Appellant / Complainant
Kusum Sharma
Respondent
Aadhar Infraholding Ltd.
aadhar infraholding ltd.
₹9,28,728
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126001032019 by Kusum Sharma against Aadhar Infraholding Ltd. before up_rera.
for delivery of Judgment/Order
The Tribunal dismissed five appeals against the rejection of complaints, ruling that because the respondent's project was not registered with UPRERA, neither the original complaint nor the subsequent appeals were maintainable under the precedent set in M/s Newtech Promoters and Developers Pvt. Ltd. Vs. State of U.P.
Final Hearing
The Tribunal noted the absence of both parties despite prior notice and subsequently reserved the judgment to be decided based on the available records.
Ex-Parte
The proceedings were adjourned due to the appellant's counsel being unwell, with the matter rescheduled for an ex parte hearing on 23.11.2022.
Final Hearing
The Tribunal adjourned the proceedings due to the illness of the appellant's counsel and scheduled the matter for an ex-parte hearing on 18.10.2022.
Final Hearing
The Tribunal directed that this appeal be listed for hearing on 20.09.2022, referencing a previous order passed in a related matter (Appeal No. 30/2019).
Final Hearing
The Tribunal directed the respondent to file a reply to the grounds of appeal or face ex-parte proceedings and ordered both parties to exchange concise written arguments with supporting judgments before the final hearing on 29.07.2022.
Final Hearing
The Tribunal directed the parties to exchange lists of dates, events, and relied-upon cases and scheduled the matter for hearing on 20.05.2022.
Final Hearing
The Tribunal granted the appellant's request for more time to present arguments and scheduled the case for a final hearing on 19.04.2022.
Final Hearing
The hearing is adjourned to 28.01.2022 because the appellant's counsel met with an accident and is currently bedridden.
Final Hearing
The Tribunal decided to proceed with an ex-parte hearing against the respondent due to their failure to appear or file objections, and subsequently adjourned the matter to 07.01.2022 at the appellant's request for more preparation time.
Final Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to a scheduling conflict and rescheduled the hearing for 14.12.2021.
Final Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for December 9, 2021.
Hearing
The Tribunal closed the respondent's opportunity to file objections due to repeated non-appearance and failure to file replies despite previous extensions, and scheduled the matter for hearing on 23.11.2021.
Hearing
The Tribunal directed the respondent to file a reply to the appeal before the next hearing and scheduled the matter for 27.10.2021.
Hearing
The Tribunal granted the respondent 15 days to file a reply to the grounds of appeal and permitted the appellant to file a rejoinder thereafter.
Tribunal Order #0901126001032019-29-05-2023
The Tribunal dismissed five appeals against the rejection of complaints, ruling that because the respondent's project was not registered with UPRERA, neither the original complaint nor the subsequent appeals were maintainable under the precedent set in M/s Newtech Promoters and Developers Pvt. Ltd. Vs. State of U.P.
Tribunal Order #0901126001032019-14-12-2021
The Tribunal decided to proceed with an ex-parte hearing against the respondent due to their failure to appear or file objections, and subsequently adjourned the matter to 07.01.2022 at the appellant's request for more preparation time.
Tribunal Order #0901126001032019-27-10-2021
The Tribunal closed the respondent's opportunity to file objections due to repeated non-appearance and failure to file replies despite previous extensions, and scheduled the matter for hearing on 23.11.2021.
Tribunal Order #0901126001032019-20-05-2022
The Tribunal directed the respondent to file a reply to the grounds of appeal or face ex-parte proceedings and ordered both parties to exchange concise written arguments with supporting judgments before the final hearing on 29.07.2022.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed five appeals against the rejection of complaints, ruling that because the respondent's project was not registered with UPRERA, neither the original complaint nor the subsequent appeals were maintainable under the precedent set in M/s Newtech Promoters and Developers Pvt. Ltd. Vs. State of U.P. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed five appeals against the rejection of complaints, ruling that because the respondent's project was not registered with UPRERA, neither the original complaint nor the subsequent appeals were maintainable under the precedent set in M/s Newtech Promoters and Developers Pvt. Ltd. Vs. State of U.P.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Prabhat Kumar Tripathi
Respondent Advocate(s)
- Vikas Verma
- Romit Seth
Official RERA Tribunal Orders (4)
The Tribunal dismissed five appeals against the rejection of complaints, ruling that because the respondent's project was not registered with UPRERA, neither the original complaint nor the subsequent appeals were maintainable under the precedent set in M/s Newtech Promoters and Developers Pvt. Ltd. Vs. State of U.P.
The Tribunal decided to proceed with an ex-parte hearing against the respondent due to their failure to appear or file objections, and subsequently adjourned the matter to 07.01.2022 at the appellant's request for more preparation time.
The Tribunal closed the respondent's opportunity to file objections due to repeated non-appearance and failure to file replies despite previous extensions, and scheduled the matter for hearing on 23.11.2021.
The Tribunal directed the respondent to file a reply to the grounds of appeal or face ex-parte proceedings and ordered both parties to exchange concise written arguments with supporting judgments before the final hearing on 29.07.2022.