CASE ID: 0901126000262019

Appellant / Complainant

SVP Builder India Limited

VS

Respondent

Neha Sharma

Developer Firm

svp builder india limited

Disputed Amount

29,84,236

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000262019 by SVP Builder India Limited against Neha Sharma before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 127/09/2021

Compliance of section 43(5)

The U.P. Real Estate Appellate Tribunal dismissed four appeals filed by M/s S. V. P. Builders India Ltd. due to non-compliance with the mandatory pre-deposit requirements of Section 43(5) of the RERA Act, 2016.

3
Stage 221/09/2021

Hearing

The Tribunal granted the appellant a final three-day extension to comply with Section 43(5) of the Act, warning that failure to do so will result in the dismissal of the appeal.

4
Stage 308/09/2021

Hearing

The Tribunal granted a request from the appellant's counsel to adjourn the matter and rescheduled the case for hearing on 21.09.2021.

5
Stage 401/04/2021

Hearing

No text available.

6
Stage 512/03/2021

Rest deposit Amount under 43(5) of the Act

No text available.

7
Stage 602/03/2021

Compliance of section 43(5)

The Tribunal directed the applicant to ensure complete compliance with Section 43(5) of the Act, 2016 by the next hearing date, warning that failure to comply will result in the dismissal of the appeal.

8
Stage 718/02/2021

Compliance of section 43(5)

The Tribunal granted a request by the appellant's counsel to adjourn the matter to 02.03.2021 to allow for compliance with Section 43(5) of the Act.

9
Stage 804/02/2021

Hearing

The Tribunal granted a final one-week extension for the appellant to comply with Section 43(5) of the Act, warning that failure to do so by the next hearing on 18.02.2021 will result in the dismissal of the appeal.

10
Stage 907/10/2020

Hearing

No text available.

11
Stage 10Final Ruling Order

Tribunal Order #0901126000262019-27-09-2021

The U.P. Real Estate Appellate Tribunal dismissed four appeals filed by M/s S. V. P. Builders India Ltd. due to non-compliance with the mandatory pre-deposit requirements of Section 43(5) of the RERA Act, 2016.

12
Stage 11Interim Order

Tribunal Order #0901126000262019-04-02-2021

The Tribunal granted a final one-week extension for the appellant to comply with Section 43(5) of the Act, warning that failure to do so by the next hearing on 18.02.2021 will result in the dismissal of the appeal.

13
Stage 12Interim Order

Tribunal Order #0901126000262019-02-03-2021

The Tribunal directed the applicant to ensure complete compliance with Section 43(5) of the Act, 2016 by the next hearing date, warning that failure to comply will result in the dismissal of the appeal.

14
Stage 13Interim Order

Tribunal Order #0901126000262019-21-09-2021

The Tribunal granted the appellant a final three-day extension to comply with Section 43(5) of the Act, warning that failure to do so will result in the dismissal of the appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed four appeals filed by M/s S. V. P. Builders India Ltd. due to non-compliance with the mandatory pre-deposit requirements of Section 43(5) of the RERA Act, 2016. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed four appeals filed by M/s S. V. P. Builders India Ltd. due to non-compliance with the mandatory pre-deposit requirements of Section 43(5) of the RERA Act, 2016.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.05.2016 till the date of obtaining OC/CC or offer of possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 43(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Azhar Ikram
  • Manish Singh

Respondent Advocate(s)

  • Mohammad Alam Khan

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126000262019-27-09-2021

The U.P. Real Estate Appellate Tribunal dismissed four appeals filed by M/s S. V. P. Builders India Ltd. due to non-compliance with the mandatory pre-deposit requirements of Section 43(5) of the RERA Act, 2016.

INTERIM_ORDEROrder ID: 0901126000262019-04-02-2021

The Tribunal granted a final one-week extension for the appellant to comply with Section 43(5) of the Act, warning that failure to do so by the next hearing on 18.02.2021 will result in the dismissal of the appeal.

INTERIM_ORDEROrder ID: 0901126000262019-02-03-2021

The Tribunal directed the applicant to ensure complete compliance with Section 43(5) of the Act, 2016 by the next hearing date, warning that failure to comply will result in the dismissal of the appeal.

INTERIM_ORDEROrder ID: 0901126000262019-21-09-2021

The Tribunal granted the appellant a final three-day extension to comply with Section 43(5) of the Act, warning that failure to do so will result in the dismissal of the appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for svp builder india limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.