up_reraStatus: Completed
CASE ID: 0901126000452023

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Nardev Ku Wig.

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disputed Amount

17,58,120

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000452023 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Nardev Ku Wig. before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 102/12/2024

for delivery of Judgment/Order

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations under Section 18 of the RERA Act for an ongoing project.

3
Stage 201/10/2024

Delay condonation

The Tribunal condoned a 13-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal before reserving judgment.

4
Stage 330/08/2024

Delay condonation

The tribunal noted the filing of a Vakalatnama by the respondent's counsel and adjourned the matter to 01.10.2024 for orders/hearing.

5
Stage 430/07/2024

Delay condonation

The Tribunal granted the appellant seven days to file a supplementary affidavit and relevant Supreme Court documents, directing that copies be sent to the respondent for objections before the next hearing on 30.08.2024.

6
Stage 502/07/2024

Delay condonation

Upon the joint request of the counsels for both parties, the tribunal has rescheduled the hearing for this defective appeal to 30.07.2024.

7
Stage 602/05/2024

Delay condonation

The Tribunal noted that pleadings have been exchanged and listed the defective appeal for consideration of a delay condonation application on 02.07.2024.

8
Stage 701/04/2024

Delay condonation

The Tribunal noted that pleadings have been exchanged and listed the defective appeal for consideration of the application for condonation of delay on 02.05.2024.

9
Stage 827/02/2024

Delay condonation

The Tribunal granted the applicant one week to file a reply to the respondent's objection and scheduled the matter for hearing on 01.04.2024 regarding the application for condonation of delay.

10
Stage 917/01/2024

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and directed the matter be listed on 27.02.2024.

11
Stage 1019/12/2023

Delay condonation

The Tribunal acknowledges the deposit of Rs 9,58,884/- under Section 43(5) of the Act and issues notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 17.01.2024.

12
Stage 11Final Ruling Order

Tribunal Order #0901126000452023-02-12-2024

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations under Section 18 of the RERA Act for an ongoing project.

13
Stage 12Interim Order

Tribunal Order #0901126000452023-01-10-2024

The Tribunal condoned a 13-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal before reserving judgment.

14
Stage 13Interim Order

Tribunal Order #0901126000452023-19-12-2023

The Tribunal acknowledges the deposit of Rs 9,58,884/- under Section 43(5) of the Act and issues notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 17.01.2024.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations under Section 18 of the RERA Act for an ongoing project. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations under Section 18 of the RERA Act for an ongoing project.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 31.03.2016 till the date of obtaining Occupancy/Completion certificate (OC/CC) or till the date of offer of possession whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav
  • Bal Kishor Verma

Respondent Advocate(s)

  • Sumit Sharma

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126000452023-02-12-2024

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations under Section 18 of the RERA Act for an ongoing project.

INTERIM_ORDEROrder ID: 0901126000452023-01-10-2024

The Tribunal condoned a 13-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal before reserving judgment.

INTERIM_ORDEROrder ID: 0901126000452023-19-12-2023

The Tribunal acknowledges the deposit of Rs 9,58,884/- under Section 43(5) of the Act and issues notice to the respondent regarding the application for condonation of delay, scheduled for hearing on 17.01.2024.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →