up_reraStatus: Completed
CASE ID: 0901126000512018

Appellant / Complainant

Vijay Sharma

VS

Respondent

S.V.P Builder

Developer Firm

s.v.p builder

Disputed Amount

21,79,353

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

31 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000512018 by Vijay Sharma against S.V.P Builder before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferJurisdiction & Maintainability
2
Stage 112/12/2025

for delivery of Judgment/Order

The Appellate Tribunal set aside the Regulatory Authority's order, directing the promoter to pay delay interest at MCLR+1% from 25.09.2014 to 27.11.2019 and to deliver possession of the top-floor flat (Gokul-1-1401) after adjusting the payable interest against the remaining consideration.

3
Stage 217/09/2025

Part Heard

The Tribunal heard arguments from both counsels regarding the appeal and its objections, subsequently reserving the judgment for further decision.

4
Stage 303/09/2025

Part Heard

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the appeal for hearing on 17.09.2025.

5
Stage 426/08/2025

Part Heard

The Tribunal granted a request to list the appeal for orders or hearing on September 3, 2025, before Bench No. 2.

6
Stage 522/08/2025

Part Heard

The Tribunal adjourned the appeal to 26.08.2025 and issued a strict warning that no further adjournments will be granted, noting that the matter may proceed based on available records if counsel fail to appear.

7
Stage 606/08/2025

Part Heard

The Tribunal heard arguments from both parties and scheduled the appeal for a final hearing on August 22, 2025.

8
Stage 728/07/2025

Part Heard

Upon a joint request from the counsel for both parties, the tribunal adjourned the matter and scheduled the next hearing for August 6, 2025.

9
Stage 807/07/2025

Part Heard

The Tribunal ordered that the appeal be tied up to Bench No. 2 and scheduled for hearing/orders on 28.07.2025.

10
Stage 906/05/2025

Hearing

The Tribunal heard arguments from both parties and adjourned the appeal to July 7, 2025, for further arguments.

11
Stage 1010/04/2025

Hearing

The Tribunal granted a request to list the appeal for orders or hearing on May 6, 2025.

12
Stage 1103/04/2025

Hearing

The Tribunal granted a request from the respondent's counsel to list the appeal for hearing on 10.04.2025, noting that no further adjournments will be permitted.

13
Stage 1205/03/2025

Hearing

The Tribunal granted an adjournment application filed by the respondent and rescheduled the hearing for April 3, 2025.

14
Stage 1311/02/2025

Hearing

The Tribunal granted the respondent one week to upload the Occupancy Certificate (OC) or Completion Certificate (CC) to the record and scheduled the case for hearing on March 5, 2025.

15
Stage 1429/01/2025

Hearing

The Tribunal directed the Registry to send a reminder to RERA to summon the case records and scheduled the matter for orders on 11.02.2025.

16
Stage 1517/01/2025

Hearing

The Tribunal granted time to both parties to upload necessary documents (allotment letter, tripartite agreement, and legible BBA) and directed the Registry to summon records from the U.P. Real Estate Regulatory Authority for the next hearing on 29.01.2025.

17
Stage 1613/12/2024

Hearing

The Tribunal directed the respondent to file legible copies of the allotment letter, BBA, and Tripartite Agreement within 15 days and ordered the Registry to summon the original complaint records from the Regulatory Authority.

18
Stage 1713/11/2024

Hearing

The proceedings were adjourned at the request of the respondent's counsel, with the matter rescheduled for hearing on 13.12.2024.

19
Stage 1804/10/2024

Hearing

The Tribunal directed the appellant to file a rejoinder affidavit to the respondent's objections within one week and scheduled the next hearing for 13.11.2024.

20
Stage 1904/09/2024

Hearing

The Tribunal granted the respondent a final seven-day extension to file objections and provide a soft copy to the appellant, with the matter scheduled for hearing on 04.10.2024.

21
Stage 2002/08/2024

Hearing

No text available.

22
Stage 2103/07/2024

Hearing

The Tribunal granted the respondent one week to file objections to the grounds of appeal and directed the appellant to reply within a week thereafter, scheduling the next hearing for August 2, 2024.

23
Stage 2203/05/2024

Hearing

The Tribunal directed the appellant to upload a soft copy of the appeal to the portal and provide physical copies to the respondent within one week to facilitate the filing of objections. The order also establishes a timeline for the respondent's objection and the appellant's subsequent reply before the next hearing on 03.07.2024.

24
Stage 2302/04/2024

Hearing

The Tribunal granted the respondent a one-week extension to file objections to the grounds of appeal due to counsel's illness and scheduled the next hearing for May 3, 2024.

25
Stage 2428/02/2024

Hearing

The Tribunal granted the respondent 10 days to file a vakalatnama and objections, with the appellant permitted to file a reply within one week thereafter. The matter is scheduled for hearing on 02.04.2024.

26
Stage 2502/02/2024

Hearing

The Tribunal issued a notice to the respondent due to their absence and directed the appellant to serve the notice via speed-post and email, scheduling the next hearing for 28.02.2024.

27
Stage 2623/07/2018

Delay condonation

No text available.

28
Stage 27Interim Order

Tribunal Order #0901126000512018-13-12-2024

The Tribunal directed the respondent to file legible copies of the allotment letter, BBA, and Tripartite Agreement within 15 days and ordered the Registry to summon the original complaint records from the Regulatory Authority.

29
Stage 28Final Ruling Order

Tribunal Order #0901126000512018-12-12-2025

The Appellate Tribunal set aside the Regulatory Authority's order, directing the promoter to pay delay interest at MCLR+1% from 25.09.2014 to 27.11.2019 and to deliver possession of the top-floor flat (Gokul-1-1401) after adjusting the payable interest against the remaining consideration.

30
Stage 29Interim Order

Tribunal Order #0901126000512018-03-05-2024

The Tribunal directed the appellant to upload a soft copy of the appeal to the portal and provide physical copies to the respondent within one week to facilitate the filing of objections. The order also establishes a timeline for the respondent's objection and the appellant's subsequent reply before the next hearing on 03.07.2024.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal set aside the Regulatory Authority's order, directing the promoter to pay delay interest at MCLR+1% from 25.09.2014 to 27.11.2019 and to deliver possession of the top-floor flat (Gokul-1-1401) after adjusting the payable interest against the remaining consideration. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.

Disposal Winner: AppellantInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal set aside the Regulatory Authority's order, directing the promoter to pay delay interest at MCLR+1% from 25.09.2014 to 27.11.2019 and to deliver possession of the top-floor flat (Gokul-1-1401) after adjusting the payable interest against the remaining consideration.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1%

Interest Period

from 25.09.2014 to 27.11.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anurag Arora
  • Alok Kumar Singh
  • Aviral Raj Singh
  • Ritwick Rai

Respondent Advocate(s)

  • Azhar Ikram
  • Manish Singh

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126000512018-13-12-2024

The Tribunal directed the respondent to file legible copies of the allotment letter, BBA, and Tripartite Agreement within 15 days and ordered the Registry to summon the original complaint records from the Regulatory Authority.

FINAL_ORDEROrder ID: 0901126000512018-12-12-2025

The Appellate Tribunal set aside the Regulatory Authority's order, directing the promoter to pay delay interest at MCLR+1% from 25.09.2014 to 27.11.2019 and to deliver possession of the top-floor flat (Gokul-1-1401) after adjusting the payable interest against the remaining consideration.

INTERIM_ORDEROrder ID: 0901126000512018-03-05-2024

The Tribunal directed the appellant to upload a soft copy of the appeal to the portal and provide physical copies to the respondent within one week to facilitate the filing of objections. The order also establishes a timeline for the respondent's objection and the appellant's subsequent reply before the next hearing on 03.07.2024.