up_reraStatus: Completed
CASE ID: 0901126000022021

Appellant / Complainant

Gopal Bindal

VS

Respondent

Gardenia Aims Developers Pvt Ltd

Developer Firm

gardenia aims developers pvt ltd

Disputed Amount

31,63,650

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferStructural Defects & QualityPromotional MisrepresentationMaintenance & Utility Disputes

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

33 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126000022021 by Gopal Bindal against Gardenia Aims Developers Pvt Ltd before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferStructural Defects & QualityPromotional MisrepresentationMaintenance & Utility Disputes
2
Stage 129/05/2024

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal partly allowed the appeals, directing the respondent to provide legal possession and execute conveyance deeds, pay interest for the delay period up until fit-out possession, and fulfill all promised amenities as per the project brochure.

3
Stage 222/03/2024

For Order

The Tribunal heard arguments regarding an appeal against a Regulatory Authority's order concerning possession and interest claims, but has reserved its judgment for a later date.

4
Stage 321/02/2024

For Order

The Tribunal rescheduled the appeal for hearing on March 22, 2024, noting that while the appellant's counsel was present, the respondent's counsel was absent.

5
Stage 412/01/2024

For Order

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the matter for further orders on February 21, 2024.

6
Stage 511/10/2023

For Order

No text available.

7
Stage 625/08/2023

For Order

The Tribunal granted a request for adjournment from both parties and rescheduled the hearing for October 11, 2023.

8
Stage 707/07/2023

For Order

The Tribunal granted an adjournment requested by the respondent's counsel due to personal reasons and rescheduled the appeal for hearing on 25-08-2023.

9
Stage 827/04/2023

For Order

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal for orders on July 7, 2023.

10
Stage 920/03/2023

For Order

No text available.

11
Stage 1009/02/2023

For Order

No text available.

12
Stage 1105/01/2023

For Order

No text available.

13
Stage 1201/12/2022

For Order

The Tribunal granted a joint request from the counsels for both parties to adjourn the matter and rescheduled the case for further orders on 05.01.2023.

14
Stage 1309/11/2022

For Order

The Tribunal granted an adjournment requested by the appellant's counsel, subject to a cost of Rs. 1000/-, split equally between the Tribunal's fund and the respondent's counsel.

15
Stage 1410/10/2022

Further Order

The Tribunal adjourned the appeal to 09.11.2022 following a joint request from the counsels for both parties.

16
Stage 1528/09/2022

Further Order

The Tribunal granted a request from both parties to adjourn the matter and rescheduled the appeal for hearing on 10.10.2022.

17
Stage 1626/08/2022

Further Order

The Tribunal adjourned the appeal on 26.08.2022 and scheduled it for further orders on 28.09.2022.

18
Stage 1718/07/2022

Further Order

The Tribunal granted an adjournment requested by the appellant and rescheduled the hearing for August 26, 2022.

19
Stage 1810/05/2022

Further Order

The Tribunal directed the respondent's counsel to file a list of dates, events, and relied-upon cases within 15 days and adjourned the matter to 18.07.2022.

20
Stage 1905/04/2022

Further Order

The Tribunal directed both parties to exchange lists of dates, events, and relied-upon cases at least seven days before the next hearing and scheduled the matter for 10.05.2022.

21
Stage 2007/03/2022

Further Order

The Tribunal directed the appellant to file a replication/rejoinder if desired and ordered both parties to submit lists of dates, events, and relied-upon judgments before the next hearing on 05.04.2022.

22
Stage 2104/01/2022

Further Order

The Tribunal directed the appellant to file a rejoinder/replication against the respondent's reply and scheduled the next hearing for 24.01.2022.

23
Stage 2229/11/2021

For Order

The Tribunal closed the respondent's opportunity to file a reply to the grounds of appeal due to non-appearance and failure to file a response despite previous opportunities, and scheduled the next hearing for 04.01.2022.

24
Stage 2308/11/2021

Further Order

The Tribunal allowed an application for adjournment and rescheduled the case to 29.11.2021.

25
Stage 2420/09/2021

Hearing

The Tribunal granted the respondent a final opportunity to file a reply to the appeal and directed them to serve a copy to the appellant before the next hearing on 08.11.2021.

26
Stage 2520/04/2021

Hearing

No text available.

27
Stage 2619/03/2021

Hearing

No text available.

28
Stage 2702/03/2021

Hearing on Appeal

The appeal was adjourned due to lawyers abstaining from work in support of a call by the Oudh Bar Association; the matter is rescheduled for hearing on 19.03.2021.

29
Stage 2802/02/2021

Hearing on Appeal

The Tribunal directed the respondent to file their vakalatnama within one week and submit a reply to the grounds of appeal within 15 days, with the matter listed for hearing on 02.03.2021.

30
Stage 2912/01/2021

Hearing on Appeal

No text available.

31
Stage 30Final Ruling Order

Tribunal Order #0901126000022021-29-05-2024

The U.P. Real Estate Appellate Tribunal partly allowed the appeals, directing the respondent to provide legal possession and execute conveyance deeds, pay interest for the delay period up until fit-out possession, and fulfill all promised amenities as per the project brochure.

32
Stage 31Interim Order

Tribunal Order #0901126000022021-09-11-2022

The Tribunal granted an adjournment requested by the appellant's counsel, subject to a cost of Rs. 1000/-, split equally between the Tribunal's fund and the respondent's counsel.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal partly allowed the appeals, directing the respondent to provide legal possession and execute conveyance deeds, pay interest for the delay period up until fit-out possession, and fulfill all promised amenities as per the project brochure. Awarded in favor of Appellant. Awarded interest rate: MCLR+1% per annum.

Disposal Winner: AppellantInterest Rate: MCLR+1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal partly allowed the appeals, directing the respondent to provide legal possession and execute conveyance deeds, pay interest for the delay period up until fit-out possession, and fulfill all promised amenities as per the project brochure.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1% per annum

Interest Period

from promised date of possession as per agreement till providing fit out possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 14(3)Section 12Section 11(4)(d)Section 19(6)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav

Respondent Advocate(s)

  • Shuchita Singh
  • Ankit Yadav

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126000022021-29-05-2024

The U.P. Real Estate Appellate Tribunal partly allowed the appeals, directing the respondent to provide legal possession and execute conveyance deeds, pay interest for the delay period up until fit-out possession, and fulfill all promised amenities as per the project brochure.

INTERIM_ORDEROrder ID: 0901126000022021-09-11-2022

The Tribunal granted an adjournment requested by the appellant's counsel, subject to a cost of Rs. 1000/-, split equally between the Tribunal's fund and the respondent's counsel.

TathyaGrid RERA Intelligence AI