up_reraStatus: Completed
CASE ID: 0901126000502023

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Suman Agarwal

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disputed Amount

29,76,007

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

26 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000502023 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Suman Agarwal before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 125/03/2026

For Order

The Tribunal dismissed the developer's appeal, upholding the Authority's order that the respondent allottee is entitled to possession of the unit upon receipt of OC/CC and delay interest under Section 18(1) of the Act 2016 until physical possession is handed over.

3
Stage 223/02/2026

Hearing

The Tribunal granted a request from the appellant's counsel to adjourn the matter and scheduled the case for orders on 25.03.2026.

4
Stage 303/02/2026

Hearing

The Tribunal has adjourned the matter to 23.02.2026 for orders/hearing following a request made by the counsel for the respondent.

5
Stage 408/01/2026

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 03.02.2026.

6
Stage 511/12/2025

Hearing

The Tribunal directed the counsel for both parties to upload the dates and events of the case and scheduled the appeal for a hearing on 08.01.2025.

7
Stage 619/11/2025

Hearing

The Tribunal granted the respondent a final opportunity to file objections to the appellant's supplementary affidavit and adjourned the matter to 11.12.2025.

8
Stage 729/10/2025

Hearing

The Tribunal granted the respondent 10 days to file a reply and scheduled the appeal for a hearing on November 19, 2025.

9
Stage 806/10/2025

Hearing

The Tribunal directed the respondent's counsel to file a reply to the objections against the supplementary affidavit within ten days and scheduled the case for hearing on 29.10.2025.

10
Stage 908/09/2025

Hearing

The Tribunal granted the appellant seven days to file or upload required documents and scheduled the appeal for a hearing on October 6, 2025.

11
Stage 1019/08/2025

Hearing

The Tribunal noted the appellant's submission that the project has received OC/CC and that possession will be offered to the respondent shortly, subsequently adjourning the matter to 08.09.2025.

12
Stage 1128/07/2025

Re-Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the case for orders on 19.08.2025, noting that no further adjournments will be permitted.

13
Stage 1207/07/2025

Re-Hearing

Upon a joint request from the counsel for both parties, the matter has been adjourned for orders on 28.07.2025.

14
Stage 1307/05/2025

Re-Hearing

The Tribunal issued a notice to the respondent and scheduled the appeal for a hearing on July 7, 2025.

15
Stage 1401/10/2024

For Order

The Tribunal heard arguments from both parties, and the judgment has been reserved for later delivery.

16
Stage 1530/08/2024

For Order

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for October 1, 2024, noting technical issues with the web portal.

17
Stage 1630/07/2024

For Order

The Tribunal granted the appellant seven days to file a rejoinder and directed that a soft copy be sent to the respondent within three days, with the next hearing scheduled for 30.08.2024.

18
Stage 1703/07/2024

For Order

The Tribunal adjourned the proceedings due to the absence of the respondent and scheduled the appeal for orders/hearing on 30.07.2024.

19
Stage 1803/05/2024

For Order

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the next hearing for July 3, 2024.

20
Stage 1902/04/2024

For Order

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for hearing on May 3, 2024.

21
Stage 2028/02/2024

For Order

The Tribunal granted the respondent 10 days to file a vakalatnama and objections, with the appellant permitted to file a reply within one week thereafter. The matter is scheduled for hearing on 02.04.2024.

22
Stage 2117/01/2024

For Order

The Tribunal adjourned the appeal to 28.02.2024 because the counsel for the appellant was reported to be ill or on leave.

23
Stage 2219/12/2023

Admission

The Tribunal issued notice to the respondent regarding the application for condonation of delay and noted the deposit of Rs 18,86,238/- in compliance with Section 43(5) of the Act, scheduling the next hearing for 17.01.2024.

24
Stage 23Final Ruling Order

Tribunal Order #0901126000502023-25-03-2026

The Tribunal dismissed the developer's appeal, upholding the Authority's order that the respondent allottee is entitled to possession of the unit upon receipt of OC/CC and delay interest under Section 18(1) of the Act 2016 until physical possession is handed over.

25
Stage 24Interim Order

Tribunal Order #0901126000502023-19-12-2023

The Tribunal issued notice to the respondent regarding the application for condonation of delay and noted the deposit of Rs 18,86,238/- in compliance with Section 43(5) of the Act, scheduling the next hearing for 17.01.2024.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the developer's appeal, upholding the Authority's order that the respondent allottee is entitled to possession of the unit upon receipt of OC/CC and delay interest under Section 18(1) of the Act 2016 until physical possession is handed over. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the developer's appeal, upholding the Authority's order that the respondent allottee is entitled to possession of the unit upon receipt of OC/CC and delay interest under Section 18(1) of the Act 2016 until physical possession is handed over.

Ruling Awarded To

Respondent

Interest Period

from 27.11.2015 till grant of OC/CC or till the date of offer of possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Surangama Sharma

Respondent Advocate(s)

  • Anoop Kumar
  • Vineet Srivastava

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126000502023-25-03-2026

The Tribunal dismissed the developer's appeal, upholding the Authority's order that the respondent allottee is entitled to possession of the unit upon receipt of OC/CC and delay interest under Section 18(1) of the Act 2016 until physical possession is handed over.

INTERIM_ORDEROrder ID: 0901126000502023-19-12-2023

The Tribunal issued notice to the respondent regarding the application for condonation of delay and noted the deposit of Rs 18,86,238/- in compliance with Section 43(5) of the Act, scheduling the next hearing for 17.01.2024.

TathyaGrid RERA Intelligence AI