up_reraStatus: Completed
CASE ID: 0901126001002019

Appellant / Complainant

Anil Kumar Singh

VS

Respondent

Kanpur Development Authority

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

17 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126001002019 by Anil Kumar Singh against Kanpur Development Authority before up_rera.

Delay Compensation / Interest
2
Stage 118/04/2022

Final Hearing

The case was disposed of as the appellant informed the tribunal that they had obtained possession of the allotted flat and no longer wished to pursue the matter.

3
Stage 225/02/2022

Final Hearing

This text represents the header/caption of a case filing (MISC. CASE-637/2019) before the U.P. Real Estate Appellate Tribunal involving Anilkumar Singh and the Kanpur Development Authority, but contains no substantive ruling or directive.

4
Stage 317/01/2022

Final Hearing

No text available.

5
Stage 422/12/2021

Hearing

The Tribunal directed the appellant to file a better affidavit regarding the limitation application within 10 days and scheduled the case for further hearing on January 17, 2022.

6
Stage 515/12/2021

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to personal difficulty and rescheduled the hearing for the application for condonation of delay to 22.12.2021.

7
Stage 624/11/2021

Hearing

No text available.

8
Stage 729/09/2021

Hearing

The Tribunal directed the applicant to visit the Kanpur Development Authority to attempt an amicable settlement regarding a refund of Rs. 1,00,000 and pending delay penalties, ordering both parties to appear for resolution on the next date.

9
Stage 808/09/2021

Hearing

The Tribunal adjourned the case due to the absence of the respondent's counsel and directed that a notice be issued to the opposite party via email regarding the next hearing date on 29.09.2021.

10
Stage 904/05/2021

Hearing

No text available.

11
Stage 1007/04/2021

Hearing

No text available.

12
Stage 1116/03/2021

Hearing

No text available.

13
Stage 1229/01/2021

Hearing

The Tribunal directed the Kanpur Development Authority to cooperate with the applicant to amicably settle the matter regarding an excess payment of Rs. 1,00,000/-.

14
Stage 1306/11/2020

Hearing

No text available.

15
Stage 14Interim Order

Tribunal Order #0901126001002019-29-09-2021

The Tribunal directed the applicant to visit the Kanpur Development Authority to attempt an amicable settlement regarding a refund of Rs. 1,00,000 and pending delay penalties, ordering both parties to appear for resolution on the next date.

16
Stage 15Interim Order

Tribunal Order #0901126001002019-29-01-2021

The Tribunal directed the Kanpur Development Authority to cooperate with the applicant to amicably settle the matter regarding an excess payment of Rs. 1,00,000/-.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Disposed of Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Disposed of

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Kushagra Dikshit

Respondent Advocate(s)

  • Bhupendra Singh

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126001002019-29-09-2021

The Tribunal directed the applicant to visit the Kanpur Development Authority to attempt an amicable settlement regarding a refund of Rs. 1,00,000 and pending delay penalties, ordering both parties to appear for resolution on the next date.

INTERIM_ORDEROrder ID: 0901126001002019-29-01-2021

The Tribunal directed the Kanpur Development Authority to cooperate with the applicant to amicably settle the matter regarding an excess payment of Rs. 1,00,000/-.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.