Appellant / Complainant
Mithlesh Singh
Respondent
Uppal Chaddha Hi-Tech Developers Pvt. Ltd.
uppal chaddha hi-tech developers pvt. ltd.
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126000172019 by Mithlesh Singh against Uppal Chaddha Hi-Tech Developers Pvt. Ltd. before up_rera.
Further Order
The appellant withdrew the appeal to pursue execution of the previous order dated 31.10.2019 regarding plot possession; the Tribunal permitted this withdrawal and granted liberty to move an execution petition before the Regulatory Authority.
Further Order
The appeal was adjourned due to the absence of the appellant, with the matter rescheduled for further orders on 27.01.2022.
Further Order
The Tribunal adjourned the appeal to 05.01.2022 and issued a warning to the respondent's counsel regarding improper procedure for requesting adjournments via email.
Further Order
The Tribunal granted an adjournment requested by the respondent's counsel and granted the appellant a final opportunity to file a replication or rejoinder before the next hearing on 13.12.2021.
Further Order
The Tribunal granted the appellant permission to file a rejoinder affidavit within one week and scheduled the matter for further orders on 18.11.2021.
Hearing
The Tribunal granted the respondent a final opportunity to file a reply to the appeal and directed that a copy be sent to the appellant via email. The case is adjourned to 26.10.2021.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for April 13, 2021.
Hearing
The appeal is adjourned because advocates are abstaining from work due to a call by the Oudh Bar Association; the matter is rescheduled for 18.03.2021.
Hearing on Appeal
The Tribunal directed the respondent to file a reply to the grounds of appeal on both the e-portal and in physical form at least three days before the next hearing date.
Tribunal Order #0901126000172019-09-03-2022
The appellant withdrew the appeal to pursue execution of the previous order dated 31.10.2019 regarding plot possession; the Tribunal permitted this withdrawal and granted liberty to move an execution petition before the Regulatory Authority.
Tribunal Disposal & Final Award Ruling
The appellant withdrew the appeal to pursue execution of the previous order dated 31.10.2019 regarding plot possession; the Tribunal permitted this withdrawal and granted liberty to move an execution petition before the Regulatory Authority. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The appellant withdrew the appeal to pursue execution of the previous order dated 31.10.2019 regarding plot possession; the Tribunal permitted this withdrawal and granted liberty to move an execution petition before the Regulatory Authority.
Ruling Awarded To
Appellant
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Vinay Pandey
- Prasoon Kumar Anjor
Respondent Advocate(s)
- Bal Kishor Verma
- Amit Yadav
Official RERA Tribunal Orders (1)
The appellant withdrew the appeal to pursue execution of the previous order dated 31.10.2019 regarding plot possession; the Tribunal permitted this withdrawal and granted liberty to move an execution petition before the Regulatory Authority.
Need to research all rulings for uppal chaddha hi-tech developers pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.