up_reraStatus: Completed
CASE ID: 0901126000202019

Appellant / Complainant

Jagdish Prasad

VS

Respondent

SJP Infracon Limited

Developer Firm

sjp infracon limited

Disputed Amount

46,66,636

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000202019 by Jagdish Prasad against SJP Infracon Limited before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 115/03/2022

for delivery of Judgment/Order

The Tribunal set aside the previous order of the Regulatory Authority because it exceeded the original prayers made by the appellant, and instead directed the respondent to refund the entire deposited amount with interest at MCLR+1% per annum.

3
Stage 220/11/2021

Hearing

The Tribunal heard arguments regarding an appeal against a RERA order that directed possession instead of a refund; the appellant seeks a full refund with interest, citing legal precedent.

4
Stage 311/11/2021

Hearing

The Tribunal adjourned the appeal to 22.11.2021 because the appellant's counsel was in transit and other cases on the cause-list had already been taken up.

5
Stage 422/09/2021

Hearing

The Tribunal directed the respondent to provide specific details regarding super area and carpet area as previously ordered and mandated both parties to file and exchange a list of dates, events, and relied-upon cases before the next hearing.

6
Stage 506/09/2021

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to a medical emergency (eye operation) and rescheduled the hearing for 22.09.2021.

7
Stage 630/04/2021

Hearing

No text available.

8
Stage 705/04/2021

Rest Arg. on Merit

No text available.

9
Stage 812/03/2021

Hearing

The Tribunal granted a request from the appellant's counsel to adjourn the appeal and rescheduled the matter for hearing on 05.04.2021.

10
Stage 902/02/2021

Hearing on Appeal

The Tribunal noted the respondent's failure to comply with a previous directive to provide super area and carpet area details and directed both parties to file lists of dates and relied-upon judgments before the next hearing.

11
Stage 1015/12/2020

Hearing on Appeal

No text available.

12
Stage 11Interim Order

Tribunal Order #0901126000202019-20-11-2021

The Tribunal heard arguments regarding an appeal against a RERA order that directed possession instead of a refund; the appellant seeks a full refund with interest, citing legal precedent.

13
Stage 12Final Ruling Order

Tribunal Order #0901126000202019-15-03-2022

The Tribunal set aside the previous order of the Regulatory Authority because it exceeded the original prayers made by the appellant, and instead directed the respondent to refund the entire deposited amount with interest at MCLR+1% per annum.

14
Stage 13Interim Order

Tribunal Order #0901126000202019-22-09-2021

The Tribunal directed the respondent to provide specific details regarding super area and carpet area as previously ordered and mandated both parties to file and exchange a list of dates, events, and relied-upon cases before the next hearing.

15
Stage 14Interim Order

Tribunal Order #0901126000202019-02-02-2021

The Tribunal noted the respondent's failure to comply with a previous directive to provide super area and carpet area details and directed both parties to file lists of dates and relied-upon judgments before the next hearing.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the previous order of the Regulatory Authority because it exceeded the original prayers made by the appellant, and instead directed the respondent to refund the entire deposited amount with interest at MCLR+1% per annum. Awarded in favor of Appellant. Awarded interest rate: MCLR+1% per annum.

Disposal Winner: AppellantInterest Rate: MCLR+1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the previous order of the Regulatory Authority because it exceeded the original prayers made by the appellant, and instead directed the respondent to refund the entire deposited amount with interest at MCLR+1% per annum.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1% per annum

Interest Period

from the date of deposit till the refund of the amount

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Azhar Ikram
  • Manish Singh

Respondent Advocate(s)

  • Shashi Kant Verma

Official RERA Tribunal Orders (4)

INTERIM_ORDEROrder ID: 0901126000202019-20-11-2021

The Tribunal heard arguments regarding an appeal against a RERA order that directed possession instead of a refund; the appellant seeks a full refund with interest, citing legal precedent.

FINAL_ORDEROrder ID: 0901126000202019-15-03-2022

The Tribunal set aside the previous order of the Regulatory Authority because it exceeded the original prayers made by the appellant, and instead directed the respondent to refund the entire deposited amount with interest at MCLR+1% per annum.

INTERIM_ORDEROrder ID: 0901126000202019-22-09-2021

The Tribunal directed the respondent to provide specific details regarding super area and carpet area as previously ordered and mandated both parties to file and exchange a list of dates, events, and relied-upon cases before the next hearing.

INTERIM_ORDEROrder ID: 0901126000202019-02-02-2021

The Tribunal noted the respondent's failure to comply with a previous directive to provide super area and carpet area details and directed both parties to file lists of dates and relied-upon judgments before the next hearing.

TathyaGrid RERA Intelligence AI

Need to research all rulings for sjp infracon limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →