Appellant / Complainant
Vijay Sharma
Respondent
S.V.P Builder
s.v.p builder
₹21,79,353
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126000512018 by Vijay Sharma against S.V.P Builder before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal set aside the Regulatory Authority's order, directing the promoter to pay delay interest at MCLR+1% from 25.09.2014 to 27.11.2019 and to deliver possession of the top-floor flat (Gokul-1-1401) after adjusting the payable interest against the remaining consideration.
Part Heard
The Tribunal heard arguments from both counsels regarding the appeal and its objections, subsequently reserving the judgment for further decision.
Part Heard
The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the appeal for hearing on 17.09.2025.
Part Heard
The Tribunal granted a request to list the appeal for orders or hearing on September 3, 2025, before Bench No. 2.
Part Heard
The Tribunal adjourned the appeal to 26.08.2025 and issued a strict warning that no further adjournments will be granted, noting that the matter may proceed based on available records if counsel fail to appear.
Part Heard
The Tribunal heard arguments from both parties and scheduled the appeal for a final hearing on August 22, 2025.
Part Heard
Upon a joint request from the counsel for both parties, the tribunal adjourned the matter and scheduled the next hearing for August 6, 2025.
Part Heard
The Tribunal ordered that the appeal be tied up to Bench No. 2 and scheduled for hearing/orders on 28.07.2025.
Hearing
The Tribunal heard arguments from both parties and adjourned the appeal to July 7, 2025, for further arguments.
Hearing
The Tribunal granted a request to list the appeal for orders or hearing on May 6, 2025.
Hearing
The Tribunal granted a request from the respondent's counsel to list the appeal for hearing on 10.04.2025, noting that no further adjournments will be permitted.
Hearing
The Tribunal granted an adjournment application filed by the respondent and rescheduled the hearing for April 3, 2025.
Hearing
The Tribunal granted the respondent one week to upload the Occupancy Certificate (OC) or Completion Certificate (CC) to the record and scheduled the case for hearing on March 5, 2025.
Hearing
The Tribunal directed the Registry to send a reminder to RERA to summon the case records and scheduled the matter for orders on 11.02.2025.
Hearing
The Tribunal granted time to both parties to upload necessary documents (allotment letter, tripartite agreement, and legible BBA) and directed the Registry to summon records from the U.P. Real Estate Regulatory Authority for the next hearing on 29.01.2025.
Hearing
The Tribunal directed the respondent to file legible copies of the allotment letter, BBA, and Tripartite Agreement within 15 days and ordered the Registry to summon the original complaint records from the Regulatory Authority.
Hearing
The proceedings were adjourned at the request of the respondent's counsel, with the matter rescheduled for hearing on 13.12.2024.
Hearing
The Tribunal directed the appellant to file a rejoinder affidavit to the respondent's objections within one week and scheduled the next hearing for 13.11.2024.
Hearing
The Tribunal granted the respondent a final seven-day extension to file objections and provide a soft copy to the appellant, with the matter scheduled for hearing on 04.10.2024.
Hearing
The Tribunal granted the respondent one week to file objections to the grounds of appeal and directed the appellant to reply within a week thereafter, scheduling the next hearing for August 2, 2024.
Hearing
The Tribunal directed the appellant to upload a soft copy of the appeal to the portal and provide physical copies to the respondent within one week to facilitate the filing of objections. The order also establishes a timeline for the respondent's objection and the appellant's subsequent reply before the next hearing on 03.07.2024.
Hearing
The Tribunal granted the respondent a one-week extension to file objections to the grounds of appeal due to counsel's illness and scheduled the next hearing for May 3, 2024.
Hearing
The Tribunal granted the respondent 10 days to file a vakalatnama and objections, with the appellant permitted to file a reply within one week thereafter. The matter is scheduled for hearing on 02.04.2024.
Hearing
The Tribunal issued a notice to the respondent due to their absence and directed the appellant to serve the notice via speed-post and email, scheduling the next hearing for 28.02.2024.
Tribunal Order #0901126000512018-13-12-2024
The Tribunal directed the respondent to file legible copies of the allotment letter, BBA, and Tripartite Agreement within 15 days and ordered the Registry to summon the original complaint records from the Regulatory Authority.
Tribunal Order #0901126000512018-12-12-2025
The Appellate Tribunal set aside the Regulatory Authority's order, directing the promoter to pay delay interest at MCLR+1% from 25.09.2014 to 27.11.2019 and to deliver possession of the top-floor flat (Gokul-1-1401) after adjusting the payable interest against the remaining consideration.
Tribunal Order #0901126000512018-03-05-2024
The Tribunal directed the appellant to upload a soft copy of the appeal to the portal and provide physical copies to the respondent within one week to facilitate the filing of objections. The order also establishes a timeline for the respondent's objection and the appellant's subsequent reply before the next hearing on 03.07.2024.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal set aside the Regulatory Authority's order, directing the promoter to pay delay interest at MCLR+1% from 25.09.2014 to 27.11.2019 and to deliver possession of the top-floor flat (Gokul-1-1401) after adjusting the payable interest against the remaining consideration. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal set aside the Regulatory Authority's order, directing the promoter to pay delay interest at MCLR+1% from 25.09.2014 to 27.11.2019 and to deliver possession of the top-floor flat (Gokul-1-1401) after adjusting the payable interest against the remaining consideration.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR + 1%
Interest Period
from 25.09.2014 to 27.11.2019
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Anurag Arora
- Alok Kumar Singh
- Aviral Raj Singh
- Ritwick Rai
Respondent Advocate(s)
- Azhar Ikram
- Manish Singh
Official RERA Tribunal Orders (3)
The Tribunal directed the respondent to file legible copies of the allotment letter, BBA, and Tripartite Agreement within 15 days and ordered the Registry to summon the original complaint records from the Regulatory Authority.
The Appellate Tribunal set aside the Regulatory Authority's order, directing the promoter to pay delay interest at MCLR+1% from 25.09.2014 to 27.11.2019 and to deliver possession of the top-floor flat (Gokul-1-1401) after adjusting the payable interest against the remaining consideration.
The Tribunal directed the appellant to upload a soft copy of the appeal to the portal and provide physical copies to the respondent within one week to facilitate the filing of objections. The order also establishes a timeline for the respondent's objection and the appellant's subsequent reply before the next hearing on 03.07.2024.
Need to research all rulings for s.v.p builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.