up_reraStatus: Completed
CASE ID: 0901126000162018

Appellant / Complainant

Yatish Agarwal

VS

Respondent

Pushpanjali Constructions Private Ltd.

Developer Firm

pushpanjali constructions private ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

49 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000162018 by Yatish Agarwal against Pushpanjali Constructions Private Ltd. before up_rera.

2
Stage 120/01/2025

Final Hearing

The Tribunal allowed the appellant's application to withdraw the appeal, granting liberty to file a fresh complaint or execution before the appropriate forum as per law.

3
Stage 217/12/2024

Final Hearing

The Tribunal directed the appellant's counsel to comply with a previous order dated 30.05.2022 by bringing on record the specific amounts deposited for apartments/flats with the respondent promoter.

4
Stage 329/11/2024

Final Hearing

No text available.

5
Stage 418/10/2024

Final Hearing

The Tribunal noted that the Court Commissioner's report is expected within 24 hours and directed parties to file any objections before the next hearing. The matter is scheduled for final hearing on 29.11.2024.

6
Stage 518/09/2024

Final Hearing

The Tribunal granted the Advocate Commissioners seven days to file their final spot inspection report and directed parties to file objections within one week thereafter.

7
Stage 602/09/2024

Final Hearing

The Tribunal granted a final opportunity for the inspection of the respondent's project in Agra, scheduling it for September 7, 2024, due to previous non-cooperation by the respondent.

8
Stage 724/07/2024

Final Hearing

The Tribunal has fixed August 31, 2024, at 11:00 A.M. for the inspection of the project in Agra and directed all parties and the inspection team to be present at the site.

9
Stage 827/05/2024

Final Hearing

The Tribunal modified its previous order to replace the appointed Advocate Commissioners with Sri Siddharth Nandwani and Sri Saurabh Mishra due to potential conflicts of interest.

10
Stage 902/05/2024

Final Hearing

The Tribunal constituted an inspection team of advocates to verify the current status of the respondent's project and its OC/CC documentation, directing the appellant to bear the inspection costs.

11
Stage 1009/04/2024

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to medical reasons and rescheduled the hearing for May 2, 2024, upon the respondent's request for urgency.

12
Stage 1107/03/2024

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and rescheduled the hearing for April 9, 2024.

13
Stage 1201/03/2024

Final Hearing

The Tribunal has rescheduled the hearing of Appeal-117/2018 to 07.03.2024 following a joint request from the counsel for both parties.

14
Stage 1330/01/2024

Final Hearing

The Tribunal noted that the counsel for the appellant were on sanctioned leave and ordered the appeal to be listed for hearing on 01.03.2024.

15
Stage 1431/10/2023

Final Hearing

No text available.

16
Stage 1519/09/2023

Final Hearing

The Tribunal granted an adjournment to the appellant's counsel due to lack of preparation and rescheduled the hearing for 31.10.2023.

17
Stage 1606/09/2023

Final Hearing

The Tribunal adjourned today's proceedings due to a call by the Bar Council of Uttar Pradesh for lawyers to abstain from judicial work.

18
Stage 1725/08/2023

Final Hearing

The order records that the counsel for the appellant is on leave and notes that the respondent's counsel appeared, stating the appeal is ripe for hearing.

19
Stage 1808/08/2023

Final Hearing

The Tribunal noted that pleadings have been exchanged and the appeal is ripe for hearing; consequently, the matter is scheduled for hearing on 25.08.2023.

20
Stage 1926/05/2023

Final Hearing

No text available.

21
Stage 2025/04/2023

Hearing

The Tribunal granted a request from the appellant's counsel to reschedule the hearing of Appeal-117/2018 to 26.05.2023.

22
Stage 2127/03/2023

Hearing

The Tribunal noted the substitution of counsel for the appellant due to illness and scheduled the appeal for a hearing on 25.04.2023.

23
Stage 2228/02/2023

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the final hearing for 27.03.2023, with a strict directive that no further adjournments will be permitted.

24
Stage 2327/01/2023

Hearing

No text available.

25
Stage 2421/12/2022

Hearing

The Tribunal adjourned the appeal due to the absence of parties and scheduled the matter for hearing on 27.01.2023.

26
Stage 2530/05/2022

Re-Hearing

The Tribunal directed the respondent to file details regarding the balance amount claimed from the appellant and ordered the appellant to clarify the joinder of parties and the discrepancy in the appellants' identities compared to the original complaint.

27
Stage 2605/03/2022

Final Hearing

The Tribunal noted the appellant's concern regarding the respondent's lack of interest in the expedited proceedings and listed the matter for hearing on 05.03.2022.

28
Stage 2704/03/2022

Final Hearing

The Tribunal noted the respondent's absence and the appellant's concern regarding delays despite High Court directions to expedite, subsequently listing the matter for hearing on 05.03.2022.

29
Stage 2804/01/2022

Final Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to health reasons and rescheduled the final hearing for 21.01.2022.

30
Stage 2917/12/2021

Final Hearing

The Tribunal granted the appellant's counsel one week to file a response to documents submitted by the respondent and scheduled the next hearing for 04.01.2022.

31
Stage 3009/12/2021

Final Hearing

The Tribunal granted a request by the respondent's counsel to adjourn the matter to 17.12.2021 and directed the respondent to ensure compliance with the previous order dated 09.12.2021.

32
Stage 3120/11/2021

Final Hearing

No text available.

33
Stage 3216/11/2021

Hearing

The Tribunal granted a brief adjournment due to bereavement but issued a strict directive that the case will not be adjourned again and must proceed to final hearing on 20.11.2021, in compliance with High Court directions for an expeditious disposal.

34
Stage 3323/10/2021

Hearing

The Tribunal directed the respondent to file objections on record and ordered the appellant to submit a copy of the original RERA complaint with specific details regarding plot numbers and allottees within 10 days.

35
Stage 3417/09/2021

Hearing

The Tribunal granted the respondent one final opportunity to file a list of dates and events and scheduled the matter for hearing on 29.10.2021.

36
Stage 3519/04/2021

Arguments

No text available.

37
Stage 3623/03/2021

Hearing

The Tribunal granted the respondent a final opportunity to file a list of dates and events along with supporting judgments within 15 days and rescheduled the matter for arguments on 19.04.2021.

38
Stage 3705/02/2021

For Order

The Tribunal ruled that the appeal was filed within the prescribed time limit, thereby dismissing the need to dispose of the limitation application. The parties were directed to file relevant documents and lists of dates, with the matter adjourned to 23.03.2021.

39
Stage 3815/01/2021

Arguments

No text available.

40
Stage 3901/12/2020

Arguments

No text available.

41
Stage 40Interim Order

Tribunal Order #0901126000162018-17-12-2024

The Tribunal directed the appellant's counsel to comply with a previous order dated 30.05.2022 by bringing on record the specific amounts deposited for apartments/flats with the respondent promoter.

42
Stage 41Interim Order

Tribunal Order #0901126000162018-16-11-2021

The Tribunal granted a brief adjournment due to bereavement but issued a strict directive that the case will not be adjourned again and must proceed to final hearing on 20.11.2021, in compliance with High Court directions for an expeditious disposal.

43
Stage 42Interim Order

Tribunal Order #0901126000162018-05-02-2021

The Tribunal ruled that the appeal was filed within the prescribed time limit, thereby dismissing the need to dispose of the limitation application. The parties were directed to file relevant documents and lists of dates, with the matter adjourned to 23.03.2021.

44
Stage 43Final Ruling Order

Tribunal Order #0901126000162018-20-01-2025

The Tribunal allowed the appellant's application to withdraw the appeal, granting liberty to file a fresh complaint or execution before the appropriate forum as per law.

45
Stage 44Interim Order

Tribunal Order #0901126000162018-24-07-2024

The Tribunal has fixed August 31, 2024, at 11:00 A.M. for the inspection of the project in Agra and directed all parties and the inspection team to be present at the site.

46
Stage 45Interim Order

Tribunal Order #0901126000162018-02-05-2024

The Tribunal constituted an inspection team of advocates to verify the current status of the respondent's project and its OC/CC documentation, directing the appellant to bear the inspection costs.

47
Stage 46Interim Order

Tribunal Order #0901126000162018-30-05-2022

The Tribunal directed the respondent to file details regarding the balance amount claimed from the appellant and ordered the appellant to clarify the joinder of parties and the discrepancy in the appellants' identities compared to the original complaint.

48
Stage 47Interim Order

Tribunal Order #0901126000162018-23-10-2021

The Tribunal directed the respondent to file objections on record and ordered the appellant to submit a copy of the original RERA complaint with specific details regarding plot numbers and allottees within 10 days.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appellant's application to withdraw the appeal, granting liberty to file a fresh complaint or execution before the appropriate forum as per law. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appellant's application to withdraw the appeal, granting liberty to file a fresh complaint or execution before the appropriate forum as per law.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Azhar Ikram
  • Manish Singh

Respondent Advocate(s)

  • Abhinav Singh

Official RERA Tribunal Orders (8)

INTERIM_ORDEROrder ID: 0901126000162018-17-12-2024

The Tribunal directed the appellant's counsel to comply with a previous order dated 30.05.2022 by bringing on record the specific amounts deposited for apartments/flats with the respondent promoter.

INTERIM_ORDEROrder ID: 0901126000162018-16-11-2021

The Tribunal granted a brief adjournment due to bereavement but issued a strict directive that the case will not be adjourned again and must proceed to final hearing on 20.11.2021, in compliance with High Court directions for an expeditious disposal.

INTERIM_ORDEROrder ID: 0901126000162018-05-02-2021

The Tribunal ruled that the appeal was filed within the prescribed time limit, thereby dismissing the need to dispose of the limitation application. The parties were directed to file relevant documents and lists of dates, with the matter adjourned to 23.03.2021.

FINAL_ORDEROrder ID: 0901126000162018-20-01-2025

The Tribunal allowed the appellant's application to withdraw the appeal, granting liberty to file a fresh complaint or execution before the appropriate forum as per law.

INTERIM_ORDEROrder ID: 0901126000162018-24-07-2024

The Tribunal has fixed August 31, 2024, at 11:00 A.M. for the inspection of the project in Agra and directed all parties and the inspection team to be present at the site.

INTERIM_ORDEROrder ID: 0901126000162018-02-05-2024

The Tribunal constituted an inspection team of advocates to verify the current status of the respondent's project and its OC/CC documentation, directing the appellant to bear the inspection costs.

INTERIM_ORDEROrder ID: 0901126000162018-30-05-2022

The Tribunal directed the respondent to file details regarding the balance amount claimed from the appellant and ordered the appellant to clarify the joinder of parties and the discrepancy in the appellants' identities compared to the original complaint.

INTERIM_ORDEROrder ID: 0901126000162018-23-10-2021

The Tribunal directed the respondent to file objections on record and ordered the appellant to submit a copy of the original RERA complaint with specific details regarding plot numbers and allottees within 10 days.

TathyaGrid RERA Intelligence AI

Need to research all rulings for pushpanjali constructions private ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →