Appellant / Complainant
Naresh Kumar Gupta
Respondent
Greater Noida Industrial Development Authority
₹12,49,936
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126000072018 by Naresh Kumar Gupta against Greater Noida Industrial Development Authority before up_rera.
for delivery of Judgment/Order
The Tribunal dismissed the appeal, ruling that the project was completed and more than 80% of lease deeds were executed prior to the enactment of the RERA Act 2016, meaning it did not qualify as an 'ongoing project' and fell outside the purview of the Act.
Hearing
The court heard arguments from both the appellant and respondent and reserved the judgment for a later date.
Further Hearing
The matter was adjourned upon a joint request from both parties and is scheduled for further hearing on 25.03.2021.
Tribunal Order #0901126000072018-21-03-2022
The Tribunal dismissed the appeal, ruling that the project was completed and more than 80% of lease deeds were executed prior to the enactment of the RERA Act 2016, meaning it did not qualify as an 'ongoing project' and fell outside the purview of the Act.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal, ruling that the project was completed and more than 80% of lease deeds were executed prior to the enactment of the RERA Act 2016, meaning it did not qualify as an 'ongoing project' and fell outside the purview of the Act. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal, ruling that the project was completed and more than 80% of lease deeds were executed prior to the enactment of the RERA Act 2016, meaning it did not qualify as an 'ongoing project' and fell outside the purview of the Act.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Azhar Ikram
- Manish Singh
Respondent Advocate(s)
- Rajesh Chadha
Official RERA Tribunal Orders (1)
The Tribunal dismissed the appeal, ruling that the project was completed and more than 80% of lease deeds were executed prior to the enactment of the RERA Act 2016, meaning it did not qualify as an 'ongoing project' and fell outside the purview of the Act.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.