Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126000232018 by Ritu Jain against Bulland Buildtech Pvt. Ltd. before up_rera.
Final Hearing
The appeal was dismissed due to the appellant's counsel stating they had received no instructions from the appellant.
Final Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to a personal emergency and scheduled the final hearing for December 13, 2021, while directing parties to exchange pleadings.
Final Hearing
The Tribunal directed the appellant to file an impleadment application to include RERA as a party and scheduled the matter for hearing on 29.11.2021.
Hearing
The Tribunal directed the respondent to provide details of the Interim Resolution Professional (IRP) appointed by the NCLT and to seek authorization for the IRP to represent the company in the upcoming hearing.
to file objections and its reply
The Tribunal directed the Registry to summon the records of related complaints (Shri Satish Jain vs. M/s Bulland Buildtech Pvt. Ltd. and Smt. Laxmi Devi vs. M/s Bulland Buildtech Pvt. Ltd.) to verify facts regarding the clubbing of complaints and observations made by RERA.
to file objections and its reply
The Tribunal granted the appellant's counsel a one-week extension to file a reply to the respondent's objections and scheduled the next hearing for October 6, 2021.
For Order
The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objections and scheduled the next hearing for 09.04.2021.
Hearing
The Tribunal adjourned the appeal to 24.03.2021 and directed the parties to exchange pleadings in the interim.
For Order
The Tribunal granted the appellant one week to file a reply to the respondent's objections and directed both parties to upload their filings on the e-portal before the next hearing on 09.02.2021.
Tribunal Order #0901126000232018-06-10-2021
The Tribunal directed the Registry to summon the records of related complaints (Shri Satish Jain vs. M/s Bulland Buildtech Pvt. Ltd. and Smt. Laxmi Devi vs. M/s Bulland Buildtech Pvt. Ltd.) to verify facts regarding the clubbing of complaints and observations made by RERA.
Tribunal Disposal & Final Award Ruling
Dismissed Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Siddharth Nandwani
- Prashant Kumar
Respondent Advocate(s)
- Mohd. Khalid
Official RERA Tribunal Orders (1)
The Tribunal directed the Registry to summon the records of related complaints (Shri Satish Jain vs. M/s Bulland Buildtech Pvt. Ltd. and Smt. Laxmi Devi vs. M/s Bulland Buildtech Pvt. Ltd.) to verify facts regarding the clubbing of complaints and observations made by RERA.
Need to research all rulings for bulland buildtech pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.