up_reraStatus: Completed
CASE ID: 0901126000762019

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Shilpi Srivastava

Disputed Amount

29,60,160

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

45 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000762019 by Lucknow Development Authority against Shilpi Srivastava before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 127/05/2025

Hearing

The Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to provide the respondent with an alternate unit in the 'Sargam Apartment' project due to the abandonment of the original 'Smriti Apartment' project.

3
Stage 226/05/2025

Hearing

The Tribunal granted the appellant's request to reschedule the hearing to 27.05.2025 to ensure compliance with a previous order, while explicitly noting that no further adjournments will be permitted.

4
Stage 301/05/2025

Hearing

Upon the joint request of the counsel for both parties, the matter has been adjourned and listed for orders on 26.05.2025.

5
Stage 403/04/2025

Hearing

The Tribunal has granted a request to list the appeal for orders or hearing on May 1, 2025.

6
Stage 510/03/2025

Hearing

The Tribunal has adjourned the appeal to 03.04.2025 upon joint request of the counsel and directed the appellant to seek instructions regarding the payment of delay interest to the respondent.

7
Stage 607/02/2025

Hearing

The appeal has been adjourned at the request of the appellant's counsel and is scheduled to be listed on 10.03.2025.

8
Stage 707/01/2025

Hearing

The Tribunal heard arguments regarding a dispute over interest components and alleged unfair trade practices by the Lucknow Development Authority, and subsequently adjourned the matter for further hearing on 07.02.2025.

9
Stage 811/12/2024

Hearing

The Tribunal granted a request from the appellant's counsel to list the appeal for a hearing on January 7, 2025, and directed the respondent's counsel to supply a copy.

10
Stage 921/11/2024

Hearing

The Tribunal has adjourned the appeal to 11.12.2024 following a joint request from the counsels for both parties.

11
Stage 1011/11/2024

Hearing

The Tribunal has granted a request to list the appeal for orders or hearing on 21.11.2024.

12
Stage 1104/10/2024

Hearing

The Tribunal granted a request for adjournment made by the counsel for the appellant and rescheduled the appeal for hearing on 11.11.2024, noting that no further adjournments will be permitted.

13
Stage 1204/09/2024

Hearing

The Tribunal granted the respondent's counsel seven days to seek instructions and scheduled the matter for orders on October 4, 2024.

14
Stage 1302/08/2024

Hearing

No text available.

15
Stage 1418/07/2024

Hearing

The Tribunal granted the appellant a one-week extension to seek instructions regarding compliance with the order dated 04.04.2024 and scheduled the matter for orders on 02.08.2024.

16
Stage 1517/05/2024

Hearing

No text available.

17
Stage 1606/05/2024

Hearing

The Tribunal noted the absence of the appellant's counsel and rescheduled the appeal for orders/hearing to 17.05.2024.

18
Stage 1704/04/2024

Hearing

The Tribunal ruled that the appellant's 2018 offer of possession was invalid as it was made prior to receiving the Occupancy Certificate (OC/CC), and directed the appellant to clarify actions taken regarding possession following the Regulatory Authority's 2019 order.

19
Stage 1804/03/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to personal difficulties and rescheduled the appeal for hearing on 04.04.2024.

20
Stage 1925/01/2024

Hearing

The Tribunal noted that the appellant's counsel was out of station and scheduled the appeal for a hearing on 04.03.2024.

21
Stage 2027/10/2023

Hearing

No text available.

22
Stage 2115/09/2023

Hearing

The court has scheduled the appeal for a hearing on 27.10.2023 following a joint request from the counsels for both parties.

23
Stage 2227/07/2023

Hearing

No text available.

24
Stage 2329/05/2023

Hearing

The Tribunal granted the appellant, Lucknow Development Authority, a 10-day extension to file a reply to the respondent's objections and scheduled the next hearing for 27.07.2023.

25
Stage 2418/04/2023

Hearing

The Tribunal granted the appellant, Lucknow Development Authority, 10 days to file a reply to the respondent's objections and directed the service of a soft copy of said reply to the respondent.

26
Stage 2503/03/2023

Hearing

The Tribunal adjourned the matter to 18.04.2023 due to the absence of representation for the appellant (LDA) and issued a strict directive that no further adjournments will be granted on the next date.

27
Stage 2601/02/2023

Hearing

No text available.

28
Stage 2721/12/2022

Hearing

The Tribunal adjourned the case due to the absence of the respondent and scheduled the next hearing for February 1, 2023.

29
Stage 2819/05/2022

Part Heard

The Tribunal converted the matter from a miscellaneous case to a regular appeal and reserved the judgment for further orders.

30
Stage 2918/04/2022

Part Heard

The Tribunal granted an application for adjournment requested by the respondent's counsel and rescheduled the hearing for 19.05.2022.

31
Stage 3025/02/2022

Part Heard

The Tribunal directed the Respondent's counsel to file a physical copy of the list of dates and events in the Registry and scheduled the case for hearing on 18.04.2022.

32
Stage 3117/01/2022

Part Heard

No text available.

33
Stage 3214/12/2021

Further Order

The Tribunal directed the parties to exchange a list of dates and events and adjourned the matter to 17.01.2022 for further arguments.

34
Stage 3322/11/2021

Further Order

The Tribunal noted the filing of a rejoinder affidavit by the appellant and adjourned the matter to 14.12.2021 for further orders.

35
Stage 3425/10/2021

Further Order

The Tribunal granted the appellant permission to file a replication/rejoinder affidavit and directed the case to be listed on 22.11.2021.

36
Stage 3513/09/2021

Hearing

The Tribunal granted the appellant permission to file a replication/rejoinder affidavit in response to the respondent's reply and scheduled the next hearing for 25.10.2021.

37
Stage 3607/05/2021

Hearing

No text available.

38
Stage 3712/04/2021

Hearing

No text available.

39
Stage 3818/03/2021

Hearing

No text available.

40
Stage 3903/03/2021

Hearing

The case is adjourned to 18.03.2021 due to a lawyer strike, with a direction for parties to exchange their pleadings in the interim.

41
Stage 4004/02/2021

Hearing

The Tribunal granted an adjournment requested by the applicant and directed the applicant to upload their rejoinder/replication on the e-portal and serve a copy to the respondent's counsel.

42
Stage 4105/11/2020

Hearing

No text available.

43
Stage 42Final Ruling Order

Tribunal Order #0901126000762019-27-05-2025

The Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to provide the respondent with an alternate unit in the 'Sargam Apartment' project due to the abandonment of the original 'Smriti Apartment' project.

44
Stage 43Interim Order

Tribunal Order #0901126000762019-04-04-2024

The Tribunal ruled that the appellant's 2018 offer of possession was invalid as it was made prior to receiving the Occupancy Certificate (OC/CC), and directed the appellant to clarify actions taken regarding possession following the Regulatory Authority's 2019 order.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to provide the respondent with an alternate unit in the 'Sargam Apartment' project due to the abandonment of the original 'Smriti Apartment' project. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to provide the respondent with an alternate unit in the 'Sargam Apartment' project due to the abandonment of the original 'Smriti Apartment' project.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • Vaibhav Srivastava

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126000762019-27-05-2025

The Tribunal dismissed the appeal filed by Lucknow Development Authority, upholding the Regulatory Authority's order to provide the respondent with an alternate unit in the 'Sargam Apartment' project due to the abandonment of the original 'Smriti Apartment' project.

INTERIM_ORDEROrder ID: 0901126000762019-04-04-2024

The Tribunal ruled that the appellant's 2018 offer of possession was invalid as it was made prior to receiving the Occupancy Certificate (OC/CC), and directed the appellant to clarify actions taken regarding possession following the Regulatory Authority's 2019 order.