CASE ID: 0901126000972020

Appellant / Complainant

Greater Noida Industrial Development Authority

VS

Respondent

Atul Kumar Chaudhari

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

20 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000972020 by Greater Noida Industrial Development Authority against Atul Kumar Chaudhari before up_rera.

2
Stage 106/04/2022

Delay condonation

The Appellate Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, while directing that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.

3
Stage 221/03/2022

Delay condonation

The Tribunal granted a 10-day extension for the appellant to file a reply to the respondent's objections and scheduled the matter for hearing on April 6, 2022.

4
Stage 302/03/2022

Delay condonation

The Tribunal has adjourned the matter to 21.03.2022 for consideration of an application for condonation of delay and a subsequent hearing.

5
Stage 419/01/2022

Delay condonation

No text available.

6
Stage 523/12/2021

Delay condonation

The Tribunal adjourned the matter to 19.01.2022 for the disposal of a pending limitation application and directed both counsels to appear or face disposal of said application.

7
Stage 625/11/2021

Delay condonation

No text available.

8
Stage 702/11/2021

Delay condonation

No text available.

9
Stage 820/10/2021

Delay condonation

The Tribunal adjourned the proceedings due to a lawyers' strike in Shahjahanpur and rescheduled the case for 02.11.2021 to address the condonation application.

10
Stage 919/10/2021

Delay condonation

No text available.

11
Stage 1015/09/2021

Delay condonation

The Tribunal noted the respondent's non-appearance despite service and directed that the matter proceed ex-parte, subsequently scheduling a hearing for 19.10.2021 to consider an application for condonation of delay.

12
Stage 1130/04/2021

Delay condonation

No text available.

13
Stage 1207/04/2021

Delay condonation

No text available.

14
Stage 1310/03/2021

For Order

The Tribunal decided to proceed ex parte against the respondent due to their repeated failure to appear or file objections despite being served notice via post and email. The case is listed for an ex parte hearing on 07.04.2021.

15
Stage 1417/02/2021

For Order

The Tribunal noted the respondent's absence despite service of notice and adjourned the defective appeal to 10.03.2021, warning that the matter may be heard ex-parte if no one appears.

16
Stage 1518/01/2021

Notice

The Tribunal noted the respondent's failure to appear despite multiple notices and adjourned the appeal to 17.02.2021, providing a timeline for filing objections and replies via email and the e-Portal.

17
Stage 1626/08/2020

Notice

No text available.

18
Stage 17Final Ruling Order

Tribunal Order #0901126000972020-06-04-2022

The Appellate Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, while directing that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.

19
Stage 18Interim Order

Tribunal Order #0901126000972020-10-03-2021

The Tribunal decided to proceed ex parte against the respondent due to their repeated failure to appear or file objections despite being served notice via post and email. The case is listed for an ex parte hearing on 07.04.2021.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, while directing that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, while directing that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rajesh Chadha

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126000972020-06-04-2022

The Appellate Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, while directing that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee during execution proceedings.

INTERIM_ORDEROrder ID: 0901126000972020-10-03-2021

The Tribunal decided to proceed ex parte against the respondent due to their repeated failure to appear or file objections despite being served notice via post and email. The case is listed for an ex parte hearing on 07.04.2021.