up_reraStatus: Completed
CASE ID: 0901126000332018

Appellant / Complainant

Rajiv

VS

Respondent

U.P. Avas Evam Vikas Parishad

Disputed Amount

78,99,888

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional MisrepresentationMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

8 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000332018 by Rajiv against U.P. Avas Evam Vikas Parishad before up_rera.

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityPromotional MisrepresentationMaintenance & Utility Disputes
2
Stage 108/12/2022

for delivery of Judgment/Order

The Appellate Tribunal set aside the previous order of the Secretary RERA, ruling that the project was delayed and directing the respondent to pay interest at MCLR+1% per annum on the appellant's deposited amount for the period from 29.03.2016 to 07.12.2016 and to rectify any structural defects within four months.

3
Stage 217/03/2021

Further Order

No text available.

4
Stage 318/02/2021

Part Heard

The Tribunal adjourned the appeal to 17.03.2021 due to the absence of the respondent's counsel and issued a warning that the matter may be heard ex-parte if no one appears on the next date.

5
Stage 412/01/2021

Rest Arg. on Merit

No text available.

6
Stage 510/12/2020

Rest Arg. on Merit

No text available.

7
Stage 6Final Ruling Order

Tribunal Order #0901126000332018-08-12-2022

The Appellate Tribunal set aside the previous order of the Secretary RERA, ruling that the project was delayed and directing the respondent to pay interest at MCLR+1% per annum on the appellant's deposited amount for the period from 29.03.2016 to 07.12.2016 and to rectify any structural defects within four months.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal set aside the previous order of the Secretary RERA, ruling that the project was delayed and directing the respondent to pay interest at MCLR+1% per annum on the appellant's deposited amount for the period from 29.03.2016 to 07.12.2016 and to rectify any structural defects within four months. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% per annum.

Disposal Winner: AppellantInterest Rate: MCLR + 1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal set aside the previous order of the Secretary RERA, ruling that the project was delayed and directing the respondent to pay interest at MCLR+1% per annum on the appellant's deposited amount for the period from 29.03.2016 to 07.12.2016 and to rectify any structural defects within four months.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1% per annum

Interest Period

from 29.03.2016 to 07.12.2016

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 14(3)Section 12Section 11(4)(d)Section 19(6)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Adarsh Prabhat Asthana

Respondent Advocate(s)

  • Vijay Pratap Singh Chauhan
  • Akhand Pratap Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126000332018-08-12-2022

The Appellate Tribunal set aside the previous order of the Secretary RERA, ruling that the project was delayed and directing the respondent to pay interest at MCLR+1% per annum on the appellant's deposited amount for the period from 29.03.2016 to 07.12.2016 and to rectify any structural defects within four months.