Appellant / Complainant
Rajiv Saini
Respondent
Aadhar Infraholding Limited
aadhar infraholding limited
₹9,28,728
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126000742019 by Rajiv Saini against Aadhar Infraholding Limited before up_rera.
for delivery of Judgment/Order
The Tribunal dismissed five appeals filed by homebuyers against M/s Aadhar Infraholding Ltd., ruling that because the project was not registered with RERA, the complaints and appeals were not maintainable under the precedent set in M/s Newtech Promoters and Developers Pvt. Ltd. Vs. State of U.P.
Final Hearing
The Tribunal noted the absence of both parties despite prior notice and subsequently reserved judgment to be decided based on the existing pleadings and documents on record.
Ex-Parte
The Tribunal granted an adjournment of the proceedings due to the illness of the appellant's counsel and rescheduled the ex parte hearing for 23.11.2022.
Final Hearing
The Tribunal adjourned the proceedings due to the illness of the appellant's counsel and scheduled an ex-parte hearing for 18.10.2022.
Final Hearing
The Tribunal closed the respondent's opportunity to file objections and ordered the matter to proceed ex parte due to their failure to respond despite being represented by counsel.
Final Hearing
The Tribunal directed the respondent to file a reply to the grounds of appeal or face ex-parte proceedings and ordered both parties to exchange concise written arguments before the next hearing on 29.07.2022.
Final Hearing
The Tribunal directed the parties to exchange lists of dates, events, and relied-upon cases before the next hearing, which is scheduled for May 20, 2022.
Final Hearing
The Tribunal granted the appellant's request for more time to present arguments and scheduled the case for a final hearing on 19.04.2022.
Final Hearing
The appeal is adjourned to 28.01.2022 because the appellant's counsel met with an accident and is currently bedridden.
Final Hearing
The Tribunal decided to proceed ex-parte against the respondent due to their failure to file objections despite repeated opportunities and granted the appellant additional time to prepare his brief, scheduling the next hearing for 07.01.2022.
Final Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to his unavailability and rescheduled the hearing for 14.12.2021.
Final Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the hearing for December 9, 2021.
Hearing
The Tribunal closed the respondent's opportunity to file objections due to repeated non-appearance and failure to file a reply since 2019, directing that the appeal be heard based on available records.
Hearing
The Tribunal directed the respondent to file a reply to the appeal before the next hearing and scheduled the matter for 27.10.2021.
Hearing
The Tribunal granted the respondent 15 days to file a reply to the grounds of appeal and scheduled the next hearing for April 15, 2021.
Tribunal Order #0901126000742019-29-05-2023
The Tribunal dismissed five appeals filed by homebuyers against M/s Aadhar Infraholding Ltd., ruling that because the project was not registered with RERA, the complaints and appeals were not maintainable under the precedent set in M/s Newtech Promoters and Developers Pvt. Ltd. Vs. State of U.P.
Tribunal Order #0901126000742019-14-12-2021
The Tribunal decided to proceed ex-parte against the respondent due to their failure to file objections despite repeated opportunities and granted the appellant additional time to prepare his brief, scheduling the next hearing for 07.01.2022.
Tribunal Order #0901126000742019-27-10-2021
The Tribunal closed the respondent's opportunity to file objections due to repeated non-appearance and failure to file a reply since 2019, directing that the appeal be heard based on available records.
Tribunal Order #0901126000742019-25-08-2022
The Tribunal closed the respondent's opportunity to file objections and ordered the matter to proceed ex parte due to their failure to respond despite being represented by counsel.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed five appeals filed by homebuyers against M/s Aadhar Infraholding Ltd., ruling that because the project was not registered with RERA, the complaints and appeals were not maintainable under the precedent set in M/s Newtech Promoters and Developers Pvt. Ltd. Vs. State of U.P. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed five appeals filed by homebuyers against M/s Aadhar Infraholding Ltd., ruling that because the project was not registered with RERA, the complaints and appeals were not maintainable under the precedent set in M/s Newtech Promoters and Developers Pvt. Ltd. Vs. State of U.P.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Prabhat Kumar Tripathi
- Romit Seth
Respondent Advocate(s)
- Vikas Verma
Official RERA Tribunal Orders (4)
The Tribunal dismissed five appeals filed by homebuyers against M/s Aadhar Infraholding Ltd., ruling that because the project was not registered with RERA, the complaints and appeals were not maintainable under the precedent set in M/s Newtech Promoters and Developers Pvt. Ltd. Vs. State of U.P.
The Tribunal decided to proceed ex-parte against the respondent due to their failure to file objections despite repeated opportunities and granted the appellant additional time to prepare his brief, scheduling the next hearing for 07.01.2022.
The Tribunal closed the respondent's opportunity to file objections due to repeated non-appearance and failure to file a reply since 2019, directing that the appeal be heard based on available records.
The Tribunal closed the respondent's opportunity to file objections and ordered the matter to proceed ex parte due to their failure to respond despite being represented by counsel.
Need to research all rulings for aadhar infraholding limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.