Appellant / Complainant
Sameer Kumar Mishra
Respondent
Lucknow Development Authority
Unknown
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126000982020 by Sameer Kumar Mishra against Lucknow Development Authority before up_rera.
Further Order
The appellant declined to press the appeal regarding interest rates due to pending related appeals, leading the Tribunal to dispose of the matter and consign the file to the record room.
Further Order
The Tribunal granted the appellant a final opportunity to file a replication or rejoinder affidavit and adjourned the case to November 26, 2021.
Hearing
The Tribunal adjourned the matter to 28.10.2021 because the counsel for the respondent was on sanctioned leave.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to him being out of station and rescheduled the matter for hearing on 01.10.2021.
For Order
The Tribunal granted the respondent a two-week extension to file objections to the grounds of appeal and directed both parties to exchange replies via e-mail and upload documents to the e-portal before the next hearing on 08.03.2021.
For Order
The Tribunal granted the respondent two weeks to file objections to the appeal and directed the parties to exchange replies via email and upload documents to the e-Portal before the next hearing on 12.02.2021.
Tribunal Disposal & Final Award Ruling
Disposed of Awarded in favor of Unknown.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Disposed of
Ruling Awarded To
Unknown
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Alok Sinha
Respondent Advocate(s)
- Amit Yadav