up_reraStatus: Completed
CASE ID: 0901126000962019

Appellant / Complainant

Arun Kumar

VS

Respondent

Mjs Infrahousing Pvt. Ltd.

Developer Firm

mjs infrahousing pvt. ltd.

Disputed Amount

2,53,125

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

14 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000962019 by Arun Kumar against Mjs Infrahousing Pvt. Ltd. before up_rera.

Delay in PossessionJurisdiction & Maintainability
2
Stage 129/09/2022

for delivery of Judgment/Order

The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the complaint was not maintainable because the appellant failed to prove 'allottee' status under the Real Estate (Regulation and Development) Act 2016 due to a lack of an allotment letter or agreement.

3
Stage 221/07/2022

Hearing

The Tribunal heard arguments from the counsel for the appellant and reserved the judgment for further delivery.

4
Stage 330/05/2022

Hearing

No text available.

5
Stage 422/04/2022

Further Order

No text available.

6
Stage 505/03/2022

for delivery of Judgment/Order

The Tribunal allowed the application for condonation of delay, finding that the appellant's delay was unintentional due to lack of notice regarding changes in regulatory review provisions, and directed the Registry to register the matter as a regular appeal.

7
Stage 625/03/2021

Further Hearing

No text available.

8
Stage 712/02/2021

Further Hearing

The Tribunal ordered that the case proceed ex-parte against opposite party no. 2 due to their repeated failure to appear despite having filed a vakalatnama, and scheduled the matter for hearing on 25.03.2021.

9
Stage 811/01/2021

Hearing

No text available.

10
Stage 905/11/2020

Hearing

No text available.

11
Stage 10Final Ruling Order

Tribunal Order #0901126000962019-29-09-2022

The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the complaint was not maintainable because the appellant failed to prove 'allottee' status under the Real Estate (Regulation and Development) Act 2016 due to a lack of an allotment letter or agreement.

12
Stage 11Interim Order

Tribunal Order #0901126000962019-05-03-2022

The Tribunal allowed the application for condonation of delay, finding that the appellant's delay was unintentional due to lack of notice regarding changes in regulatory review provisions, and directed the Registry to register the matter as a regular appeal.

13
Stage 12Interim Order

Tribunal Order #0901126000962019-12-02-2021

The Tribunal ordered that the case proceed ex-parte against opposite party no. 2 due to their repeated failure to appear despite having filed a vakalatnama, and scheduled the matter for hearing on 25.03.2021.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the complaint was not maintainable because the appellant failed to prove 'allottee' status under the Real Estate (Regulation and Development) Act 2016 due to a lack of an allotment letter or agreement. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the complaint was not maintainable because the appellant failed to prove 'allottee' status under the Real Estate (Regulation and Development) Act 2016 due to a lack of an allotment letter or agreement.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shashi Kant Verma

Respondent Advocate(s)

  • Shobhit Mohan Shukla

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126000962019-29-09-2022

The Tribunal dismissed the appeal, upholding the Regulatory Authority's decision that the complaint was not maintainable because the appellant failed to prove 'allottee' status under the Real Estate (Regulation and Development) Act 2016 due to a lack of an allotment letter or agreement.

INTERIM_ORDEROrder ID: 0901126000962019-05-03-2022

The Tribunal allowed the application for condonation of delay, finding that the appellant's delay was unintentional due to lack of notice regarding changes in regulatory review provisions, and directed the Registry to register the matter as a regular appeal.

INTERIM_ORDEROrder ID: 0901126000962019-12-02-2021

The Tribunal ordered that the case proceed ex-parte against opposite party no. 2 due to their repeated failure to appear despite having filed a vakalatnama, and scheduled the matter for hearing on 25.03.2021.

TathyaGrid RERA Intelligence AI

Need to research all rulings for mjs infrahousing pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →