Appellant / Complainant
Lucknow Development Authority
Respondent
Sneh Lata Verma
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126000062019 by Lucknow Development Authority against Sneh Lata Verma before up_rera.
for delivery of Judgment/Order
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority against Sneh Lata Verma via an order passed on separate sheets.
Final Hearing
The Tribunal ruled that the appellant is not required to deposit further amounts under Section 43(5) as the principal amount has already been recovered and paid; however, judgment was reserved following arguments regarding the respondent's demand for habitable possession and interest for delay.
Final Hearing
The Tribunal adjourned the matter to 20.11.2021 for hearing alongside a cross-appeal and directed the parties to be prepared for final hearing on that date.
Hearing
The Tribunal ordered the case to be listed alongside Appeal no. 179/2019 on 15.11.2021.
Compliance of section 43(5)
The Tribunal granted the applicant one week's time to submit an offer of possession and scheduled the case for a joint hearing with Appeal No. 179/2019 on 01.10.2021.
Compliance of section 43(5)
The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the case for April 8, 2021.
Hearing
The Tribunal directed the applicant to ensure complete compliance with Section 43(5) of the Act and submit a CA certificate detailing the calculations. It also established a timeline for filing objections regarding the condonation of delay and grounds of appeal.
Hearing
The Tribunal ordered the case to be listed along with Appeal No. 179 of 2019 on February 23, 2021.
Tribunal Order #0901126000062019-23-02-2021
The Tribunal directed the applicant to ensure complete compliance with Section 43(5) of the Act and submit a CA certificate detailing the calculations. It also established a timeline for filing objections regarding the condonation of delay and grounds of appeal.
Tribunal Order #0901126000062019-15-03-2022
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority against Sneh Lata Verma via an order passed on separate sheets.
Tribunal Order #0901126000062019-20-11-2021
The Tribunal ruled that the appellant is not required to deposit further amounts under Section 43(5) as the principal amount has already been recovered and paid; however, judgment was reserved following arguments regarding the respondent's demand for habitable possession and interest for delay.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority against Sneh Lata Verma via an order passed on separate sheets. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority against Sneh Lata Verma via an order passed on separate sheets.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Abhinav Singh
Respondent Advocate(s)
- Mohd Zafar Khan
Official RERA Tribunal Orders (3)
The Tribunal directed the applicant to ensure complete compliance with Section 43(5) of the Act and submit a CA certificate detailing the calculations. It also established a timeline for filing objections regarding the condonation of delay and grounds of appeal.
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Lucknow Development Authority against Sneh Lata Verma via an order passed on separate sheets.
The Tribunal ruled that the appellant is not required to deposit further amounts under Section 43(5) as the principal amount has already been recovered and paid; however, judgment was reserved following arguments regarding the respondent's demand for habitable possession and interest for delay.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.