Appellant / Complainant
Akhilesh Kumar Gupta
Respondent
Greater Noida Industrial Development Authority
₹9,29,100
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126000872020 by Akhilesh Kumar Gupta against Greater Noida Industrial Development Authority before up_rera.
for delivery of Judgment/Order
The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposited amount with interest at the rate of MCLR+1% per annum due to project delay.
Hearing
The court heard arguments from both counsel and reserved the judgment for a later date.
Hearing
The Tribunal directed the appellant to place on record the respondent's offer of possession and the subsequent cancellation order of the unit to evaluate actions taken following a previous RERA order.
Hearing
The Tribunal closed the respondent's opportunity to file objections to the appeal due to their failure to comply with previous directions and has ordered that the matter be heard on the basis of the existing record on 17.11.2021.
Hearing
The Tribunal granted the respondent a final two-week extension to file objections to the appeal and directed both parties to file original pleadings in the Registry before the next hearing on 22.10.2021.
Hearing on Appeal
The case was adjourned due to a lawyers' strike, with the next hearing scheduled for 22.03.2021 and parties directed to exchange pleadings in the interim.
For Order
The Tribunal adjourned the appeal to 04.03.2021 and directed the parties to exchange pleadings in the interim.
Hearing
The Tribunal corrected a clerical error regarding the respondent's counsel's name and adjourned the matter to 15.02.2021 to allow for a potential amicable settlement between the parties.
Tribunal Order #0901126000872020-21-03-2022
The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposited amount with interest at the rate of MCLR+1% per annum due to project delay.
Tribunal Order #0901126000872020-08-12-2021
The Tribunal directed the appellant to place on record the respondent's offer of possession and the subsequent cancellation order of the unit to evaluate actions taken following a previous RERA order.
Tribunal Order #0901126000872020-22-10-2021
The Tribunal closed the respondent's opportunity to file objections to the appeal due to their failure to comply with previous directions and has ordered that the matter be heard on the basis of the existing record on 17.11.2021.
Tribunal Disposal & Final Award Ruling
The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposited amount with interest at the rate of MCLR+1% per annum due to project delay. Awarded in favor of Appellant. Awarded interest rate: MCLR+1% per annum.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposited amount with interest at the rate of MCLR+1% per annum due to project delay.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1% per annum
Interest Period
from the date of deposit till the refund of the amount
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Arvind Kumar
Respondent Advocate(s)
- Rajesh Chadha
Official RERA Tribunal Orders (3)
The Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's deposited amount with interest at the rate of MCLR+1% per annum due to project delay.
The Tribunal directed the appellant to place on record the respondent's offer of possession and the subsequent cancellation order of the unit to evaluate actions taken following a previous RERA order.
The Tribunal closed the respondent's opportunity to file objections to the appeal due to their failure to comply with previous directions and has ordered that the matter be heard on the basis of the existing record on 17.11.2021.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.