportunity to the respondent's counsel to prepare their brief and adjourned the matter to 30.08.2024 for hearing.

12
Stage 1112/07/2024

Hearing

No text available.

13
Stage 1221/05/2024

Hearing

The Tribunal granted an adjournment to the appellant's counsel to prepare a brief and rescheduled the hearing for July 12, 2024.

14
Stage 1323/04/2024

Hearing

The Tribunal granted a request for adjournment and rescheduled the appeal for hearing/orders on 21.05.2024.

15
Stage 1418/04/2024

Hearing

The Tribunal granted a request from the respondent's counsel to reschedule the hearing of the matter to 23.04.2024.

16
Stage 1520/03/2024

Hearing

The Tribunal granted a request from both parties' counsel to reschedule the hearing of Appeal-100/2019 to 18.04.2024.

17
Stage 1615/03/2024

Hearing

The Tribunal granted an adjournment to the respondent's counsel to research a specific legal issue regarding whether an undertaking not to raise disputes affects interest claims under Section 18(1), rescheduling the hearing to 20.03.2024.

18
Stage 1727/02/2024

Hearing

The Tribunal granted the respondent one week to file objections to the appellant's amended memo of appeal and scheduled the next hearing for 15.03.2024, noting that no further adjournments will be permitted due to the age of the case.

19
Stage 1824/01/2024

Hearing

The Tribunal allowed the appellant's application (IA No. 2456/2023) to amend the grounds and relief in the memo of appeal, directing specific timelines for filing amended copies and subsequent objections.

20
Stage 1926/10/2023

Hearing

No text available.

21
Stage 2014/09/2023

Hearing

The Tribunal adjourned the proceedings due to a call by the Bar Council of Uttar Pradesh for lawyers to abstain from judicial work, rescheduling the hearing for 26.10.2023.

22
Stage 2108/08/2023

Hearing

The Tribunal granted the appellant one week to file a fresh amendment application regarding the grounds of appeal and directed that a soft copy be provided to the respondent.

23
Stage 2226/05/2023

Hearing

No text available.

24
Stage 2321/04/2023

Hearing

Due to the non-appearance of the respondent (Lucknow Development Authority) despite prior warnings regarding counsel changes, the Tribunal decided to proceed ex-parte against them and scheduled an ex-parte hearing for 26.05.2023.

25
Stage 2417/03/2023

Hearing

The Tribunal adjourned the proceedings due to the absence of counsel for both parties and scheduled the next hearing for April 21, 2023.

26
Stage 2508/02/2023

Hearing

No text available.

27
Stage 2622/12/2022

Hearing

The Tribunal adjourned the matter due to lack of time and scheduled the appeal for hearing on 08.02.2023.

28
Stage 2715/11/2021

Further Order

The Tribunal reserved its judgment and directed both parties to file written submissions, including a list of dates and events and cited case law, within 15 days.

29
Stage 2801/11/2021

Further Order

No text available.

30
Stage 2904/10/2021

Hearing

The case is adjourned due to the counsel for the respondent being on sanctioned leave, with the next hearing scheduled for 01.11.2021.

31
Stage 3019/04/2021

Delay condonation

No text available.

32
Stage 3125/03/2021

Hearing

No text available.

33
Stage 3215/03/2021

Hearing on Amendment Application

The Tribunal granted a request for time to examine an amendment application and adjourned the appeal to 25.03.2021.

34
Stage 3323/02/2021

Hearing

The Tribunal corrected clerical errors regarding the names of the counsel for both the appellant and respondent and scheduled the appeal for hearing on 15.03.2021.

35
Stage 3410/02/2021

For Order

The Tribunal directed the Registry to locate a missing amendment application and scheduled the appeal for a subsequent hearing on 23.02.2021.

36
Stage 3520/01/2021

Hearing on Appeal

The Tribunal granted an adjournment request from the respondent's counsel due to personal reasons and rescheduled the appeal for hearing on 10.02.2021.

37
Stage 3604/01/2021

Hearing

No text available.

38
Stage 3709/12/2020

Hearing

No text available.

39
Stage 38Final Ruling Order

Tribunal Order #0901126001122019-01-04-2025

The Tribunal set aside the Regulatory Authority's order and ruled that a one-sided settlement cannot waive a promoter's statutory obligation to pay delay interest under Section 18(1) of the Act; consequently, the appellant is awarded interest at MCLR +1% from the promised completion date until physical possession.

40
Stage 39Interim Order

Tribunal Order #0901126001122019-24-01-2024

The Tribunal allowed the appellant's application (IA No. 2456/2023) to amend the grounds and relief in the memo of appeal, directing specific timelines for filing amended copies and subsequent objections.

41
Stage 40Interim Order

Tribunal Order #0901126001122019-21-04-2023

Due to the non-appearance of the respondent (Lucknow Development Authority) despite prior warnings regarding counsel changes, the Tribunal decided to proceed ex-parte against them and scheduled an ex-parte hearing for 26.05.2023.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order and ruled that a one-sided settlement cannot waive a promoter's statutory obligation to pay delay interest under Section 18(1) of the Act; consequently, the appellant is awarded interest at MCLR +1% from the promised completion date until physical possession. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.

Disposal Winner: AppellantInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order and ruled that a one-sided settlement cannot waive a promoter's statutory obligation to pay delay interest under Section 18(1) of the Act; consequently, the appellant is awarded interest at MCLR +1% from the promised completion date until physical possession.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1%

Interest Period

from 16.11.2013 till the date of physical possession of the unit (04.06.2019), and on the amount so computed, interest at MCLR+1% till the date of payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Atul Tripathi

Respondent Advocate(s)

  • Abhishek Khare

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126001122019-01-04-2025

The Tribunal set aside the Regulatory Authority's order and ruled that a one-sided settlement cannot waive a promoter's statutory obligation to pay delay interest under Section 18(1) of the Act; consequently, the appellant is awarded interest at MCLR +1% from the promised completion date until physical possession.

INTERIM_ORDEROrder ID: 0901126001122019-24-01-2024

The Tribunal allowed the appellant's application (IA No. 2456/2023) to amend the grounds and relief in the memo of appeal, directing specific timelines for filing amended copies and subsequent objections.

INTERIM_ORDEROrder ID: 0901126001122019-21-04-2023

Due to the non-appearance of the respondent (Lucknow Development Authority) despite prior warnings regarding counsel changes, the Tribunal decided to proceed ex-parte against them and scheduled an ex-parte hearing for 26.05.2023.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →