Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000482023 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Naresh Kumar Yadav before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 102/12/2024

for delivery of Judgment/Order

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to exempt a promoter from paying delay interest to an allottee under Section 18 of the RERA Act.

3
Stage 201/10/2024

Delay condonation

The Tribunal condoned a 13-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal; judgment on the merits has been reserved.

4
Stage 330/08/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to a conflict with a High Court matter and rescheduled the hearing for October 1, 2024.

5
Stage 430/07/2024

Delay condonation

The Tribunal granted the appellant seven days to file a supplementary affidavit containing a Supreme Court judgment and directed the respondent to file any objections within the following week.

6
Stage 502/07/2024

Delay condonation

The Tribunal granted a joint request from the counsels to list the defective appeal for hearing on 30.07.2024.

7
Stage 602/05/2024

Delay condonation

The Tribunal noted the exchange of pleadings and scheduled the defective appeal for consideration of a delay condonation application on 02.07.2024.

8
Stage 701/04/2024

Delay condonation

The Tribunal noted that pleadings have been exchanged and scheduled the defective appeal for consideration of the condonation of delay application on 02.05.2024.

9
Stage 827/02/2024

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objection and scheduled the matter for hearing on 01.04.2024 regarding the application for condonation of delay.

10
Stage 917/01/2024

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and grounds of appeal, scheduling the next hearing for 27.02.2024.

11
Stage 1019/12/2023

Delay condonation

The Tribunal noted the deposit of Rs 10,13,286/- under Section 43(5) and issued notice to the respondent regarding the application for condonation of delay, scheduling the matter for hearing on 17.01.2024.

12
Stage 11Final Ruling Order

Tribunal Order #0901126000482023-02-12-2024

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to exempt a promoter from paying delay interest to an allottee under Section 18 of the RERA Act.

13
Stage 12Interim Order

Tribunal Order #0901126000482023-19-12-2023

The Tribunal noted the deposit of Rs 10,13,286/- under Section 43(5) and issued notice to the respondent regarding the application for condonation of delay, scheduling the matter for hearing on 17.01.2024.

14
Stage 13Interim Order

Tribunal Order #0901126000482023-01-10-2024

The Tribunal condoned a 13-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal; judgment on the merits has been reserved.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to exempt a promoter from paying delay interest to an allottee under Section 18 of the RERA Act. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to exempt a promoter from paying delay interest to an allottee under Section 18 of the RERA Act.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 31.03.2016 till the date of obtaining Occupancy/Completion certificate (OC/CC) or till the date of offer of possession whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav
  • Bal Kishor Verma

Respondent Advocate(s)

  • Sumit Sharma

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126000482023-02-12-2024

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to exempt a promoter from paying delay interest to an allottee under Section 18 of the RERA Act.

INTERIM_ORDEROrder ID: 0901126000482023-19-12-2023

The Tribunal noted the deposit of Rs 10,13,286/- under Section 43(5) and issued notice to the respondent regarding the application for condonation of delay, scheduling the matter for hearing on 17.01.2024.

INTERIM_ORDEROrder ID: 0901126000482023-01-10-2024

The Tribunal condoned a 13-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal; judgment on the merits has been reserved.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →