CASE ID: 0901126000102024

Appellant / Complainant

Dharmender Rana

VS

Respondent

U.P. Awas Evam Vikas Parishad

Disputed Amount

32,53,304

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestMaintenance & Utility DisputesNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

13 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000102024 by Dharmender Rana against U.P. Awas Evam Vikas Parishad before up_rera.

Delay in PossessionDelay Compensation / InterestMaintenance & Utility DisputesNon-Compliance & Execution
2
Stage 113/02/2025

For Order

The Tribunal set aside the Execution Court's order rejecting the execution petition, restored the execution proceedings, and directed the Executing Authority to recalculate the interest due at MCLR+1% until the issuance of OC/CC (28.02.2019).

3
Stage 213/01/2025

For Order

No text available.

4
Stage 302/09/2024

Delay condonation

The Tribunal heard arguments regarding the delay condonation application and the appeal itself, subsequently reserving judgment.

5
Stage 431/07/2024

Delay condonation

No text available.

6
Stage 508/07/2024

Delay condonation

The Tribunal granted the appellant three days to file a High Court order and allowed the respondent one week to file a response once that order is uploaded, scheduling the next hearing for July 31, 2024.

7
Stage 627/05/2024

Delay condonation

The Tribunal adjourned the proceedings of the defective appeal due to the respondent's counsel being unavailable in the High Court and rescheduled the matter for hearing on 08.07.2024.

8
Stage 706/05/2024

Delay condonation

The Tribunal granted the applicant seven days to file a better affidavit explaining the delay in filing the appeal and scheduled the matter for hearing on May 27, 2024.

9
Stage 805/04/2024

Delay condonation

The Tribunal granted the respondent two days to file objections and directed the appellant to file a reply within one week of receiving said objections, scheduling the next hearing for May 6, 2024.

10
Stage 901/03/2024

Defect Removal

The Tribunal granted the respondent a 10-day extension to file objections to the application for condonation of delay and grounds of appeal, with the matter scheduled for hearing on 05.04.2024.

11
Stage 1025/01/2024

Defect Removal

The Tribunal disposed of an application for exemption from filing a certified copy by directing the applicant to file it within 10 days and granted the respondent 10 days to file objections.

12
Stage 11Final Ruling Order

Tribunal Order #0901126000102024-13-02-2025

The Tribunal set aside the Execution Court's order rejecting the execution petition, restored the execution proceedings, and directed the Executing Authority to recalculate the interest due at MCLR+1% until the issuance of OC/CC (28.02.2019).

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Execution Court's order rejecting the execution petition, restored the execution proceedings, and directed the Executing Authority to recalculate the interest due at MCLR+1% until the issuance of OC/CC (28.02.2019). Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.

Disposal Winner: AppellantInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Execution Court's order rejecting the execution petition, restored the execution proceedings, and directed the Executing Authority to recalculate the interest due at MCLR+1% until the issuance of OC/CC (28.02.2019).

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1%

Interest Period

from the date of default i.e. 24.07.2015 till the issuance of OC/CC or till the handing over of the possession, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(d)Section 19(6)Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • In Person

Respondent Advocate(s)

  • Anurag Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126000102024-13-02-2025

The Tribunal set aside the Execution Court's order rejecting the execution petition, restored the execution proceedings, and directed the Executing Authority to recalculate the interest due at MCLR+1% until the issuance of OC/CC (28.02.2019).