Appellant / Complainant
Raj Rani
Respondent
Agc Realty Pvt. Ltd.
agc realty pvt. ltd.
₹75,87,757
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126000272019 by Raj Rani against Agc Realty Pvt. Ltd. before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund Rs. 75,87,757/- to the appellants with interest at MCLR+1% per annum due to project delays and failure to register the ongoing project.
Final Hearing
The Tribunal heard arguments from the counsel for the appellant and reserved the judgment for a later date.
Re-Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to personal difficulty and rescheduled the hearing for 28.11.2022.
Re-Hearing
The Tribunal granted a request for adjournment made by the appellant's counsel and rescheduled the matter for orders on 21.10.2022.
Re-Hearing
The U.P. Real Estate Appellate Tribunal granted a request for adjournment made by the appellant's counsel and rescheduled the hearing for 22.09.2022.
Re-Hearing
The Tribunal revised the list and scheduled the appeal for a hearing on 14.09.2022.
Re-Hearing
The Tribunal granted the appellant two weeks to examine previous orders regarding project registration and adjourned the matter to 30.08.2022.
Re-Hearing
The Tribunal granted a request for adjournment to facilitate a potential amicable settlement between the parties and rescheduled the hearing for 08.08.2022.
Re-Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to personal difficulties and rescheduled the hearing for 25.07.2022.
Re-Hearing
The Tribunal adjourned the proceedings to allow the parties time for potential amicable settlement through negotiation, listing the matter for 22.07.2022.
Hearing
The Tribunal granted a request by the appellant's counsel to reschedule the hearing of Appeal-308/2019 to 08.07.2022.
Hearing
The Tribunal adjourned the appeal to 20.05.2022 due to the absence of the respondent's counsel.
Hearing
The Tribunal heard arguments from both parties and reserved the judgment for a later date.
Hearing
The Tribunal adjourned the appeal due to the absence of the Respondent's counsel and scheduled the matter for further orders on 25.10.2021.
Hearing
The Tribunal noted that pleadings have been exchanged between the parties and scheduled the matter for hearing on 13.04.2021.
Hearing on Appeal
The Tribunal noted that pleadings have been exchanged and directed the parties to upload the reply on the e-portal within three days. The matter is adjourned to 18.03.2021, with a directive for counsels to submit lists of dates and relied judgments in advance.
Tribunal Order #0901126000272019-08-12-2022
The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund Rs. 75,87,757/- to the appellants with interest at MCLR+1% per annum due to project delays and failure to register the ongoing project.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund Rs. 75,87,757/- to the appellants with interest at MCLR+1% per annum due to project delays and failure to register the ongoing project. Awarded in favor of Appellant. Awarded interest rate: MCLR+1% per annum.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund Rs. 75,87,757/- to the appellants with interest at MCLR+1% per annum due to project delays and failure to register the ongoing project.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1% per annum
Interest Period
from the date of deposit till the refund of the amount
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Abhinav Singh
- Ankush Yadav
Respondent Advocate(s)
- S.S. Rajawat
Official RERA Tribunal Orders (1)
The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund Rs. 75,87,757/- to the appellants with interest at MCLR+1% per annum due to project delays and failure to register the ongoing project.
Need to research all rulings for agc realty pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.