Appellant / Complainant
Uppal Chadha Hi-Tech Developers Pvt. Ltd.
Respondent
Suman Agarwal
uppal chadha hi-tech developers pvt. ltd.
₹29,76,007
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126000502023 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Suman Agarwal before up_rera.
For Order
The Tribunal dismissed the developer's appeal, upholding the Authority's order that the respondent allottee is entitled to possession of the unit upon receipt of OC/CC and delay interest under Section 18(1) of the Act 2016 until physical possession is handed over.
Hearing
The Tribunal granted a request from the appellant's counsel to adjourn the matter and scheduled the case for orders on 25.03.2026.
Hearing
The Tribunal has adjourned the matter to 23.02.2026 for orders/hearing following a request made by the counsel for the respondent.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 03.02.2026.
Hearing
The Tribunal directed the counsel for both parties to upload the dates and events of the case and scheduled the appeal for a hearing on 08.01.2025.
Hearing
The Tribunal granted the respondent a final opportunity to file objections to the appellant's supplementary affidavit and adjourned the matter to 11.12.2025.
Hearing
The Tribunal granted the respondent 10 days to file a reply and scheduled the appeal for a hearing on November 19, 2025.
Hearing
The Tribunal directed the respondent's counsel to file a reply to the objections against the supplementary affidavit within ten days and scheduled the case for hearing on 29.10.2025.
Hearing
The Tribunal granted the appellant seven days to file or upload required documents and scheduled the appeal for a hearing on October 6, 2025.
Hearing
The Tribunal noted the appellant's submission that the project has received OC/CC and that possession will be offered to the respondent shortly, subsequently adjourning the matter to 08.09.2025.
Re-Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the case for orders on 19.08.2025, noting that no further adjournments will be permitted.
Re-Hearing
Upon a joint request from the counsel for both parties, the matter has been adjourned for orders on 28.07.2025.
Re-Hearing
The Tribunal issued a notice to the respondent and scheduled the appeal for a hearing on July 7, 2025.
For Order
The Tribunal heard arguments from both parties, and the judgment has been reserved for later delivery.
For Order
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for October 1, 2024, noting technical issues with the web portal.
For Order
The Tribunal granted the appellant seven days to file a rejoinder and directed that a soft copy be sent to the respondent within three days, with the next hearing scheduled for 30.08.2024.
For Order
The Tribunal adjourned the proceedings due to the absence of the respondent and scheduled the appeal for orders/hearing on 30.07.2024.
For Order
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the next hearing for July 3, 2024.
For Order
The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for hearing on May 3, 2024.
For Order
The Tribunal granted the respondent 10 days to file a vakalatnama and objections, with the appellant permitted to file a reply within one week thereafter. The matter is scheduled for hearing on 02.04.2024.
For Order
The Tribunal adjourned the appeal to 28.02.2024 because the counsel for the appellant was reported to be ill or on leave.
Admission
The Tribunal issued notice to the respondent regarding the application for condonation of delay and noted the deposit of Rs 18,86,238/- in compliance with Section 43(5) of the Act, scheduling the next hearing for 17.01.2024.
Tribunal Order #0901126000502023-25-03-2026
The Tribunal dismissed the developer's appeal, upholding the Authority's order that the respondent allottee is entitled to possession of the unit upon receipt of OC/CC and delay interest under Section 18(1) of the Act 2016 until physical possession is handed over.
Tribunal Order #0901126000502023-19-12-2023
The Tribunal issued notice to the respondent regarding the application for condonation of delay and noted the deposit of Rs 18,86,238/- in compliance with Section 43(5) of the Act, scheduling the next hearing for 17.01.2024.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the developer's appeal, upholding the Authority's order that the respondent allottee is entitled to possession of the unit upon receipt of OC/CC and delay interest under Section 18(1) of the Act 2016 until physical possession is handed over. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the developer's appeal, upholding the Authority's order that the respondent allottee is entitled to possession of the unit upon receipt of OC/CC and delay interest under Section 18(1) of the Act 2016 until physical possession is handed over.
Ruling Awarded To
Respondent
Interest Period
from 27.11.2015 till grant of OC/CC or till the date of offer of possession
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Surangama Sharma
Respondent Advocate(s)
- Anoop Kumar
- Vineet Srivastava
Official RERA Tribunal Orders (2)
The Tribunal dismissed the developer's appeal, upholding the Authority's order that the respondent allottee is entitled to possession of the unit upon receipt of OC/CC and delay interest under Section 18(1) of the Act 2016 until physical possession is handed over.
The Tribunal issued notice to the respondent regarding the application for condonation of delay and noted the deposit of Rs 18,86,238/- in compliance with Section 43(5) of the Act, scheduling the next hearing for 17.01.2024.
Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.